Summary
"Builder" covers more ground than any other trade title: a one-person outfit doing garden walls and patios, a two-person team doing kitchens and bathrooms, a small firm running extensions with subcontracted trades, and a main contractor on a £300,000 refurbishment. The day rate means something different at each level. For the sole trader it is their wage and the business in one number. For the firm it is the number the estimator uses to price labour on a job that will be sold as a fixed price, with the subcontractors, materials, plant, skips, scaffold, preliminaries, overhead and profit added on top — and it is also the rate on the variation when the customer asks for "a couple of extra sockets while you're here".
This guide builds the general builder's day rate from 2026 costs, gives the regional market figures for solo, team and firm, explains how the rate turns into a job price with overhead and profit, and sets out the rules that attach to being the builder rather than the trade: CIS deductions on the subbies you pay, CDM 2015 duties as the principal contractor, Building Regulations applications, the Consumer Rights Act on the contract, VAT and the domestic reverse charge. For the method across all trades see pricing labour; for the trades a builder prices in see bricklayer day rate guide, carpenter day rate guide and labourer day rate guide.
Key Facts
- Day rate, skilled general builder, 2026 — £200–£300 regionally; £240–£350 South East; £300–£450 London, with own tools and van, 8 hours on site
- Two-person team — £400–£600 regionally, £480–£700 South East, £600–£850 London; builder plus labourer at the lower end, two skilled trades at the upper
- Hourly equivalent — £30–£60; the hourly rate is for small works and day-work variations, derived as day rate ÷ 7 (a builder on a job rarely bills more than 7 productive hours of an 8-hour day)
- Half-day minimum — £130–£200; small repairs, a survey visit that turns into a fix, snagging returns
- Overhead and profit (OHP) — 15–25% on subcontract labour, materials and plant passing through the builder's contract; 10–15% on the builder's own labour already carries overhead in the day rate
- Materials markup — 10–20%; lower than a single trade because the volumes are higher and the builder is paid for managing supply, not just buying it
- Preliminaries — skips, scaffold, welfare, temporary services, waste carrier, site set-up and clean: itemised lines, never absorbed into the day rate
- Billable days — 200–215 a year; a builder loses fewer days to weather than a bricklayer or roofer because internal work fills the gaps, but loses days to quoting, site visits, ordering and chasing subbies that a single trade does not
- CIS — a builder paying subcontractors is a contractor: register with HMRC, verify each subbie, deduct 20% (or 30% unverified) from the labour element, file monthly returns; the builder's own invoices to a domestic customer have no deduction; see cis tax explained and cis subcontractor verification
- CDM 2015 — on a domestic project with more than one contractor, the builder who controls the construction phase is the principal contractor: construction phase plan, site induction, welfare, coordination; a single-contractor job needs a construction phase plan too
- Building Regulations — the builder usually makes the application (full plans or building notice) and books the inspections; fees of £300–£1,500 for a typical extension are a disbursement, not margin
- Planning — permitted development limits for extensions (single-storey rear: 3 m detached / 4 m attached under standard PD, 6 m / 8 m under the larger home extension scheme with prior approval); the builder is not the planning consultant but should know when to say "check first"
- Insurance — public liability £2 million minimum, £5 million common on anything with a party wall or a highway; £900–£2,500 a year for a small builder; employers' liability compulsory from the first employee; contractors' all-risks on larger jobs
- VAT — compulsory registration above £90,000 taxable turnover in a rolling 12 months; a builder passing £60,000 of materials and subbies through one extension is registered whether they like it or not; the domestic reverse charge applies between VAT-registered CIS businesses, not to domestic customers; see domestic reverse charge vat guide
- Reduced-rate VAT — 5% on some conversions and renovations of properties empty 2+ years, 0% on qualifying new-build; the builder has to get this right on the invoice
- Consumer Rights Act 2015, s.51 — reasonable price where none agreed; a written quote with the scope, the day rate for extras and the payment schedule is the protection; see quotes vs estimates
- Payment — stage payments against defined milestones; never more than the value of work done; a deposit of 10–25% for materials ordering on a job over £5,000; final payment on completion with a snagging list, no retention on domestic work unless the contract says so
- Trade associations — FMB, NFB, TrustMark; membership £400–£1,200 a year is overhead, and TrustMark is required for some grant-funded work
Quick Reference Table
Spending too long on quotes? squote turns a 2-minute voice recording into a professional quote.
