Site Survey and Setting Out: A Groundworker's Guide

Quick Answer: Setting out transfers the positions shown on drawings to physical pegs and profiles on site. It must be accurate to the building's design dimensions — errors in setting out propagate through the entire build and are expensive to correct later. Use a total station or laser level for accuracy; builder's squares and profile boards for control. Check your datum point, confirm the OS grid reference with the client's drawings, and verify the building's relationship to the site boundary before driving the first peg.

Summary

Setting out is one of the most critical early tasks on any construction site and one of the most commonly rushed. A 50mm error in the position of a foundation, an out-of-square corner, or a slab 100mm too high can mean thousands of pounds in remedial work once the build has progressed. Building inspectors will check finished foundation sizes and depths; a building that is significantly out of position relative to the planning permission boundary can trigger enforcement action.

The principles of setting out are straightforward — the challenge is the rigour required to apply them correctly. Every dimension must be checked twice, from a known datum, with tolerances understood. The basic tools are a tape measure, builder's square, and boning rods, but a laser level and total station make the job significantly faster and more accurate.

For groundworkers, competent setting out is a genuine skill that justifies a premium. The ability to set out from a drawing independently, without relying on the main contractor or structural engineer to hold your hand, marks the experienced operator from the beginner.

Key Facts

Quick Reference Table — Common Setting Out Equipment

Spending too long on quotes? squote turns a 2-minute voice recording into a professional quote.

Try squote free →
Equipment Use Accuracy Cost Range
Builder's square (300mm) Internal right angles, profiles ±2mm/m £10–30
Tape measure (50m) Distance measurement ±3–5mm over 20m £20–80
Laser level (rotating) Horizontal datum transfer ±1–2mm/10m £80–400
Builder's optical level Long-range levelling ±2–5mm £80–250
Total station Combined angles + distances ±2–5mm absolute £2000–15,000
GPS survey unit Site coordinates from OS grid ±10–50mm £500–3000
Plumb bob Vertical transfer ±1mm £5–20
Boning rods (3 off) Gradient/level checking Visual £30–80/set
String line Alignment over distances ±3–5mm £5–20

Detailed Guidance

Setting Up the Site Datum (TBM)

The temporary benchmark (TBM) is the height reference for the entire site. It must be:

Transfer the OS benchmark level to your TBM using a level and staff. Book the readings in a level book (BSB method: backsight, intermediate sight, foresight) and calculate the height of instrument (HI) at each instrument position. Check your arithmetic: sum of backsights minus sum of foresights must equal first RL minus last RL.

Reading a Topographic Drawing

Before setting out, extract from the drawings:

Establishing Building Lines

For a rectangular building, you need four corners accurately positioned. Method using profile boards:

  1. Mark one corner — from the site boundary or a fixed reference, measure the dimension shown on the drawing to your first building corner. Drive a peg.
  2. Set the first building line — drive profile boards 1.2–1.5m beyond each end of the first wall, aligned with the first corner peg. Stretch a string line between them.
  3. Set the first perpendicular — use the 3-4-5 method or a builder's square to set a second string line at exactly 90°. Check: measure 3m along wall 1, 4m along wall 2; the diagonal between these two points must be exactly 5m. For large buildings, use multiples (6m-8m-10m or 9m-12m-15m) for better accuracy.
  4. Set the remaining corners — measure the building dimensions along the two control lines to establish corners 3 and 4.
  5. Check the diagonals — measure both diagonals of the building rectangle. They must be equal. Calculate what they should be from the drawing: diagonal = √(width² + length²). An out-of-square building within 10mm of the calculated diagonal is acceptable.
  6. Mark profile boards — for each wall, mark the face of the wall on the profile board using a saw cut; also mark offsets for the centre of the foundation trench. These reference marks allow the string lines to be re-set after excavation.

Levelling for Foundation Depths

With the TBM established and the FFL known, calculate the required foundation formation level:

Set up a level over the TBM area. Take a backsight reading on the TBM staff to establish height of instrument (HI). Calculate the required staff reading at formation level: staff reading = HI − required RL. Use a boning rod set in the trench to indicate when the correct depth has been reached. Alternatively, use a laser level set to the HI and scan the trench.

Check foundation depth at each corner and midspan of each strip before proceeding — Building Control will inspect at this stage.

Using a Laser Level for Setting Out

A rotating laser level makes levelling operations significantly faster and removes the need for a second person to hold a staff. Set up:

  1. Level the instrument (self-levelling types do this automatically within ±5°)
  2. Set the instrument height over the TBM: hold a staff on the TBM, observe the laser line on the staff, record the reading (e.g. 1.530m above TBM)
  3. Calculate target staff readings at each point: required reading = TBM RL + instrument reading − required RL
  4. Move the staff to each survey point and adjust until the laser line reads the target value

Laser levels are affected by bright sunlight outdoors; use a laser detector (receiver) clipped to the staff for outdoor work in daylight.

Common Setting Out Errors and How to Avoid Them

Error Cause Prevention
Wrong datum used TBM level incorrect or misread Always check transfer from OS benchmark with two independent readings
Accumulated tape errors Tape stretched or not read flat Use a steel tape, pull taut, read at the same end as the zero
Out-of-square building 3-4-5 rule applied without checking diagonal Always check both diagonals; compare to calculated value
Wrong north orientation Drawing north ≠ magnetic north Confirm orientation from site boundary, not compass
Profile board shift Unsecured pegs moved by plant Drive 50×50mm stakes 450mm into ground; recheck before excavation
Wrong RL used FFL from drawing not confirmed Confirm FFL and datum reference with engineer before setting out levels

Frequently Asked Questions

Do I need a surveyor to set out my building?

For simple domestic extensions and new dwellings, a competent groundworker with the right equipment can set out the foundations. For anything that requires OS coordinate accuracy (e.g. the precise position of a building on a large plot), a new-build where the planning permission specifies exact setback distances, or where the boundary is disputed, a specialist land surveyor with a total station and GPS kit should carry out the initial control survey. The cost is £200–600 for a typical domestic setting out survey — cheap insurance against position errors.

How accurate does setting out need to be?

BS 8000 Part 1 specifies ±10mm positional accuracy for residential buildings. In practice, the structural engineer and Building Control will accept ±20–25mm for foundation positions. For the building position relative to the boundary, check the planning condition — some permissions specify setbacks to ±100mm; others are less prescriptive. The closer to boundaries or planning limits, the more precise you need to be.

What if the ground isn't level and I'm reading gradients?

All height references must be reduced levels — height above the site datum, not height above the sloping ground surface. On sloped sites, use a level and staff (or laser level) to transfer reduced levels to all areas of the site. Do not measure depths from the existing sloping surface unless explicitly shown that way on the drawings.

Regulations & Standards