Domestic Extension Trade Sequence: From Groundworks to Decoration — Who Does What, When and in What Order

Quick Answer: A domestic extension typically runs across 8–12 trade stages from groundworks to decoration. Each stage has specific handover conditions that must be met before the next trade can start. CDM 2015 applies where there are 2 or more contractors. Building Control inspections are required at key stages (foundations, oversite, drains, structure, insulation, and final completion).

Summary

The trade sequence for a domestic single-storey or two-storey extension is the most common multi-trade construction project in the UK. Getting the sequence wrong costs real money: a plasterer arriving before first-fix electrics and plumbing is complete, or a floor layer turning up before the screed has cured, creates abortive work, damaged materials, and rescheduling delays that can run to weeks.

This guide presents the canonical sequence, dependency rules, and Building Control inspection trigger points. It is designed to be a working reference for the lead contractor, project manager, or tradesperson quoting multi-trade work. Not every project requires every stage — a garage conversion skips foundations, a loft conversion skips drainage. Use the stages relevant to your job and cross-reference linked articles for depth on individual trades.

CDM 2015 (Construction Design and Management Regulations) applies to any domestic project with more than one contractor involved (including subcontractors). The client must be given a F10 pre-construction notification if the project exceeds 500 person-days or 30 working days with >20 workers simultaneously. Even below these thresholds, CDM 2015 still imposes duties — a Construction Phase Plan must be in place before work starts.

Key Facts

Quick Reference Table

Spending too long on quotes? squote turns a 2-minute voice recording into a professional quote.

Try squote free →
Stage Work Lead Trade Building Control Inspection
0 Pre-start (planning, BR application, CDM, party wall, services) Principal Contractor Notify work start (building notice)
1 Demolition and strip-out Demolition / builder None (asbestos survey if pre-2000)
2 Groundworks and foundations Groundworker Foundations (before pour), drains (before backfill), oversite/DPM
3 Superstructure: walls and roof structure Bricklayer / carpenter Structural beam (if specified)
4 Roofing and weathertight Roofer None
5 First fix: services Electrician / plumber / heating None (visual at insulation stage)
6 Insulation and airtightness Insulation installer Insulation before covering
7 Plastering and dry-lining Plasterer None
8 Joinery: first and second fix Carpenter / joiner None
9 Second fix: services Electrician / plumber Electrical (Part P certificate)
10 Tiling and floor finishes Tiler / floor layer None
11 Decoration Decorator None
12 External works and landscaping Landscaper / groundworker None
13 Final sign-off and handover Principal Contractor Completion certificate

Detailed Guidance

The Trade Sequence

Stage 0 — Pre-Start (Before Any Groundworks)

Who: Principal Contractor, client, planning authority, building control, utility companies.

Tasks:

Handover to Stage 1: All pre-conditions confirmed. Building Control application registered. CDM plan in place.


Stage 1 — Demolition and Strip-Out

Who: Demolition contractor, builder, groundworker.

Tasks:

Dependencies: Planning consent confirmed. Asbestos survey complete. Skip in position.

Building Control inspection: Not required at this stage, but notify BCO that work has started (if building notice route).


Stage 2 — Groundworks and Foundations

Who: Groundworker / groundworks contractor.

Tasks:

Dependencies: Foundation inspection signed off. Drain test passed. Concrete cured before loading.

See also: strip foundation design, concrete mix designs groundworks, soil classification, underground drainage


Stage 3 — Superstructure: Walls and Roof Structure

Who: Bricklayer / mason, carpenter/joiner, structural steel installer.

Tasks:

Dependencies: Foundation slab cured (minimum 7–14 days). Lintels and beams designed, certified, and on site.

See also: structural steel, party wall, roof trusses, pitched roof structure, leadwork


Stage 4 — Roofing and Weathertight

Who: Roofer, lead worker.

Tasks:

Critical milestone: Building is WEATHERTIGHT when this stage is complete. First-fix trades can start.

See also: roof tile types, leadwork, grp fibreglass flat roofing, gutter downpipe sizing


Stage 5 — First Fix: Services

Who: Electrician, plumber, heating engineer. All work concurrently in sequence below.