Try squote free →| Charge | Regional (outside London/SE) | South East | London | Notes |
|---|---|---|---|---|
| Day rate, skilled builder, solo | £200–£300 | £240–£350 | £300–£450 | Own tools and van |
| Day rate, builder + labourer | £350–£480 | £400–£550 | £500–£680 | Labourer £130–£230 of it |
| Day rate, two skilled trades | £420–£600 | £480–£700 | £600–£850 | |
| Hourly, small works | £30–£45 | £35–£52 | £45–£65 | First hour often £60–£90 |
| Half-day minimum | £130–£200 | £150–£220 | £180–£280 | |
| Day-work variation rate (on a contract) | Day rate + 10–15% | Day rate + 10–15% | Day rate + 10–15% | For unpriced extras |
| OHP on subcontractors and materials | 15–25% | 15–25% | 15–25% | On the pass-through value |
| Materials markup | 10–20% | 10–20% | 10–20% | |
| Single-storey extension, 20 m², all-in | £1,800–£2,600 per m² | £2,100–£3,000 | £2,600–£3,800 | Builder's finish, excl. kitchen; see extension guides |
| Kitchen fit (rip-out, first fix, fit, second fix), labour | £2,500–£4,500 | £3,000–£5,200 | £3,800–£6,500 | 6–10 days, two people |
| Bathroom refit, labour | £2,000–£3,500 | £2,400–£4,000 | £3,000–£5,000 | 5–8 days |
Detailed Guidance
Building the day rate from your costs
A sole-trader general builder outside London, working with a labourer on most jobs and subcontracting the certified trades:
| Item | Annual figure |
|---|---|
| Target income before tax | £42,000 |
| Van: finance or depreciation, insurance, tax, servicing, fuel | £8,500 |
| Public liability (£5 million) and tools cover | £1,400 |
| Tools and plant: mixer, saws, breaker, laser, replacements, small plant hire not recharged | £2,500 |
| Consumables not recharged: blades, fixings, PPE, fuel for plant | £900 |
| Phone, software, accountant (CIS returns add to this), bank and card fees | £2,600 |
| Advertising, website, directories, trade association | £1,500 |
| Training, cards (CSCS, asbestos awareness, first aid, SMSTS/SSSTS on larger sites) | £500 |
| Pension contribution | £3,000 |
| Total to recover | £62,900 |
A builder working 47 weeks and losing a day a week to quoting, site visits, ordering, Building Control appointments and chasing subbies has about 205 billable days. £62,900 ÷ 205 = £307 a day to earn £42,000 before tax. At £200 a day the income before tax is about £20,000 — the reason £200-a-day builders go out of business in year three. At £300 it is about £40,500. The market range of £200–£300 regionally has a bottom half that works only for a builder with no van payment and no marketing cost, and a top that produces a modest wage for someone carrying the risk of other people's work.
From day rate to job price: overhead and profit
The day rate pays the builder for the days the builder is on the tools. It does not pay for managing a £40,000 extension where £24,000 is subcontractors and materials, where the builder is liable to the customer for the plumber's leak and the plasterer's cracks, funds the materials for 30 days before the stage payment, and spends two hours a day on the phone. That is what overhead and profit on the pass-through value is for:
Single-storey rear extension, 4 m × 5 m, regional, builder's finish
Builder's own labour: 24 days × £290 = £6,960
Labourer: 20 days × £160 = £3,200
Bricklayer (sub): per thousand / m², agreed = £3,400
Groundworker + mini digger (sub): = £2,800
Roofer (sub): = £2,600
Electrician (sub, Part P): = £1,900
Plumber / heating (sub): = £1,600
Plasterer (sub): = £1,800
Materials (at cost): = £13,500
Preliminaries: skips ×4, scaffold, welfare, waste carrier = £3,100
Building Control fee, structural engineer (disbursements) = £1,400
--------
Cost £42,260
OHP 18% on subs, materials and prelims (£30,700) = £5,526
(no separate materials markup: the OHP covers it)
Contingency 5% on the whole (declared or held) = £2,113
--------
Quote (ex VAT) £49,899 → £49,900
(£2,495 per m²)
The builder's own 24 days at £290 are the day rate; the £5,500 of OHP is the builder's profit for running the job and carrying the risk. A builder who quotes £42,260 — cost — has worked 24 days for a wage and managed £30,000 of other people's work for nothing. If the customer finds the £49,900 high, the answer is the breakdown, not a cut to the OHP.
