Bathroom Refit Trade Sequence: Strip-Out, First Fix, Wet Areas and Decoration — Trade Coordination and Handovers

Quick Answer: A full bathroom refit runs across 6–8 trade stages, from strip-out to decoration. The critical path is: strip-out → structural repairs → first-fix plumbing and electrics → waterproofing → tiling → second-fix plumbing → second-fix electrics → decoration. Building Regulations Part P applies to electrical work in bathrooms; Part G applies to unvented hot water; bathroom zones (BS 7671 Section 701) govern electrical installation in wet areas.

Summary

A bathroom refit is the most common multi-trade domestic job in the UK. It looks straightforward but regularly goes wrong because trades are sequenced incorrectly or handover conditions between stages are not respected. The most common failure points are: tiling before waterproofing (leading to leaks into the floor or wall below), second-fix plumbing before tiling is complete (creating difficult cuts around fixed valves), and electrical second-fix before floor is finished (creating trip hazards for finishing trades).

This guide presents the canonical sequence for a full bathroom refit — replacing all sanitaryware, retiling, and upgrading the suite. Partial refits (suite swap only, retile only) can follow the relevant stages. En-suite installations in a new room follow the domestic extension trade sequence first (see domestic extension trade sequence) and then apply the bathroom sequence from Stage 3.

CDM 2015 applies where two or more contractors are involved. On a domestic bathroom refit where a plumber and an electrician are both engaged alongside the main contractor or client, CDM duties arise. In practice, most domestic bathroom jobs are managed by the main contractor or plumber as de facto Principal Contractor — a written Construction Phase Plan (even a brief one) is legally required.

Key Facts

Quick Reference Table

Spending too long on quotes? squote turns a 2-minute voice recording into a professional quote.

Try squote free →
Stage Work Lead Trade Key Compliance / Handover
0 Measure, design, specification Plumber / designer Layout clearances; order long-lead items
1 Strip-out Plumber / builder Safe isolation; asbestos check (pre-2000)
2 Substrate prep and structural repairs Builder / plasterer MR board / tile backer in wet areas
3 First fix: plumbing Plumber Pipe runs pressure-tested before covering
4 First fix: electrics Electrician BS 7671 Section 701 zones; Part P
5 Waterproofing (tanking) Tiler / specialist Tank before tiling; cure per data sheet
6 Tiling: floors and walls Tiler Adhesive coverage (BS 5385); fall to gully
7 Floor finish (if not tiled) Floor layer Moisture test substrate before laying
8 Second fix: plumbing Plumber Connect suite; flexible pan connector
9 Second fix: electrics Electrician Test, certify, Part P notification
10 Accessories, decoration, snagging Decorator / plumber Silicone movement joints (BS 5385-1)

Detailed Guidance

The Trade Sequence

Stage 0 — Measure, Design, and Specification

Who: Plumber/main contractor, bathroom designer (if applicable), client.

Tasks:

Handover to Stage 1: All materials on order. Sequence agreed. Trades booked in correct order with sufficient gaps between stages.


Stage 1 — Strip-Out

Who: Plumber or general builder.

Tasks:

Critical check: Once stripped, inspect: (1) any evidence of previous leaks in floor or walls; (2) condition of joists if ground floor is suspended timber; (3) presence of any hidden runs (asbestos insulation pipe lagging in pre-1985 properties — check before cutting).

Asbestos note: Artex ceilings, old floor tiles, pipe lagging, and some textured wall surfaces pre-2000 may contain asbestos. Do not disturb without an asbestos survey under Control of Asbestos Regulations 2012 if age and condition suggest risk.

See also: asbestos containing materials acm, bathroom floor prep


Stage 2 — Substrate Preparation and Structural Repairs

Who: Builder/plasterer, carpenter (if floor repair needed).

Tasks:

Handover condition to Stage 3: Substrate sound, dry, and level. All MR board or tile backer board installed. No structural defects.

See also: drylining in wet areas, floor levelling, bathroom floor prep


Stage 3 — First Fix: Plumbing

Who: Plumber.

