Summary

Retention is the construction industry's standard mechanism for giving clients security that defects will be fixed. The client withholds a small percentage of every interim payment and only releases the held money in two stages — half when the work is substantially complete, the other half once any defects identified during the rectification period have been put right. On paper this is sensible: it incentivises the contractor to finish properly and to respond to defect notices.

In practice, retention is one of the most contentious areas of construction finance, especially for sub-contractors and smaller firms. Money that has been earned is held back, often for 12–24 months, by clients who may go insolvent, dispute defects, or simply refuse to release the funds without a fight. Industry research (BEIS 2017) estimated that £700–900 million of retention money is lost to construction firms each year through delayed release and upstream insolvency. The Construction (Retentions) Bill — first introduced in 2018 and revived in subsequent parliamentary sessions — proposes a statutory retention deposit scheme to ring-fence retention money, but at the time of writing it has not become law.

For a sole trader or small builder, the priority is to know exactly what your contract says about retention, what your statutory rights are under the Construction Act, and to invoice and chase retention with the same discipline as any other payment. Forgetting to invoice retention is the most common reason it never gets paid.

Key Facts

Quick Reference Table

Spending too long on quotes? squote turns a 2-minute voice recording into a professional quote.

Try squote free →
Contract Default Retention At PC At DRP End
JCT Standard Building Contract 2024 3% 1.5% released 1.5% released
JCT Intermediate Building Contract 2024 3% 1.5% released 1.5% released
JCT Minor Works Building Contract 2024 5% during, 2.5% after PC First half released Balance released
JCT Design and Build Contract 2024 3% 1.5% released 1.5% released
NEC4 ECC (Option X16) As stated in Contract Data First half at PC Balance at end of defects period
FIDIC Red Book As stated First half Balance
Subcontracts (back-to-back) Often mirrors main contract Mirrors Mirrors
Construction Act 2011 — Key Deadlines (Default Scheme)
Interim payments every 28 days
Payment due date: 17 days after payment application
Final date for payment: 17 days after due date
Pay-less notice: at least 7 days before final date for payment
Suspension notice: 7 days after non-payment
Adjudication: 28 days from referral

Detailed Guidance

How retention is deducted

Retention is deducted from each Interim Payment (also called Application for Payment, Payment Notice or Stage Payment). Worked example using JCT default 3%:

Interim Application:           £20,000.00
Less retention 3%:                -£600.00
Net interim payment:           £19,400.00

This continues for the duration of the works. By PC, the accumulated retention represents 3% of the contract sum. At PC, half (1.5% of the total) is released. The other half stays with the client through the Defects Rectification Period.

Practical Completion and the first release

Practical Completion is the point at which the works are substantially complete and ready for use, despite minor outstanding defects (snagging). The contract administrator issues the Certificate of Practical Completion. Under JCT, this triggers:

The contractor should issue an invoice for the first half of retention immediately after PC. Do not assume the client will pay automatically — many small contractors lose retention simply because they forgot to ask.

Defects Rectification Period

During the DRP (commonly 12 months), the contractor remains liable for defects in their work. The contract administrator typically issues a schedule of defects within 14 days of the end of the DRP. Contractor has a reasonable period to make good. Once made good, the contract administrator issues a Certificate of Making Good Defects.

This certificate triggers release of the balance of retention.

Invoicing retention — practical steps

Retention does not invoice itself. Process:

  1. Track retention from day one. On every interim valuation, record the retention deducted. Maintain a running total.
  2. Diary PC and DRP end dates. When the Certificate of Practical Completion is issued, calendar the date and the DRP end date.
  3. First retention invoice — at PC. Issue an invoice for 1.5% of contract sum (or whatever the contract specifies) immediately after the Certificate of Practical Completion. Reference the certificate.
  4. Snagging — fix promptly. Address defect notices quickly to avoid disputes at DRP end.
  5. Second retention invoice — at DRP end. When the Certificate of Making Good is issued, invoice for the balance. Reference the certificate.
  6. Chase via payment notices. If payment is not made by the final date, issue an unpaid notice and consider adjudication or suspension.

Payment notice and pay-less notice regime

The Construction Act 2011 requires every payment to follow a notice timetable:

If the payer does not issue a payer's notice or pay-less notice, the contractor's notified sum becomes the "notified sum" and is payable in full. This is the strongest statutory tool the contractor has — clients who try to withhold retention without a pay-less notice are in breach of the Act.

When the client refuses to release retention

Common scenarios and responses:

Adjudication — the contractor's tool

Adjudication is a statutory right under HGCRA Section 108. Either party can refer a dispute to an adjudicator at any time. Key features:

Cost of adjudication is normally £5,000–£15,000 in adjudicator's fees plus legal costs. Suitable when retention amount justifies the spend.

Suspension for non-payment

Under HGCRA Section 112, the contractor can suspend performance after 7 days' written notice of non-payment. The contractor is entitled to:

Suspension is a powerful tool but rarely used by small contractors due to relationship damage. Adjudication is generally preferred.

Retention bonds as an alternative

Instead of cash retention, the contract can provide for a retention bond — a guarantee from a bank or surety company for the equivalent amount. The contractor pays an annual premium (typically 1–2% of the bonded amount). Cash flow benefit: full payment is received now, with the bond providing the security.

Retention bonds are common on projects above £1m. For smaller works, the bond cost often exceeds the cash flow benefit.

Domestic clients — HGCRA exemption

HGCRA Section 106 excludes contracts with residential occupiers (a person who occupies the dwelling as a residence). For these contracts:

For homeowner work, agree retention terms in writing before starting. Many builders avoid retention altogether on domestic work and instead offer a 12-month workmanship guarantee.

Frequently Asked Questions

Can I refuse to accept retention in my contract?

Yes, retention is a contractual matter — there is no legal requirement to accept it. In a tendering situation, you can quote on a no-retention basis, perhaps with a workmanship guarantee, retention bond or higher price to reflect the risk. Whether the client accepts is up to them.

Do I need to invoice retention separately?

Yes. Retention is a discrete payment with its own due date and triggers. Issue separate invoices for first and second retention releases, each referencing the relevant certificate (PC certificate, Certificate of Making Good). VAT becomes due at the point of retention release, not the original work.

What if the client goes insolvent before retention is released?

This is the single biggest risk with cash retention. Retention money is part of the client's general assets and ranks as an unsecured debt in insolvency. Practical mitigations: prefer retention bonds, require retention to be held in a trust account (some public-sector contracts do this), or negotiate no retention with appropriate pricing.

Can the client deduct more than the agreed retention?

Only by issuing a valid pay-less notice within the prescribed period before the final date for payment. Without a pay-less notice, the notified sum is payable in full. If the client issues a pay-less notice, the contractor can dispute it via adjudication.

How long can retention be held?

Until the Defects Rectification Period ends and defects are made good. JCT default DRP is 6 or 12 months depending on the form. If the contract specifies 24 months, the client can hold for that period. Retention held beyond the contractual period without justification is a breach and can be claimed back via adjudication.

Is retention taxable income before it is paid?

For most contractors using accrual accounting, retention is recognised as income when the work is done, even though cash is not yet received. This means tax may be payable on retention before the cash arrives. Cash-accounting basis (available to small businesses under thresholds) defers the tax until cash is received. Consult an accountant.

Regulations & Standards