Electrical Testing & EICR: Periodic Inspection, Test Schedule & Documentation

Quick Answer: An Electrical Installation Condition Report (EICR) is a formal assessment of an existing electrical installation. It is legally required for rental properties every 5 years (or at change of tenancy), and is strongly recommended every 10 years for owner-occupied homes. New installations require an Electrical Installation Certificate (EIC) at completion. All testing must follow BS 7671:2018+A2:2022 Appendix 6 and the IET Guidance Note 3.

Summary

Electrical testing is not just a compliance exercise — it's the only way to confirm that a completed or existing installation is safe to energise and use. In the UK, every new electrical installation must be tested and documented before it is put into service. Existing installations must be periodically inspected to catch deterioration, damage, modification errors, and outdated wiring before they cause fire or shock.

For tradespeople, understanding what testing involves matters for several reasons: you need to know when your work on an installation requires a test certificate, what tests you or a qualified electrician will perform, and how to read an EICR when assessing whether an installation is safe to work on.

The EICR replaced the Periodic Inspection Report (PIR) as the standard document format. Its coded grading system (C1, C2, C3, FI) is well known but frequently misapplied — understanding what each code means practically is important for advising customers.

Key Facts

Quick Reference Table

Quoting an electrical job? Describe the work and squote handles the pricing.

Try squote free →
Test Purpose Pass Threshold Tool Required
Continuity of ring final Verify ring integrity Low, consistent resistance across all sockets Low-resistance ohmmeter
Continuity of CPCs Verify earth path ≤ R1+R2 from Ze table Low-resistance ohmmeter
Insulation resistance No conductor leakage ≥1MΩ at 500V DC (≥0.5MΩ for existing with equipment connected) Insulation resistance tester
Polarity Correct L/N/E connections No reverse polarity, switches on live Visual + continuity
Earth fault loop impedance (Zs) Fault current disconnects in time Per BS 7671 Table 41.2 (e.g., ≤1.44Ω for B32) Loop impedance tester
RCD operation RCD trips within time limit ≤300ms at rated current (I△n); ≤40ms at 5×I△n RCD tester
Prospective fault current (Pfc) Within equipment rating Typically <6kA domestic; rated equipment Loop impedance tester

Detailed Guidance

Test Sequence — Why Order Matters

BS 7671 specifies tests must be carried out in sequence. The reason is safety and logic:

  1. Continuity tests first — with installation de-energised, verify all CPCs are continuous before you rely on them. A broken CPC with insulation failure could mean shock risk when energised.
  2. Insulation resistance — with all MCBs off and equipment disconnected, apply 500V DC between each conductor pair. A reading below 1MΩ indicates deterioration, damage, or contaminated cable/connections.
  3. Polarity — verify that the phase conductor is connected to phase terminals throughout, that switches interrupt the phase, and that sockets are correctly polarised. Carried out de-energised using a continuity tester from the CU outwards.
  4. Earth fault loop impedance — now energised, measure the complete fault loop at each socket and fixed connection point. Compare to BS 7671 Table 41.2 maximum values for the MCB type and rating.
  5. RCD testing — using an RCD tester, verify that each RCD trips within the time limits at rated tripping current, half rated current, and five times rated current.

EICR Coding — Practical Application

C1 (Danger present) examples:

C2 (Potentially dangerous) examples:

C3 (Improvement recommended) examples:

FI (Further investigation) examples:

Insulation Resistance — Common Issues

Minimum acceptable: 1MΩ per circuit at 500V DC for new or rewired installations. For older existing installations with equipment connected (where full disconnection is impractical), ≥0.5MΩ is the minimum but indicates investigation is warranted.

Failures are commonly caused by:

If insulation resistance is low, disconnect individual circuits and re-test to isolate the problem circuit. Within each circuit, disconnect outlets one by one to locate the specific fault.

Earth Fault Loop Impedance — Reading the Results

Zs must not exceed the values in BS 7671 Table 41.2. Key values to memorise:

MCB Type Rating Max Zs (0.4s disconnection)
B-type 6A 7.67Ω
B-type 16A 2.87Ω
B-type 20A 2.30Ω
B-type 32A 1.44Ω
B-type 40A 1.15Ω
C-type 32A 0.72Ω

Measured Zs = Ze (external, from supply) + R1+R2 (internal circuit resistance). If Zs is marginal, check:

RCD Testing

Every 30mA RCD must be tested:

Test in both positive and negative half-cycles (the tester does this automatically). Many modern RCBOs will show different trip times on positive vs negative half-cycles — both must be within limits.

The test button on the RCD is a functional check only — it does not verify the actual trip current or time.

Frequently Asked Questions

Can a gas engineer or kitchen fitter issue an EICR?

No. EICRs must only be issued by a qualified electrician who is competent to undertake inspection and testing. They should hold a recognised qualification (City & Guilds 2391-52 or equivalent) and be registered with a competent person scheme such as NICEIC or NAPIT. If you are a non-electrician tradesperson who notices obvious safety concerns during your work (live parts exposed, scorch marks), you should bring them to the customer's attention and recommend they get an electrical assessment.

What's the difference between an EIC and an EICR?

An EIC is issued at the end of new installation work — it's the "pass" certificate confirming the new installation has been tested and complies with BS 7671 at the time of completion. An EICR is issued after inspecting an existing installation and may identify C1/C2/C3 deficiencies. An EICR that is "Unsatisfactory" (has C1 or C2 codes) does not condemn the installation immediately but requires remediation.

How long is an EICR valid?

There is no expiry date on an EICR, but the report specifies the recommended interval for the next inspection. For private rental, the legal maximum is 5 years. The inspector may recommend a shorter interval based on installation condition.

Regulations & Standards