Tasks:

Key rule: All plumbing runs in walls or under floors must be complete, pressure-tested, and signed off before tiling. Any future leak behind tiles = full re-tile job.

See also: waste pipes, sanitary pipework design, underfloor heating


Stage 4 — First Fix: Electrics

Who: Electrician.

Tasks:

Key rule: Confirm all zone positions with tiler before cables are routed behind tiles. The zone boundary is fixed by the bath/shower edge — measure carefully before burying cables.

See also: bathroom fan wiring, bathroom lighting, bathroom zones


Stage 5 — Waterproofing (Tanking)

Who: Tiler or waterproofing specialist.

Tasks:

Critical inspection point: Tanking is the most important quality gate in a bathroom refit. Inspect for pinholes, missed areas at corners, and coverage at penetrations BEFORE tiling covers it. A failed tanking system = tiles off, retank, retile.

See also: bathroom waterproofing tanking, wetroom construction, wet room installation guide


Stage 6 — Tiling: Floors and Walls

Who: Tiler.

Tasks:

Dependencies: Tanking fully cured. Floor substrate rigid and level. All back boxes confirmed in correct position.

See also: large format tiles, tile backer board guide, waterproofing, bathroom tiles guide


Stage 7 — Floor Finish (If Not Tiled)

Who: Floor layer.

Tasks (where non-tiled floor specified — e.g., luxury vinyl tile, vinyl sheet):

See also: lvt installation, vinyl sheet


Stage 8 — Second Fix: Plumbing

Who: Plumber.

Tasks:

Key rule: Apply sanitary-grade silicone sealant between ALL sanitaryware and tile surfaces (bath rim, shower tray perimeter, basin back to wall). Use a single continuous bead. No grout between bath and tiles — silicone only.

See also: bath installation, walk in shower installation, thermostatic mixing valves


Stage 9 — Second Fix: Electrics

Who: Electrician.

Tasks:

See also: part p overview, bathroom lighting, bathroom extractor fan guide


Stage 10 — Accessories, Decoration, and Snagging

Who: Decorator, plumber, main contractor.

Tasks:

Handover to client:

See also: interior emulsion, snagging list management


Frequently Asked Questions

Can I tile before the plumber has finished?

Only after first-fix plumbing is complete, pressure-tested, and the plumber has confirmed no further runs will be needed. You cannot tile and then modify pipework — every cut into a tiled wall is disruptive, expensive, and risks damaging tiles. Agree all plumbing positions before the tiler starts. Mark socket box and fitting positions with chalk before tiling begins.

Does electrical work in a bathroom always need notifying to Building Control?

All electrical work in a bathroom is notifiable under Building Regulations Part P unless it is a like-for-like replacement of a fitting (e.g., replacing a like-for-like ceiling light with the same rating). New circuits, new positions, additional circuits, and consumer unit work must be notified. The notifier can be a registered electrician self-certifying under a competent person scheme, or the client can notify Building Control directly.

How long does a full bathroom refit take?

A standard bathroom refit (strip, substrate repair, first-fix, waterproofing, tiling, second-fix) takes 5–10 working days for one team. The main variables are: tile drying and grout cure time (24–48 hours before walking on floors, 24 hours before sealing or contact with water), and plaster drying time if re-plastering is needed. A wet room or full luxury refit can take 2–3 weeks.

Should silicone go on before or after grouting?

After grouting. Grout all joints fully (including internal corners where the tiler may have initially grouted). Once cured, rake out the internal corner joints to 5–8mm depth, clean dry, and apply sanitary silicone in a single continuous bead. The grout underneath the silicone provides colour continuity and structural support. Never grout internal corners — they will crack as the building moves.

Can a bathroom be created in a room with no external window?

Yes, under Building Regulations Part F, a bathroom without a window can use mechanical extract ventilation (minimum 15 l/s for a bathroom, 6 l/s for a separate WC). The extractor must be humidistat-controlled and run for a minimum overrun period. The duct must terminate externally (not into a loft or void space) and follow minimum duct length and bend requirements to maintain extract rate.

Regulations & Standards