First Fix vs Second Fix: What's Included in Each Stage?

Quick Answer: First fix covers all the structural and hidden infrastructure work that happens before plastering — stud walls, pipe runs, cable routes, joists, and door linings. Second fix is everything that goes on after plastering — skirting, doors, sockets, sanitaryware, radiators, and light fittings. The split exists because trades need two visits to each property, and plastering acts as the dividing line between rough-in and finishing work.

Summary

First fix and second fix are the two main internal work stages in UK construction, separated by the plastering milestone. First fix takes a building from bare structure to plaster-ready by installing all the hidden elements — timber framing, pipework, cable runs, insulation, and ventilation ducting. Once first fix is complete and signed off (including a building control pre-plaster inspection), the plasterer boards and skims the walls and ceilings. Second fix then covers every visible, finished element: hanging doors, fitting skirting and architrave, connecting sockets and switches, installing sanitaryware, hanging radiators, and commissioning all services. Getting the sequencing right between trades at both stages is one of the most common sources of delay on domestic projects, particularly at the handover from first fix to plastering.

Key Facts

First Fix vs Second Fix Overview

Spending too long on quotes? squote turns a 2-minute voice recording into a professional quote.

Try squote free →
Trade First Fix (Before Plastering) Second Fix (After Plastering)
Carpentry Stud walls, door linings, floor joists, roof trusses/cut roofs, noggins, boxing in, window boards, staircase carcass Skirting boards, architrave, door hanging, kitchen fitting, built-in wardrobes, handrails, shelving
Plumbing Hot and cold water pipe runs, waste pipes, soil stack, cylinder position, bath/shower waste positions Fit sanitaryware (WC, basin, bath, shower), connect taps, fit traps, connect appliances, test and commission
Electrical Cable runs through joists/studs, back boxes for sockets and switches, consumer unit position, ceiling rose points, smoke detector cabling Fit faceplates (sockets, switches), hang light fittings, fit consumer unit cover, connect extractor fans, test and certify (EICR)
Heating Central heating flow and return pipework, radiator tails to position, gas supply pipe, boiler flue hole, underfloor heating pipe loops Hang radiators, fit TRVs, install boiler, connect programmer/thermostat, power flush, fill and commission
Ventilation MVHR or extract ducting routes, duct drops to room positions Fit grilles and valves, connect units, commission and balance airflows

Detailed Guidance

What's included in first fix carpentry?

First fix carpentry is the structural and framing stage. It covers all the timber work that forms the skeleton of the internal spaces before the plasterer arrives:

What's included in second fix carpentry?

Second fix carpentry is the finishing stage — the visible joinery that gives rooms their completed appearance:

What's included in first fix plumbing?

First fix plumbing installs all the hidden pipework that will later be plastered or boarded over:

What's included in second fix plumbing?

Second fix plumbing connects all the visible fittings and appliances to the pipework installed at first fix:

What's included in first fix electrical?

First fix electrical installs the hidden wiring infrastructure before plastering:

What's included in second fix electrical?

Second fix electrical connects the visible components and certifies the installation:

What's the correct sequencing between trades?

Getting the sequence right is the single most important factor in avoiding delays on a domestic project. The standard sequence for a new build or major extension is:

Phase 1 — First Fix (all trades, before plastering)

  1. Carpenter first fix — Stud walls, door linings, floor joists/decking, noggins. This must happen first because plumbers and electricians need the framing in place to route their services
  2. Plumber first fix — Hot and cold pipe runs, waste pipes, soil stack, heating pipework, cylinder position. Plumber needs stud walls up to know exact positions. Requires noggins in place for pipe clips and valve positions
  3. Electrician first fix — Cable runs through joists and studs, back boxes, consumer unit. Electrician works around plumber's pipework to maintain safe separation distances. Runs cables through noggins and joists after carpenter has drilled or notched them
  4. Heating engineer first fix — Often the same person as the plumber. Central heating pipe runs, gas supply, boiler flue hole, underfloor heating loops (if applicable). Must coordinate with the electrician for boiler and thermostat wiring
  5. Ventilation first fix — MVHR or extract ducting installed. Coordinated with the electrician for fan power supplies
  6. Insulation — Fitted between and around all services once first fix is complete
  7. Building control pre-plaster inspection — Inspector checks all hidden first fix work, insulation, fire-stopping, and structural elements before they are concealed

Critical coordination points at first fix:

