Summary
A whole-house renovation is the biggest job most small building firms price, and the one where a mistake in the estimate costs the most. The customer sees a single number; behind it sit eight or more trades, a 12–24 week programme, Building Regulations applications, and a thousand small decisions about what "renovate" actually includes. Builders who lose money on renovations almost never lose it on the brickwork. They lose it on unpriced preliminaries (skips, scaffold, welfare, the project manager's own time), on the gap between what the customer imagined and what was written down, and on discovering the house is not what the survey said once the plaster comes off.
The right approach is to price bottom-up and check top-down. Bottom-up means a trade-by-trade schedule with quantities, labour days and material allowances, sequenced into a programme so you know how many weeks of preliminaries you are carrying. Top-down means checking that figure against per-square-metre benchmarks for the type of job, so that a figure that comes out at £700/m² for a back-to-brick refurbishment gets a second look before it goes to the customer. This guide gives both: the benchmarks, the schedule structure, the percentages, and the contract terms that stop a renovation turning into an unpaid argument.
It also covers the compliance items that have a price: the asbestos survey, the Building Regulations applications and the trades that must self-certify, CDM 2015 duties on domestic projects, VAT (including the 5% reduced rate on long-empty dwellings), and the cancellation rights that apply to a contract signed in the customer's kitchen. For individual trade benchmarks, see builder day rate guide, full rewire pricing guide, full house plaster pricing guide and kitchen refurbishment pricing guide.
Key Facts
- Benchmark bands (2026, excluding VAT, excluding extensions) — cosmetic refurbishment £600–£1,000/m²; full back-to-brick renovation £1,200–£2,000/m²; renovation with structural alterations, new roof covering or loft conversion £2,000–£3,000/m²; London and the South East add 15–30%
- Typical three-bed semi (85–95 m²) — full renovation £100,000–£170,000; a cosmetic refresh £50,000–£85,000; programme 12–20 weeks for a full renovation with one main contractor
- Trade split on a full renovation — roughly strip-out and structural 10–15%, electrics 8–12%, plumbing and heating 10–15%, plastering 8–12%, kitchen 10–15%, bathrooms 8–12%, windows and doors 8–12%, joinery and flooring 8–12%, decoration 5–8%, prelims 8–15%
- Preliminaries — skips (£250–£400 each, 8–15 skips on a strip-out), scaffold (£1,200–£3,500 for a semi), welfare and WC hire, temporary electrics and water, protection, site supervision, insurance and parking; typically 8–15% of the trade total
- Contingency — 10% on post-1960 housing with a good survey, 15% on pre-1950, 20% on pre-1900 solid-wall houses or anything with an unknown history of DIY alterations; agree in writing how it is drawn down
- Margin — 15–25% on top of cost including prelims; the lower end only where the firm's overheads are already recovered elsewhere
- Asbestos — any house built or refurbished before 2000 needs a refurbishment and demolition survey (HSG264) before strip-out under the Control of Asbestos Regulations 2012; survey £400–£900, removal of textured coating, floor tiles or boarding priced separately
- CDM 2015 — on a domestic project the client's duties pass to the contractor (or the principal contractor where there is more than one contractor); a construction phase plan is required for every project, and HSE notification (F10) if the work exceeds 30 working days with more than 20 workers at once, or 500 person-days
- Building Regulations — structural alterations, new drainage, replacement windows, new heating systems, rewires and new bathrooms all fall under the Building Regulations 2010; most are handled through competent person schemes (FENSA/CERTASS, Gas Safe, NICEIC/NAPIT) with a full plans or building notice application for structural and layout work
- VAT — standard rate 20% on renovation of an occupied dwelling; 5% reduced rate on renovating a dwelling empty for two years or more (VAT Notice 708 section 8), 0% on some work for disabled occupants; the domestic reverse charge does not apply to work for a homeowner
- Cancellation rights — a contract signed in the customer's home is an off-premises contract under the Consumer Contracts (Information, Cancellation and Additional Charges) Regulations 2013: 14-day cancellation period, and a customer who asks you to start inside it must do so in writing
- Payment — deposit of 5–10% on signing (held under a deposit protection scheme if you are a TrustMark or FMB member), stage payments at milestones, retention of 2.5–5% released at practical completion or after a 3–6 month defects period
- Day rates feeding the estimate (2026, regional) — builder £220–£320, labourer £140–£190, electrician £280–£380, plumber/heating engineer £280–£400, plasterer £220–£300, carpenter £220–£300, decorator £180–£260; see the individual day-rate guides
Quick Reference Table
Spending too long on quotes? squote turns a 2-minute voice recording into a professional quote.
