Summary
A 1m³ block of saturated clay weighs about a tonne. A trench wall collapse drops several tonnes of soil onto a worker faster than they can react and creates pressures that prevent the chest expanding — death by asphyxia, not crushing, is typical. HSE statistics put trench-related fatalities at 1–3 per year in UK construction, every one of them preventable.
The CDM Regulations 2015 require the contractor to plan and manage excavation work, and Regulation 22 specifically covers the safety of excavations. The Health & Safety at Work etc. Act 1974, the Construction Design and Management Regulations 2015 and HSE guidance HSG150 set the framework. PUWER (Provision and Use of Work Equipment Regulations 1998) covers trench boxes and shoring as work equipment.
The decision on shoring type is driven by depth, soil type, ground water, adjacent loading and how long the trench will be open. A 1.5m deep trench in a back garden for a drain run is a fundamentally different problem to a 3m service trench in a town centre street.
Key Facts
- Trigger depth for support — 1.2m typical (HSG150); below this, battering may be used; ground type and conditions still apply
- Maximum unsupported depth — never go below 1.2m without shoring or battering in any ground
- CDM Regulations 2015 — Reg 22 (excavations), Reg 23 (cofferdams and caissons)
- HSG150 — Health and safety in construction; principal HSE guidance
- HSG185 — Health and safety in excavations
- BS 5975:2019 — Code of practice for temporary works procedures and the permissible stress design of falsework
- BS EN 13331 parts 1–2 — Trench lining systems
- Battering angle — typically 45° in stable ground, flatter in soft ground (sometimes 1:1.5 V:H)
- Stepping (benching) — stepped excavation reducing wall height in each tier
- Trench box — modular steel shoring, typically 2–6m long, hydraulic struts
- Hydraulic shores — vertical waling + hydraulic strut, for narrow trenches
- Close-boarding — timber lagging held by walings and props, used in soft / saturated ground
- Spoil set back — minimum 1m from trench edge (HSG185 recommendation); heavier plant further
- Access — ladder secured, extending 1m above trench edge, max 7m vertical (BS 1129)
- Inspection — at start of every shift, after any incident, after any disturbance — recorded in writing
Quick Reference Table
Spending too long on quotes? squote turns a 2-minute voice recording into a professional quote.
Try squote free →| Depth | Ground Conditions | Typical Support |
|---|---|---|
| 0–1.2m | Stable, dry | Optional — battering if loose |
| 1.2–2.0m | Stable, dry | Trench box or hydraulic shores; or battered 45° |
| 1.2–2.0m | Soft / wet | Close-boarded timber or trench box |
| 2.0–3.0m | Any | Trench box (hydraulic) or piled support |
| 3.0–6.0m | Any | Designed temporary works — engineer involvement |
| >6.0m | Any | Specialist piling / cofferdam |
Detailed Guidance
Risk assessment before any dig
The Construction Phase Plan (CPP) under CDM 2015 should list excavation hazards specific to the site:
Excavation Risk Assessment Checklist
□ Depth and length of trench planned
□ Soil type (cohesive clay / granular / made ground / fill)
□ Ground water expected? (test bore / observation pits)
□ Buried services? (CAT and Genny scan; LSBUD plans)
□ Adjacent loading? (walls, plant, traffic, stockpiles)
□ Duration of works (longer = more risk)
□ Weather forecast (rain triples collapse risk)
□ Access for inspection and rescue
□ Confined space considerations if deep + narrow
□ Public exposure (footpath, schoolchildren)
A documented risk assessment, signed and dated, is required — verbal assessments are not compliant.
Battering and stepping
The simplest method of preventing collapse is to cut the trench wall back to a stable angle so that gravity holds the soil rather than vertical face resisting it.
- Battering — sloping the trench wall continuously at a safe angle (45° in firm ground; flatter in soft)
- Stepping (benching) — cutting the trench in horizontal steps each higher tier set back from the lower
Battering needs space — a 2m deep trench needs 2m of additional excavation each side at 45°. On confined sites this is often not possible and shoring is used instead.
