Summary

A whole-house renovation is the biggest job most small building firms price, and the one where a mistake in the estimate costs the most. The customer sees a single number; behind it sit eight or more trades, a 12–24 week programme, Building Regulations applications, and a thousand small decisions about what "renovate" actually includes. Builders who lose money on renovations almost never lose it on the brickwork. They lose it on unpriced preliminaries (skips, scaffold, welfare, the project manager's own time), on the gap between what the customer imagined and what was written down, and on discovering the house is not what the survey said once the plaster comes off.

The right approach is to price bottom-up and check top-down. Bottom-up means a trade-by-trade schedule with quantities, labour days and material allowances, sequenced into a programme so you know how many weeks of preliminaries you are carrying. Top-down means checking that figure against per-square-metre benchmarks for the type of job, so that a figure that comes out at £700/m² for a back-to-brick refurbishment gets a second look before it goes to the customer. This guide gives both: the benchmarks, the schedule structure, the percentages, and the contract terms that stop a renovation turning into an unpaid argument.

It also covers the compliance items that have a price: the asbestos survey, the Building Regulations applications and the trades that must self-certify, CDM 2015 duties on domestic projects, VAT (including the 5% reduced rate on long-empty dwellings), and the cancellation rights that apply to a contract signed in the customer's kitchen. For individual trade benchmarks, see builder day rate guide, full rewire pricing guide, full house plaster pricing guide and kitchen refurbishment pricing guide.

Key Facts

Quick Reference Table

Spending too long on quotes? squote turns a 2-minute voice recording into a professional quote.

Try squote free →
Scope (three-bed semi, 85–95 m²) Regional price range (ex VAT) London / South East Programme
Cosmetic refresh (decorate, floors, new kitchen and bathroom on existing services) £50,000–£85,000 £65,000–£110,000 6–10 weeks
Full renovation (rewire, replumb, new heating, replaster, kitchen, bathroom, decorate) £100,000–£170,000 £130,000–£220,000 12–20 weeks
Full renovation plus knock-through and new windows £130,000–£210,000 £170,000–£270,000 16–24 weeks
Full renovation plus loft conversion £170,000–£260,000 £220,000–£330,000 20–28 weeks
Full renovation plus single-storey rear extension (20 m²) £160,000–£250,000 £210,000–£320,000 20–28 weeks
Strip-out only (to brick, including asbestos survey, skips) £6,000–£12,000 £8,000–£16,000 1–2 weeks
Full rewire (3-bed, 50–60 points) £5,500–£9,000 £7,500–£12,000 5–8 days first fix, 3–4 days second fix
Replumb and new combi system (7–8 radiators) £8,000–£14,000 £10,000–£18,000 6–10 days
Full house replaster (skim walls and ceilings, 300 m²) £6,000–£10,000 £8,000–£13,000 8–12 days
Replacement windows and doors (10 units) £7,000–£14,000 £9,000–£18,000 2–3 days fitting

Detailed Guidance

Define the scope before you price it

"Full renovation" means something different to every customer. Before any numbers, walk the house with the customer and write a room-by-room scope that lists, for each room: what is being removed, what is being replaced, what finish is expected, and what is excluded. The exclusions matter more than the inclusions. Typical items customers assume are included and builders assume are not: kitchen appliances, sanitaryware, light fittings, floor coverings, external works, garden reinstatement, alarm and data cabling, and redecoration of rooms "not being touched" that will inevitably be touched by a rewire.

Fix the specification level for the items that swing the price most. A kitchen can be £6,000 or £40,000; a bathroom £4,000 or £18,000; flooring £25/m² or £120/m². Either price a provisional sum (a stated allowance the customer can spend up or down, with any difference adjusted) or a prime cost sum for the supply only, and make it clear which. Provisional sums are the honest way to carry an undecided kitchen; they are also the item most often disputed at the end, so define exactly what each one covers.

Agree the design and approvals route. If walls are coming out, a structural engineer's calculations are needed for Building Control (£500–£1,200). If the layout changes materially, a measured survey and drawings (£1,500–£4,000) pay for themselves in fewer arguments. Decide who applies for Building Regulations approval and who pays the fee (full plans on a domestic alteration typically £400–£900 depending on the authority or approved inspector).