Try squote free →| Scope (three-bed semi, 85–95 m²) | Regional price range (ex VAT) | London / South East | Programme |
|---|---|---|---|
| Cosmetic refresh (decorate, floors, new kitchen and bathroom on existing services) | £50,000–£85,000 | £65,000–£110,000 | 6–10 weeks |
| Full renovation (rewire, replumb, new heating, replaster, kitchen, bathroom, decorate) | £100,000–£170,000 | £130,000–£220,000 | 12–20 weeks |
| Full renovation plus knock-through and new windows | £130,000–£210,000 | £170,000–£270,000 | 16–24 weeks |
| Full renovation plus loft conversion | £170,000–£260,000 | £220,000–£330,000 | 20–28 weeks |
| Full renovation plus single-storey rear extension (20 m²) | £160,000–£250,000 | £210,000–£320,000 | 20–28 weeks |
| Strip-out only (to brick, including asbestos survey, skips) | £6,000–£12,000 | £8,000–£16,000 | 1–2 weeks |
| Full rewire (3-bed, 50–60 points) | £5,500–£9,000 | £7,500–£12,000 | 5–8 days first fix, 3–4 days second fix |
| Replumb and new combi system (7–8 radiators) | £8,000–£14,000 | £10,000–£18,000 | 6–10 days |
| Full house replaster (skim walls and ceilings, 300 m²) | £6,000–£10,000 | £8,000–£13,000 | 8–12 days |
| Replacement windows and doors (10 units) | £7,000–£14,000 | £9,000–£18,000 | 2–3 days fitting |
Detailed Guidance
Define the scope before you price it
"Full renovation" means something different to every customer. Before any numbers, walk the house with the customer and write a room-by-room scope that lists, for each room: what is being removed, what is being replaced, what finish is expected, and what is excluded. The exclusions matter more than the inclusions. Typical items customers assume are included and builders assume are not: kitchen appliances, sanitaryware, light fittings, floor coverings, external works, garden reinstatement, alarm and data cabling, and redecoration of rooms "not being touched" that will inevitably be touched by a rewire.
Fix the specification level for the items that swing the price most. A kitchen can be £6,000 or £40,000; a bathroom £4,000 or £18,000; flooring £25/m² or £120/m². Either price a provisional sum (a stated allowance the customer can spend up or down, with any difference adjusted) or a prime cost sum for the supply only, and make it clear which. Provisional sums are the honest way to carry an undecided kitchen; they are also the item most often disputed at the end, so define exactly what each one covers.
Agree the design and approvals route. If walls are coming out, a structural engineer's calculations are needed for Building Control (£500–£1,200). If the layout changes materially, a measured survey and drawings (£1,500–£4,000) pay for themselves in fewer arguments. Decide who applies for Building Regulations approval and who pays the fee (full plans on a domestic alteration typically £400–£900 depending on the authority or approved inspector).
Survey the house, not the estate agent's listing
Most renovation overruns trace back to the fabric. Spend half a day with a moisture meter, a lifting bar and a torch before you price:
- Asbestos — pre-2000 build or refurbishment means a refurbishment and demolition survey to HSG264 before strip-out is priced. Textured coatings (Artex), floor tiles and their adhesive, soffits, boiler flue and water tank boards, toilet cisterns, and fuse-board backing are the usual finds. See refurbishment demolition survey process.
- Structure — look for cracking, bowing walls, sagging floors, cut joists, chimney breasts removed without support, and lintels replaced with nothing. Any of these turns the contingency into a priced item.
- Damp — distinguish condensation, penetrating damp and rising damp before you price the plaster. Replastering over an unresolved damp problem is the single most common renovation defect claim. See rising damp vs penetrating damp.