Day-work and variations
On any job longer than a week the customer will ask for extras, and the extras are where fixed-price jobs lose money. The contract should name the day-work rates — builder, labourer, each subcontractor's hourly or daily charge — with a 10–15% uplift over the pricing rates to cover the disruption, and should say that materials for extras are at cost plus the agreed markup. Record each variation on the day (a text with a photo is enough), price it within 48 hours, and get a yes before the work is done. A builder who does £3,000 of unpriced extras on a £40,000 job and argues about them at the end has given them away; see quotes vs estimates for the Consumer Rights Act position on unagreed prices.
Small works and the hourly rate
Kitchens, bathrooms, garden walls, a new doorway, a stud wall: the solo builder's bread and butter. These are priced as jobs, built from the day rate with the materials on top, and presented as a total:
- Kitchen rip-out and fit — 6–10 days for two people depending on first-fix changes; the electrician and plumber as subs or as the builder's own ticketed work; see kitchen sink replacement pricing guide for the plumbing end
- Bathroom refit — 5–8 days; tiling is often the long pole
- Structural opening with a steel — 2–4 days plus the engineer's calculation (£300–£600) and Building Control under Approved Document A
- Garden wall — see garden wall pricing guide
For jobs under a day, charge the hourly rate with a first-hour premium (£60–£90 for the first hour, then £30–£45), or a half-day minimum. The hourly rate exists for the customer who wants "a quick look at the door that sticks"; it should not be the basis of any job over two days.
Being the contractor: CIS, CDM and the paperwork
Taking on subcontractors makes the builder a contractor three times over:
- CIS. Register as a contractor, verify each subcontractor with HMRC before first payment, deduct 20% (30% if unverified) from the labour element of every payment, pay it to HMRC monthly with a return, and give each subbie a deduction statement. The cost of getting it wrong is the tax you should have deducted plus penalties.
- CDM 2015. On a domestic project the client's duties pass to the contractor (single contractor) or the principal contractor (more than one). The practical minimum: a construction phase plan (a few pages for an extension), site induction for everyone, welfare (a toilet and washing facilities — the customer's bathroom with their agreement is acceptable on domestic work), first aid, and coordination of the trades. The HSE's CDM guidance for small builders is written for exactly this scale.
- Building Regulations. The builder usually submits the building notice or full plans, pays the fee as a disbursement, and books the inspections at foundations, DPC, drains, structure, insulation and completion; the completion certificate is what the customer needs when they sell.
See managing subcontractors and subcontracting and subbies for the working relationship; employers liability insurance guide for the point at which a regular labourer becomes an employee.
Regional, seasonal and firm-size factors
The regional spread is 40–50% from the cheapest regions to London, and London adds parking, ULEZ, congestion charge and the hour each way that the day rate must carry. Seasonally the builder is less exposed than the external trades, but January is quiet for quoting and November–February for starts; the rate carries it. A two- or three-person firm with a van each and an office has an overhead of £40,000–£80,000 before anyone is paid, which is why the firm's day rate for the same skilled builder is £50–£100 a day above the sole trader's, and why the firm's OHP is 20–25% rather than 15%.
Frequently Asked Questions
What is a fair day rate for a builder in 2026?
£200–£300 a day outside London and the South East for a skilled self-employed general builder with their own tools and van, £300–£450 in London, and £400–£600 regionally for a two-person team. The rate produces around £40,000 before tax on 205 billable days once the van, insurance, tools, marketing and pension are paid; below £250 regionally the sums only work for a builder with no van payment.
Should a builder charge by the day or by the job?
