Summary
Most domestic EV charger installations are straightforward: a wall-mounted charger fitted close to the consumer unit with a short first-fix cable run. But a meaningful minority — detached garages, charging posts positioned on a driveway away from the house, or properties where the consumer unit sits on the opposite side of the building from where the car is parked — need a buried SWA (steel wire armoured) cable run, and that is a groundworks job as much as an electrical one. Pricing this correctly matters because groundworks cost scales with ground type and surface finish, not with cable length alone, and getting it wrong either prices the installer out of the job or eats the entire margin on reinstatement.
The core pricing driver is what sits above the cable route, not the cable itself. A 10m run through a lawn is a half-day job with a spade and a narrow trencher. The same 10m run through a block-paved driveway requires lifting and storing the blocks, cutting a trench through the sub-base, laying the duct, backfilling to the correct compaction, and relaying the blocks to match the existing pattern — several times the labour and a material cost for sub-base reinstatement that the lawn job doesn't have.
This guide covers groundworks pricing specifically; for the electrical side of the installation (charger unit, consumer unit work, DNO notification) see ev charger pricing guide and domestic ev charger installation process.
Key Facts
- Trench depth for SWA cable — minimum 450-600mm in domestic garden ground, per BS 7671 guidance on buried cable protection; deeper (600-750mm) where the route crosses a driveway subject to vehicle loading
- Cable protection — SWA cable buried direct is standard practice for EV charger runs; a route under a driveway or where future digging risk is higher often adds marker tape 150mm above the cable and/or ducting for future-proofing
- Duct option — running SWA inside a pre-laid duct (typically 50mm or 63mm) rather than direct burial adds £3-£8/m in material but allows future cable replacement without re-digging; recommended on any route under hard landscaping
- BS 7671 Section 722 — specific requirements for EV charging equipment installations, including cable routing and protection against mechanical damage
- Soft ground trenching — £35-£75/m; includes digging, cable laying, backfill and turf/soil reinstatement
- Hard standing trenching (block paving) — £80-£150/m; includes lifting and storing blocks, cutting sub-base, laying cable/duct, compacting backfill, relaying blocks
- Hard standing trenching (tarmac/concrete) — £100-£180/m; includes breaking out surface (disc cutter), excavation, cable/duct laying, backfill compaction, and either cold-lay tarmac patch or concrete reinstatement — full matching reinstatement (colour/texture match) can cost more
- Mini-digger vs hand-dig — a mini-digger or trenching attachment speeds up longer soft-ground runs significantly but needs vehicle access to the garden; hand-digging is standard for short runs or access-restricted sites
- Service strikes — always carry out a CAT and Genny scan before digging to identify existing gas, water, or other electrical services — see site survey setting out; a struck gas or water service on a "simple" EV charger trench turns a profitable job into a loss-making one
- Reinstatement standard matters for price — a cold-lay tarmac patch is cheaper and faster than a hot-lay match, but will visibly differ from the surrounding surface; always agree the reinstatement standard with the customer in writing before starting, particularly on block paving where exact colour/batch match may not be possible
- Driveway crossing depth — where a trench crosses an area subject to vehicle loading (driveway, parking area), increase cover depth to 600-750mm and consider a protective concrete or paving slab above the cable/duct as additional mechanical protection
- Cable sizing — SWA cable size for the run is determined by distance (voltage drop) and load, typically 6mm² or 10mm² for a 32A 7kW charger circuit — see ev charger cable sizing calculator; groundworks pricing is independent of this but the trench must accommodate the specified cable's bend radius
- Combined quoting — groundworks should always be quoted as a distinct line item separate from the electrical installation, so the customer can see what they're paying for access versus equipment, and so a site survey revealing harder ground doesn't require re-quoting the whole job
- Permitted development — groundworks for a charger trench on private land within the curtilage does not normally require planning permission; crossing a public footpath or highway verge to reach a detached garage may require a street works licence from the local highway authority — always check before trenching across a pavement
Quick Reference Table
Spending too long on quotes? squote turns a 2-minute voice recording into a professional quote.
Try squote free →| Route Type | Length | Trenching Cost | Notes |
|---|---|---|---|
| Lawn/border, short run | 5m | £175-£375 | Hand-dig, turf reinstatement |
| Lawn/border, longer run | 15m | £525-£1,125 | Mini-digger viable if access allows |
| Block paving, short run | 5m | £400-£750 | Block lift/store/relay included |
| Block paving, longer run | 15m | £1,200-£2,250 | More blocks to lift/store; higher labour |
| Tarmac driveway | 5m | £500-£900 | Disc cut, cold-lay patch reinstatement |
| Tarmac driveway | 15m | £1,500-£2,700 | Larger reinstatement area |
| Concrete driveway | 5m | £550-£950 | Breaking out + concrete reinstatement |
| Mixed route (lawn + paving crossing) | 10m total | £600-£1,400 | Priced per metre by surface type crossed |
| Public footpath crossing | varies | £800-£2,500+ | Street works licence + reinstatement to highway authority spec |
Detailed Guidance
Surveying the route before quoting
The single biggest cause of underquoted EV charger groundworks is pricing from a verbal description rather than a site visit. Before quoting, walk the actual route and note: total length, surface type at each section (lawn, border, paving, tarmac, concrete, gravel), any existing services likely to be crossed (run a CAT scan if there's any doubt), access for a mini-digger if the run is long, and whether the route crosses any area subject to vehicle loading. A route that looks like "15m across the garden" on a phone call can turn out to be 15m of which 4m crosses a block-paved patio — price each surface type separately.