Phase 2 — Wet trades

  1. Plasterboarder — Boards walls and ceilings, covering all first fix work
  2. Plasterer — Skim coat over plasterboard. Walls need approximately 3-5 days to dry before second fix begins (longer in cold or damp conditions)

Phase 3 — Second Fix (all trades, after plastering)

  1. Electrician second fix — Faceplates, light fittings, consumer unit completion. Usually goes first in second fix because sockets are needed for other trades' power tools
  2. Plumber second fix — Sanitaryware, taps, appliance connections. Needs finished walls for accurate fitting. Must coordinate with tiler in wet rooms
  3. Heating engineer second fix — Hang radiators, fit boiler, connect controls, power flush, fill, and commission. Radiators go on after decorating is complete (or protected during decorating)
  4. Carpenter second fix — Skirting, architrave, door hanging. Goes after plumber and electrician so that skirting can be scribed around pipework and faceplates. Kitchen fitting is a separate phase requiring coordinated plumbing and electrical
  5. Tiler — Coordinated with plumber for bathroom/kitchen sequencing. Usually after sanitaryware is positioned but before final plumbing connections
  6. Decorator — After all second fix carpentry is complete. Radiators removed or protected

Common sequencing mistakes:

How do I price first fix and second fix separately?

Pricing first fix and second fix as separate line items is standard practice for new builds, extensions, and major renovations. Here is how to approach it:

Day rates (2026 guide figures):

Trade First Fix Day Rate Second Fix Day Rate
Carpenter £250-£350/day £280-£400/day
Plumber £250-£375/day £275-£400/day
Electrician £250-£350/day £275-£375/day
Heating engineer £250-£375/day £275-£400/day

Second fix day rates tend to be slightly higher because the work requires more precision, is visible in the finished building, and any mistakes are immediately obvious.

Pricing structure options:

  1. Day rate — Most common for first fix carpentry and plumbing. Straightforward but gives the customer less cost certainty
  2. Price per unit — Common for second fix items. For example, door hanging (£40-£80 per door), skirting (£3-£6 per linear metre fitted), radiator hanging (£80-£150 per radiator)
  3. Fixed price per stage — Quote a lump sum for "first fix carpentry" and a separate lump sum for "second fix carpentry". Requires an accurate specification up front
  4. Measured rates — Used on larger projects. Rates per metre run of pipework, per socket installed, per metre of skirting, etc.

Tips for accurate pricing:

Frequently Asked Questions

Can first fix trades work at the same time?

Yes, and on larger projects they usually do. Carpenters, plumbers, and electricians can overlap in different rooms or zones, but there is a natural dependency — the carpenter's stud walls must be up before the plumber and electrician can route services through them. On a small extension, trades typically follow sequentially. On a new-build house, they can work in parallel across different floors or rooms.

How long does first fix take on a typical extension?

For a single-storey rear extension (roughly 20-30m2), first fix carpentry takes 3-5 days, plumbing 2-3 days, and electrical 2-3 days. These overlap partially, so the total first fix period is typically 5-8 working days. Allow an additional 1-2 days for building control inspection and any remedial work before the plasterer starts.

Does building control need to inspect first fix?

Yes. Building control will normally carry out a pre-plaster inspection (sometimes called a first fix inspection) to check all hidden work before it is covered by plasterboard and plaster. This includes structural timber, insulation, fire-stopping, pipework, and electrical runs. You must give building control notice before covering up this work — failing to do so can result in them requiring you to open up finished walls for inspection, which is costly and disruptive.

What happens if I skip the pre-plaster inspection?

Building control may refuse to issue a completion certificate. In the worst case, they can require you to remove plasterboard to expose hidden work for inspection. This is expensive and time-consuming. Always book the pre-plaster inspection in advance and do not allow the plasterboarder to start until it has been passed.

Is underfloor heating first fix or second fix?

Underfloor heating pipe loops are first fix — they are laid before the screed is poured. The manifold, pump, mixing valve, and controls connection is second fix. The screed itself is a wet trade that sits between first and second fix, similar to plastering for walls.

Who is responsible for fire-stopping at first fix?

Every trade is responsible for fire-stopping their own penetrations through fire-rated walls and floors. In practice, the main contractor or site manager should coordinate this and carry out a final check before the pre-plaster inspection. Intumescent collars around plastic pipes, fire-rated sealant around cable penetrations, and cavity barriers in timber frame are all first fix items.

Regulations & Standards