Order within stage:

  1. Electrician (first fix): Run all cabling — ring main, lighting, spur circuits, data. Install back boxes. Mark consumer unit position. Install any distribution boards. Do NOT terminate at this stage.
  2. Plumber (first fix): Run all pipework — hot and cold water supply, heating flow and return, underfloor heating manifolds (if wet UFH). Run any waste pipes to drain connections. Do NOT fit valves, taps, radiators, or sanitaryware at this stage.
  3. Heating engineer: Install boiler (if new), cylinder, manifolds, and under-floor heating circuits. First-fix pipework including boiler flue position confirmed before wall is plastered.

Key rule: All pipework and cabling must be complete and pressure-tested / continuity-tested before boarding or plastering. Any service routes that will be inaccessible after plastering must be confirmed as leak-free.

Building Control notification: Part P notifiable electrical work must be carried out by a competent person scheme member or notified to Building Control.

See also: first fix second fix, rewire guide, hot water systems, underfloor heating


Stage 6 — Insulation and Airtightness

Who: Insulation installer, builder.

Tasks:

See also: cavity wall, warm roof cold roof, floor insulation, warm flat roof detail


Stage 7 — Plastering and Dry-Lining

Who: Plasterer, dryliner.

Tasks:

Dependencies: First fix complete, checked, and approved. All service routes confirmed. No open pipe joints or cable terminations missing.

See also: skim coat, plasterboard types, metal stud partition installation


Stage 8 — Joinery: First and Second Fix Carpentry

Who: Carpenter/joiner.

Tasks (first fix — some done pre-plaster):

Tasks (second fix — post-plaster):

Dependencies: Plaster dry (minimum 4 weeks). Decorating done before skirtings in some programmes, or skirtings done before decoration (trade preference varies).

See also: skirting architrave, door frames, first fix second fix


Stage 9 — Second Fix: Services

Who: Electrician, plumber, heating engineer.

Tasks:

See also: testing commissioning, central heating commissioning, radiator balancing


Stage 10 — Tiling and Floor Finishes

Who: Tiler, floor layer.

Tasks:

Dependencies: Plaster fully dry, second fix services complete, heating commissioned (so UFH can be tested before floor laid).

See also: large format tiles, screed types, lvt installation, wetroom construction


Stage 11 — Decoration

Who: Decorator.

Tasks:

Dependencies: Plaster fully dry. Second fix complete. Skirtings and architraves fitted.

See also: interior emulsion, lining paper before decorating


Stage 12 — External Works and Landscaping

Who: Groundworker, landscaper, paving contractor.

Tasks:

See also: patio laying, suds regulations driveways, drainage landscaping


Stage 13 — Final Sign-Off and Handover

Who: Principal Contractor, Building Control.

Tasks:

Documents to client at handover:

Frequently Asked Questions

In what order do electrician and plumber first fix happen?

Either can go first — there is no absolute rule. In practice, electricians often go first because their cabling is more flexible to route around pipework, whereas pipe routes are less easily diverted. On a well-managed project, both trades work concurrently in different zones. The critical rule: ALL first-fix services must be complete before plastering starts.

When does Building Control need to be notified?

Under the building notice route: at start of work, at foundation excavation, before oversite is covered, before drains are backfilled, at structural frame stage (if applicable), and at final completion. Under full plans approval, the approved plan sets out inspection stages. Always confirm with your local BCO — they vary in their inspection frequency.

Can decoration start before second fix is complete?

Yes — painting can start on walls and ceilings while second fix is underway, as long as sockets, switches, and luminaires are not yet in place. In practice, most programmes decorate after second fix to avoid damage to painted surfaces by the trades.

Who is the Principal Contractor under CDM 2015?

The Principal Contractor (PC) is the contractor in overall control of the construction phase. On a domestic extension where one main contractor manages multiple subcontractors, that main contractor is the PC. The PC must: prepare and maintain the Construction Phase Plan, manage site safety, co-ordinate between trades, and keep a health and safety file.

How long does a typical single-storey extension take?

From groundworks start to handover: 10–18 weeks for a straightforward 20–40m² single-storey extension, depending on size, complexity, and number of trades. The longest variable is plaster drying time and screed curing — these are fixed physical constraints that cannot be accelerated without compromising quality.

Regulations & Standards