By the job, for anything over two days: the customer gets a fixed price and the builder is paid for efficiency and for carrying the subcontract and material risk through overhead and profit. The day rate is the figure the job price is built from, the rate for day-work extras named in the contract, and the right basis for genuinely open-ended work — a structural investigation, a refurbishment where nobody knows what is behind the plaster — with a written cap.
How much should a builder add on subcontractors and materials?
15–25% overhead and profit on the value of subcontractors, materials and preliminaries that pass through the builder's contract, in addition to the builder's own day rate for the days worked. On a £40,000 extension with £30,000 of pass-through, that is £4,500–£7,500: the builder's payment for managing the job and being liable for it.
Do I have to deduct CIS from my subbies?
Yes, if you pay subcontractors for construction work: register as a CIS contractor, verify each one with HMRC, deduct 20% (30% unverified) from the labour element, and file monthly returns. It applies however small you are. A homeowner paying you is not a contractor, so nothing is deducted from your invoice to them.
Am I the principal contractor on a house extension?
If more than one contractor works on the project — you and a subcontracted electrician is enough — and you control the construction phase, yes, under CDM 2015, with the client's duties also falling to you on domestic work. The practical obligations are a construction phase plan, inductions, welfare and coordinating the trades; the HSE's guidance for small domestic projects sets out the minimum.
Regulations & Standards
Consumer Rights Act 2015 (s.49–s.52) — reasonable care and skill; reasonable price where none agreed; reasonable time
Consumer Contracts (Information, Cancellation and Additional Charges) Regulations 2013 (SI 2013/3134) — 14-day cancellation right for contracts agreed in the customer's home; information to be given before the contract
Income Tax (Construction Industry Scheme) Regulations 2005 (SI 2005/2045) — contractor registration, verification, deductions and returns
Construction (Design and Management) Regulations 2015 (SI 2015/51) — contractor and principal contractor duties; domestic client duties transferred
Building Regulations 2010 (SI 2010/2214) and the Building Safety Act 2022 — applications, inspections, completion certificates; registered building control approvers
Town and Country Planning (General Permitted Development) (England) Order 2015 (SI 2015/596) — permitted development limits for extensions
Party Wall etc. Act 1996 — notices for work on or near a shared wall or boundary and excavations within 3 m or 6 m
Value Added Tax Act 1994 and the VAT (Section 55A) (Specified Services and Excepted Supplies) Order 2019 — £90,000 threshold; domestic reverse charge for construction services; reduced rates on conversions and renovations
Employers' Liability (Compulsory Insurance) Act 1969 — compulsory from the first employee
Health and Safety at Work etc. Act 1974; Work at Height Regulations 2005 (SI 2005/735); Control of Asbestos Regulations 2012 (SI 2012/632); Control of Substances Hazardous to Health Regulations 2002 (SI 2002/2677) — site duties
Environmental Protection Act 1990, s.34 — duty of care for waste; registered carriers and transfer notes
BS 8000-0:2014+A1:2024 — workmanship on construction sites; general principles
JCT Building Contract for a Home Owner/Occupier and FMB domestic contracts — standard-form domestic contracts naming day-work rates and stage payments
Consumer Rights Act 2015, Part 1 Chapter 4 — services — reasonable price and reasonable care and skill
HMRC — Construction Industry Scheme: a guide for contractors and subcontractors (CIS 340) — registration, verification and deductions
HSE — CDM 2015: Construction work on domestic premises — duties on domestic projects
HMRC — VAT reverse charge for building and construction services — when the reverse charge applies
Planning Portal — Permitted development rights for householders: technical guidance — extension limits
Federation of Master Builders — Pricing and contracts guidance — industry body
pricing labour — the cost-based pricing method and baseline rates by trade
day rate to hourly rate calculator — converting between day rate, hourly rate and billable hours
labourer day rate guide — the labourer inside the builder's team
bricklayer day rate guide — the per-thousand and per-m² rates the builder prices in
carpenter day rate guide — the carpentry trade priced the same way
cis tax explained — CIS as a contractor
managing subcontractors — running the trades on a job
domestic reverse charge vat guide — VAT between CIS businesses
quotes vs estimates — fixed prices, day-work rates and variations
markup to margin explained — what the OHP percentage means in margin