Survey the house, not the estate agent's listing

Most renovation overruns trace back to the fabric. Spend half a day with a moisture meter, a lifting bar and a torch before you price:

Build the estimate trade by trade

Work in the order the job will be built. For each trade, list the quantities, the labour days, the material allowance and any specialist subcontract price. The sequence for a typical full renovation:

  1. Strip-out and demolition — soft strip, kitchen and bathroom removal, plaster hacking off where needed, floor coverings, asbestos removal by a licensed or notifiable non-licensed contractor as the survey dictates. Allow for the skips here: a three-bed full strip generates 8–15 eight-yard skips at £250–£400 each.
  2. Structural — steels, padstones, props, new openings, underpinning if required, chimney breast removal with gallows brackets or a steel, new lintels. Engineer's calculations and Building Control inspections.
  3. Roof and external envelope — anything that keeps the weather out before the internals start: roof repairs, chimney work, repointing, new windows and doors (or at least the openings made ready).
  4. First fix — electrics, plumbing, heating pipework, soil and waste, ventilation ducting, data and alarm cabling, carpentry (stud walls, door linings, floor repairs), insulation.
  5. Plastering — boarding, skimming, rendering, screeds. Allow drying time in the programme: a 3 mm skim needs 4–7 days before mist coating, a sand-and-cement render or screed 4 weeks before paint or floor finishes.
  6. Second fix — electrics, plumbing, kitchen fitting, bathroom fitting, joinery (doors, skirting, architrave), tiling.
  7. Decoration and floors — mist coat and two coats on new plaster (see mist coat new plaster guide), woodwork, floor finishes last.
  8. Commissioning and certification — heating commissioning and Benchmark, electrical installation certificate, gas safety, FENSA/CERTASS certificates, Building Control completion certificate.

Price each trade either from your own labour and material build-up or from a subcontractor's quotation, and record which. A subcontract quotation carried into your price with no mark-up is a loss once you have managed it.

Preliminaries: the cost most estimates miss

Preliminaries are everything the job needs that is not a trade. On a renovation they are usually 8–15% of the trade total and are the first thing to disappear when a builder prices from gut feel. List them:

Preliminary item Typical allowance (3-bed semi, 16 weeks)
Skips and waste transfer £2,500–£5,000
Scaffold (if roof, chimney or render work) £1,200–£3,500
Welfare: WC, hand wash, drying/rest facility (CDM 2015 Schedule 2) £800–£1,600
Temporary electrics and water, meter reconnection fees £300–£800
Protection: boards, sheeting, dust screens £300–£700
Site supervision and project management (0.5–1 day a week) £2,500–£5,500
Insurance (contract works, public liability), parking permits £600–£1,500
Small tools, consumables, fixings £800–£1,500
Building Control fees and structural engineer £900–£2,100
Clean, snagging and handover £500–£1,000

Contingency and margin

Contingency covers the unknown; margin covers your business. Keep them separate and show the contingency to the customer. A stated contingency of 10–15% that is only drawn down against agreed variations (with a written record) protects both sides: the customer knows the maximum exposure, and you have a mechanism for the inevitable rotten joist. A hidden contingency buried in the rates means you absorb the unknowns if they turn up and look expensive if they do not.

Margin is the figure that keeps the firm solvent. Overheads on a small building firm (vehicle, insurance, accountancy, software, phone, unpaid estimating time, down days between jobs) typically run 15–25% of turnover before any profit, so a 15% mark-up is roughly break-even for many firms. Price at 20–25% on top of cost including prelims, and understand the difference between mark-up and margin before you quote a percentage: see markup to margin explained.

Worked example: three-bed semi, full renovation

88 m² 1930s semi, back-to-brick refurbishment, no extension, one knock-through between kitchen and dining room, new windows throughout, regional rates.