Trenching process — soft ground
- Mark out the route and confirm no services present via CAT/Genny scan.
- Excavate to minimum 450-600mm depth, width sufficient for cable/duct plus hand clearance (typically 150-200mm wide).
- Lay 50mm of soft sand or sieved soil bedding at the trench base.
- Lay the SWA cable (or duct containing the cable) with gentle bends respecting minimum bend radius.
- Lay cable marker tape approximately 150mm above the cable.
- Backfill in layers, compacting as you go, reserving topsoil/turf for final reinstatement.
- Re-lay turf or reseed as agreed with the customer.
Trenching process — hard standing (block paving)
- Mark out the route and confirm no services present.
- Lift blocks along the route, keeping them in order where a pattern must be matched, and store safely.
- Excavate through the sub-base to the required depth.
- Lay bedding, cable/duct, and marker tape as per soft-ground method.
- Backfill and compact the sub-base layer (Type 1 MOT or equivalent) to match the original specification — under-compaction here causes a visible dip in the paving months later, a common comeback.
- Relay the sand bedding layer and refit the blocks, re-compacting with a plate vibrator and re-sanding joints.
Trenching process — tarmac or concrete
- Mark out and confirm no services present.
- Cut the surface cleanly with a disc cutter along the trench line to avoid ragged breakout edges.
- Break out and excavate to the required depth.
- Lay bedding, cable/duct, and marker tape.
- Backfill and compact the sub-base.
- Reinstate the surface: cold-lay tarmac patch (cheaper, faster, visible colour difference) or hot-lay/professional resurface (better match, higher cost, often subcontracted to a surfacing specialist); for concrete, pour and finish to match existing texture, allowing appropriate cure time before the area takes traffic.
Pricing the reinstatement standard explicitly
Always specify in the written quote exactly what reinstatement standard is included — "cold-lay tarmac patch, colour may not exactly match existing surface" is a very different promise to the customer than "full resurface to match." Disputes over reinstatement quality are one of the most common post-completion complaints on this job type, and a clear written scope avoids them.
Worked example — detached garage, mixed route
Job: 7kW charger on a detached garage, 12m run from the house consumer unit — 4m across a lawn, 5m across block-paved driveway, 3m across a short section of tarmac at the garage apron.
- Lawn section (4m): £140-£300
- Block paving section (5m): £400-£750
- Tarmac section (3m): £300-£540
- Groundworks subtotal: £840-£1,590
- Electrical installation (charger, circuit, SWA cable, testing) quoted separately per ev charger pricing guide
Frequently Asked Questions
Can I avoid groundworks cost by running the cable overhead instead of underground?
In some cases, yes — an overhead SWA run between buildings is permitted where the span, height clearance and support points are appropriate, and it avoids trenching cost entirely. However, overhead runs are rarely acceptable where the span crosses a driveway (vehicle height clearance, visual impact) or where the customer wants a tidy finish, so underground remains the default for most detached garage and driveway charger installs.
Do I need a street works licence to trench across a public footpath to reach a garage?
Yes, if the route crosses land outside the property's curtilage — a public footpath or verge — a street works licence (sometimes called a section 50 licence) from the local highway authority is required before digging, along with reinstatement to the authority's specification, which is typically a higher standard (and cost) than private driveway reinstatement. Always check this at quoting stage, as the licence process can add several weeks' lead time.
How do I avoid under-quoting the reinstatement on block paving?
Walk the route and count roughly how many blocks will need to be lifted, and check whether the existing blocks are a common pattern/colour likely to be relaid cleanly, or an older/discontinued style where exact joint-line matching will take longer. Always price reinstatement as a separate line so a harder-than-expected relay doesn't eat into the trenching margin.
Is 450mm trench depth always sufficient, or does it depend on the surface above?
450-600mm is the typical minimum for garden ground; increase to 600-750mm under any area subject to vehicle loading such as a driveway or parking area, and consider additional mechanical protection (a paving slab or duct) above the cable on vehicle-loaded routes. Always refer to BS 7671 Section 722 guidance and the cable manufacturer's installation instructions for the specific cable being used.
Regulations & Standards
BS 7671:2018+A4:2026 Section 722 — requirements specific to electric vehicle charging installations, including cable protection and routing (A4:2026 consolidates the prior A2:2022/A3:2024 amendments, which withdraw 15 October 2026)
Building Regulations Part P — the electrical connection (not the trenching itself) is notifiable
Health and Safety at Work etc. Act 1974 / HSG47 — avoiding danger from underground services; always scan before digging
Highways Act 1980 — governs street works licensing for any excavation crossing a public highway or footpath
HSE — Avoiding danger from underground services (HSG47) — HSE
BS 7671 IET Wiring Regulations — IET, Section 722 EV charging requirements
gov.uk — Street works and excavations — licensing for works on the public highway
ev charger pricing guide — full EV charger installation pricing including the electrical side
domestic ev charger installation process — end-to-end installation process including survey and commissioning
site survey setting out — CAT/Genny scanning and service avoidance before any excavation
trench safety guide — trench safety requirements, though scaled for domestic-depth EV charger trenches rather than deep excavation
ev charger cable sizing calculator — cable sizing for the buried SWA run