- Services — age and type of wiring (rubber or lead-sheathed cable means a full rewire, no discussion), consumer unit, incoming supply capacity (a 60 A supply will not run an electric shower, induction hob and EV charger), lead water main, gas pipe routes, drainage condition (a CCTV survey at £150–£350 is cheap insurance on a pre-1960 house).
- Roof and externals — a renovation that leaves a failing roof covering is a renovation the customer will remember for the wrong reasons. Price it or exclude it explicitly.
Build the estimate trade by trade
Work in the order the job will be built. For each trade, list the quantities, the labour days, the material allowance and any specialist subcontract price. The sequence for a typical full renovation:
- Strip-out and demolition — soft strip, kitchen and bathroom removal, plaster hacking off where needed, floor coverings, asbestos removal by a licensed or notifiable non-licensed contractor as the survey dictates. Allow for the skips here: a three-bed full strip generates 8–15 eight-yard skips at £250–£400 each.
- Structural — steels, padstones, props, new openings, underpinning if required, chimney breast removal with gallows brackets or a steel, new lintels. Engineer's calculations and Building Control inspections.
- Roof and external envelope — anything that keeps the weather out before the internals start: roof repairs, chimney work, repointing, new windows and doors (or at least the openings made ready).
- First fix — electrics, plumbing, heating pipework, soil and waste, ventilation ducting, data and alarm cabling, carpentry (stud walls, door linings, floor repairs), insulation.
- Plastering — boarding, skimming, rendering, screeds. Allow drying time in the programme: a 3 mm skim needs 4–7 days before mist coating, a sand-and-cement render or screed 4 weeks before paint or floor finishes.
- Second fix — electrics, plumbing, kitchen fitting, bathroom fitting, joinery (doors, skirting, architrave), tiling.
- Decoration and floors — mist coat and two coats on new plaster (see mist coat new plaster guide), woodwork, floor finishes last.
- Commissioning and certification — heating commissioning and Benchmark, electrical installation certificate, gas safety, FENSA/CERTASS certificates, Building Control completion certificate.
Price each trade either from your own labour and material build-up or from a subcontractor's quotation, and record which. A subcontract quotation carried into your price with no mark-up is a loss once you have managed it.
Preliminaries: the cost most estimates miss
Preliminaries are everything the job needs that is not a trade. On a renovation they are usually 8–15% of the trade total and are the first thing to disappear when a builder prices from gut feel. List them:
| Preliminary item | Typical allowance (3-bed semi, 16 weeks) |
|---|---|
| Skips and waste transfer | £2,500–£5,000 |
| Scaffold (if roof, chimney or render work) | £1,200–£3,500 |
| Welfare: WC, hand wash, drying/rest facility (CDM 2015 Schedule 2) | £800–£1,600 |
| Temporary electrics and water, meter reconnection fees | £300–£800 |
| Protection: boards, sheeting, dust screens | £300–£700 |
| Site supervision and project management (0.5–1 day a week) | £2,500–£5,500 |
| Insurance (contract works, public liability), parking permits | £600–£1,500 |
| Small tools, consumables, fixings | £800–£1,500 |
| Building Control fees and structural engineer | £900–£2,100 |
| Clean, snagging and handover | £500–£1,000 |
Contingency and margin
Contingency covers the unknown; margin covers your business. Keep them separate and show the contingency to the customer. A stated contingency of 10–15% that is only drawn down against agreed variations (with a written record) protects both sides: the customer knows the maximum exposure, and you have a mechanism for the inevitable rotten joist. A hidden contingency buried in the rates means you absorb the unknowns if they turn up and look expensive if they do not.
Margin is the figure that keeps the firm solvent. Overheads on a small building firm (vehicle, insurance, accountancy, software, phone, unpaid estimating time, down days between jobs) typically run 15–25% of turnover before any profit, so a 15% mark-up is roughly break-even for many firms. Price at 20–25% on top of cost including prelims, and understand the difference between mark-up and margin before you quote a percentage: see markup to margin explained.