Element Cost build-up Total (ex VAT)
Asbestos R&D survey and removal of Artex ceilings (3 rooms) £650 survey + £2,400 removal £3,050
Strip-out: 2 labourers × 6 days, 10 skips £1,980 labour + £3,200 skips £5,180
Structural knock-through: steel, padstones, props, engineer £1,100 steel/materials + 2 men × 4 days + £800 engineer £4,300
Full rewire, 54 points, new consumer unit, EIC Subcontract quotation £7,200
Replumb and combi heating, 8 radiators, Benchmark Subcontract quotation £11,500
Windows and doors: 9 uPVC windows, 2 composite doors, FENSA Subcontract quotation £10,800
Plastering: board and skim 310 m² walls and ceilings 2 plasterers × 10 days + £2,100 materials £7,100
Kitchen: supply (provisional sum) and fit £9,000 PS + 6 days fitting + plumbing/electrics connections £11,400
Bathroom and ensuite: supply (provisional sum), fit, tile £5,500 PS + 12 days + tiling 28 m² £11,700
Joinery: 8 internal doors, skirting, architrave, loft hatch Carpenter 9 days + £2,200 materials £4,600
Flooring: engineered oak downstairs 42 m², carpet upstairs £2,900 + £1,400 supply, 5 days fit £5,500
Decoration: mist and two coats throughout, woodwork 2 decorators × 9 days + £1,100 materials £5,300
External: repoint front elevation, new fascias and gutters Subcontract + scaffold £4,800
Trade total £92,430
Preliminaries (supervision, welfare, protection, insurance, fees, scaffold share) 11% £10,170
Cost total £102,600
Contingency (shown separately, drawn against agreed variations) 12% £12,310
Margin on cost total 20% £20,520
Contract sum (ex VAT) £123,120 + £12,310 contingency

At 88 m² that is £1,400/m² before contingency, inside the benchmark band for a full renovation at regional rates. The same job in outer London would carry £135,000–£160,000.

Programme and cash flow

Write the programme before you fix the stage payments. A 16-week renovation with monthly payments in arrears means you fund the first month's wages, materials and skips, which can be £25,000–£35,000 on the example above. Stage payments tied to milestones (strip-out complete, first fix complete, plastering complete, second fix complete, practical completion) keep your exposure to two or three weeks of cost. Set each stage so that the cumulative payment slightly leads the cumulative cost; never let it lag.

Allow drying and lead times in the programme: kitchen lead times of 4–8 weeks, windows 4–10 weeks, steels 1–2 weeks after engineer's drawings, and plaster drying before decoration. A programme that ignores these is a programme that slips, and slippage is prelims you are not being paid for.

Contract, variations and the end of the job

Use a written contract. For domestic work the JCT Building Contract for a Home Owner/Occupier (with or without a consultant) or the FMB domestic contract are both suitable; both set out payment, variations, delays and defects. The Consumer Rights Act 2015 applies regardless: work must be carried out with reasonable care and skill, and a customer can require repair or a price reduction where it is not.

Every variation goes in writing before it is done, with a price or an agreed basis for pricing it (day rate plus materials at cost plus a stated percentage). Photograph everything that is opened up. The renovation that ends in dispute is almost always the one where £8,000 of extras were agreed on the stairs and never written down. See variation orders for the process and snagging list management for the handover.

Frequently Asked Questions

Should I price a renovation per square metre or build it up trade by trade?

Build it up. Per-square-metre figures are for sense-checking and for giving a customer a first indication before you have surveyed. Two 90 m² houses can differ by £40,000 depending on the state of the services, the plaster, the roof and the kitchen specification. Use the bands in this guide to check your bottom-up figure; if it falls outside them, find out why before you send it.

What contingency should I carry, and should the customer see it?

Carry 10% on post-war housing with a good survey, 15% on pre-1950, and 20% on pre-1900 or anything with a history of unrecorded alteration. Show it as a separate line that is only drawn down against written variations. Customers accept a visible contingency far more readily than an unexplained extras bill at the end, and it protects you when the floor joists turn out to be rotten.

Can I charge 5% VAT on a renovation?

Only in specific cases set out in VAT Notice 708: renovating a dwelling that has been empty for at least two years (evidence from the council's empty property officer or electoral roll), converting a building into a different number of dwellings, or certain works for disabled people (0%). A normal occupied-house renovation is standard-rated at 20%. If you are below the £90,000 VAT registration threshold you charge no VAT, but one renovation can take you over it, so check before you sign.

Who is responsible for CDM on a domestic renovation?

The homeowner's client duties under the Construction (Design and Management) Regulations 2015 pass automatically to the contractor, or to the principal contractor where there is more than one contractor on site at any time. That means you must have a construction phase plan (a few pages for a domestic job), provide welfare facilities, and notify HSE on an F10 if the project will exceed 30 working days with more than 20 workers simultaneously or 500 person-days. A 16-week renovation with a four-man team does not reach the notification threshold; a larger one may.

How much deposit can I ask for?

Common practice is 5–10% on signing to cover design, applications and the first material orders, with the balance in stages. Large deposits (25% plus) are a red flag to customers and to trading standards. If you take a deposit you must be able to protect it, either through a scheme (TrustMark and FMB members have access to deposit and warranty protection) or by holding it in a way that it can be returned if the contract is cancelled within the 14-day period.