Worked example: three-bed semi, full renovation
88 m² 1930s semi, back-to-brick refurbishment, no extension, one knock-through between kitchen and dining room, new windows throughout, regional rates.
| Element | Cost build-up | Total (ex VAT) |
|---|---|---|
| Asbestos R&D survey and removal of Artex ceilings (3 rooms) | £650 survey + £2,400 removal | £3,050 |
| Strip-out: 2 labourers × 6 days, 10 skips | £1,980 labour + £3,200 skips | £5,180 |
| Structural knock-through: steel, padstones, props, engineer | £1,100 steel/materials + 2 men × 4 days + £800 engineer | £4,300 |
| Full rewire, 54 points, new consumer unit, EIC | Subcontract quotation | £7,200 |
| Replumb and combi heating, 8 radiators, Benchmark | Subcontract quotation | £11,500 |
| Windows and doors: 9 uPVC windows, 2 composite doors, FENSA | Subcontract quotation | £10,800 |
| Plastering: board and skim 310 m² walls and ceilings | 2 plasterers × 10 days + £2,100 materials | £7,100 |
| Kitchen: supply (provisional sum) and fit | £9,000 PS + 6 days fitting + plumbing/electrics connections | £11,400 |
| Bathroom and ensuite: supply (provisional sum), fit, tile | £5,500 PS + 12 days + tiling 28 m² | £11,700 |
| Joinery: 8 internal doors, skirting, architrave, loft hatch | Carpenter 9 days + £2,200 materials | £4,600 |
| Flooring: engineered oak downstairs 42 m², carpet upstairs | £2,900 + £1,400 supply, 5 days fit | £5,500 |
| Decoration: mist and two coats throughout, woodwork | 2 decorators × 9 days + £1,100 materials | £5,300 |
| External: repoint front elevation, new fascias and gutters | Subcontract + scaffold | £4,800 |
| Trade total | £92,430 | |
| Preliminaries (supervision, welfare, protection, insurance, fees, scaffold share) | 11% | £10,170 |
| Cost total | £102,600 | |
| Contingency (shown separately, drawn against agreed variations) | 12% | £12,310 |
| Margin on cost total | 20% | £20,520 |
| Contract sum (ex VAT) | £123,120 + £12,310 contingency |
At 88 m² that is £1,400/m² before contingency, inside the benchmark band for a full renovation at regional rates. The same job in outer London would carry £135,000–£160,000.
Programme and cash flow
Write the programme before you fix the stage payments. A 16-week renovation with monthly payments in arrears means you fund the first month's wages, materials and skips, which can be £25,000–£35,000 on the example above. Stage payments tied to milestones (strip-out complete, first fix complete, plastering complete, second fix complete, practical completion) keep your exposure to two or three weeks of cost. Set each stage so that the cumulative payment slightly leads the cumulative cost; never let it lag.
Allow drying and lead times in the programme: kitchen lead times of 4–8 weeks, windows 4–10 weeks, steels 1–2 weeks after engineer's drawings, and plaster drying before decoration. A programme that ignores these is a programme that slips, and slippage is prelims you are not being paid for.
Contract, variations and the end of the job
Use a written contract. For domestic work the JCT Building Contract for a Home Owner/Occupier (with or without a consultant) or the FMB domestic contract are both suitable; both set out payment, variations, delays and defects. The Consumer Rights Act 2015 applies regardless: work must be carried out with reasonable care and skill, and a customer can require repair or a price reduction where it is not.
Every variation goes in writing before it is done, with a price or an agreed basis for pricing it (day rate plus materials at cost plus a stated percentage). Photograph everything that is opened up. The renovation that ends in dispute is almost always the one where £8,000 of extras were agreed on the stairs and never written down. See variation orders for the process and snagging list management for the handover.
Frequently Asked Questions
Should I price a renovation per square metre or build it up trade by trade?
Build it up. Per-square-metre figures are for sense-checking and for giving a customer a first indication before you have surveyed. Two 90 m² houses can differ by £40,000 depending on the state of the services, the plaster, the roof and the kitchen specification. Use the bands in this guide to check your bottom-up figure; if it falls outside them, find out why before you send it.
What contingency should I carry, and should the customer see it?
Carry 10% on post-war housing with a good survey, 15% on pre-1950, and 20% on pre-1900 or anything with a history of unrecorded alteration. Show it as a separate line that is only drawn down against written variations. Customers accept a visible contingency far more readily than an unexplained extras bill at the end, and it protects you when the floor joists turn out to be rotten.
Can I charge 5% VAT on a renovation?
Only in specific cases set out in VAT Notice 708: renovating a dwelling that has been empty for at least two years (evidence from the council's empty property officer or electoral roll), converting a building into a different number of dwellings, or certain works for disabled people (0%). A normal occupied-house renovation is standard-rated at 20%. If you are below the £90,000 VAT registration threshold you charge no VAT, but one renovation can take you over it, so check before you sign.
Who is responsible for CDM on a domestic renovation?
The homeowner's client duties under the Construction (Design and Management) Regulations 2015 pass automatically to the contractor, or to the principal contractor where there is more than one contractor on site at any time. That means you must have a construction phase plan (a few pages for a domestic job), provide welfare facilities, and notify HSE on an F10 if the project will exceed 30 working days with more than 20 workers simultaneously or 500 person-days. A 16-week renovation with a four-man team does not reach the notification threshold; a larger one may.
How much deposit can I ask for?
Common practice is 5–10% on signing to cover design, applications and the first material orders, with the balance in stages. Large deposits (25% plus) are a red flag to customers and to trading standards. If you take a deposit you must be able to protect it, either through a scheme (TrustMark and FMB members have access to deposit and warranty protection) or by holding it in a way that it can be returned if the contract is cancelled within the 14-day period.
Regulations & Standards
Building Regulations 2010 (SI 2010/2214, as amended) — structural alterations (Approved Document A), fire safety (Approved Document B), ventilation (Approved Document F), drainage (Approved Document H), heating and energy (Approved Document L1B for existing dwellings), electrical safety (Approved Document P), and access (Approved Document M) all apply to renovation work
Control of Asbestos Regulations 2012 (SI 2012/632) — duty to identify asbestos before refurbishment; HSG264 Asbestos: The Survey Guide sets out the refurbishment and demolition survey
Construction (Design and Management) Regulations 2015 (SI 2015/51) — construction phase plan, welfare (Schedule 2), domestic client duties transferring to the contractor, F10 notification thresholds
Consumer Rights Act 2015 — services to be performed with reasonable care and skill; remedies of repeat performance or price reduction
Consumer Contracts (Information, Cancellation and Additional Charges) Regulations 2013 (SI 2013/3134) — 14-day cancellation right for off-premises contracts and the pre-contract information you must give
Party Wall etc. Act 1996 — notices required for work to a shared wall, cutting in beams, or excavation within 3 m or 6 m of a neighbour's foundations
Gas Safety (Installation and Use) Regulations 1998 — all gas work by a Gas Safe registered engineer
BS 7671:2018+A2:2022 — Requirements for Electrical Installations (IET Wiring Regulations), the standard for the rewire
VAT Notice 708 — buildings and construction: reduced-rate and zero-rate conditions for renovation and conversion
JCT Building Contract for a Home Owner/Occupier — standard form of domestic building contract
Building regulations approval — GOV.UK — when approval is needed and how to apply
Construction (Design and Management) Regulations 2015 — HSE — duty holders, domestic clients, notification
HSG264 Asbestos: The survey guide — HSE — refurbishment and demolition surveys
VAT Notice 708: buildings and construction — GOV.UK — reduced and zero rates for renovation
Consumer Contracts Regulations guidance — Trading Standards / Business Companion — cancellation rights for off-premises contracts
JCT Home Owner contracts — Joint Contracts Tribunal — domestic building contract forms
builder day rate guide — the day rate that underpins the labour lines in the estimate
full rewire pricing guide — rewire pricing by points and property size
full house plaster pricing guide — whole-house skim and board pricing
kitchen refurbishment pricing guide — kitchen supply and fit pricing
house extension pricing guide — pricing when the renovation includes an extension
markup to margin explained — the difference between mark-up and margin
refurbishment demolition survey process — what the pre-strip-out survey involves
retention payment guide — retention terms on domestic contracts