Trench boxes
A trench box is a pair of vertical steel sheets (panels) connected by horizontal struts, lowered into the trench either by excavator or pre-set onto the bucket. The box protects workers inside the box from collapse outside it.
Installation:
- Excavate to depth 1m, then lower the box partially
- Continue excavating inside the box, pushing it down as ground is removed (push-in method) or
- Excavate the full trench length, then lift the box in (trench-and-shield method)
- Maintain at least 600mm freeboard above ground level
- Brace against differential ground pressure — boxes need ground contact both sides
Trench boxes do not stop ground above the box collapsing, only ground at the level of the box. If you stand a tall worker in a deep trench with a low box, their head and chest are unprotected.
Hydraulic shores
For narrower trenches (e.g. service trenches), hydraulic shoring uses vertical aluminium walings spanning the full depth, held apart by hydraulic struts. Quick to install, lightweight, but limited in groundwater and in long trench runs.
Close-boarded timber shoring
For soft, saturated or noisy (vibrating) ground, close-boarded timber shoring fills any voids and supports the trench face continuously. Construction uses:
- Vertical timber poling boards (50 × 250mm planks)
- Horizontal timber walings holding boards back
- Hydraulic or screw-jack struts across the trench
Slower to install but the most adaptable system for difficult ground. Specified to BS 5975.
Inspection regime
HSG185 requires a competent person to inspect before each shift, after weather events, after any incident or sudden movement, and at intervals not exceeding 7 days. The inspection record covers:
- Stability of trench walls and supports
- Spoil heap position
- Access (ladder secured, in good condition)
- Plant operating clearances
- Loading on edges (vehicles, materials)
The inspection is recorded in a written report (HSE Form F91 or equivalent), kept on site and accessible to HSE inspectors on request.
Adjacent structures
A trench next to a wall, road or other structure transfers load to the trench wall. The angle of influence is typically 1:1 from the bottom edge of the loaded surface — any trench inside this zone must have designed support, not nominal shoring.
For trenches deeper than 1.5m within 5m of any structure, treat the support as designed temporary works requiring engineer's input.
Ground water
Water in the trench is a stability hazard:
- Saturated ground exerts hydrostatic pressure on shoring (effectively double the dry pressure)
- Free water in the trench bottom can wash out fines and undermine supports
- Pumping is usually needed: typical 50mm submersible pump set in a sump
- Severe inflow may need well-pointing or design ground freezing — specialist
Never enter a trench where water level is rising faster than it can be pumped.
Manual handling and confined space
- Trenches deeper than 1.2m and less than 1m wide can become confined spaces in HSE terms (limited entry/exit, oxygen deficiency risk, gas accumulation)
- Confined Space Regulations 1997 may apply; risk assessment is mandatory
- Gas detector (4-gas: O₂, CO, CH₄, H₂S) carried by anyone entering
- Communication and rescue plan; never lone working in a deep trench
Public exclusion
Heras fencing or similar 1.8m mesh fencing around the work area; chapter 8 (DfT) signage on public highway works; pedestrian routes clearly diverted. The minimum offset for pedestrian barriers from a trench edge is generally 1m — but 2m or more on busy public routes.
Frequently Asked Questions
Do I need shoring at 1.2m exactly?
Below 1.2m, shoring is required unless the trench walls are battered or stepped to a safe angle. The 1.2m trigger is a rule of thumb; if the ground is unstable, shoring may be needed at lesser depths. HSG185 is clear that risk is assessed on the actual ground conditions, not depth alone.
Can I dig a 1.5m trench without a trench box if I work fast?
No. The work-fast-and-leg-it approach is a common excuse for trench fatalities. Even a few seconds inside an unprotected 1.5m trench is unacceptable risk. The CDM Reg 22 duty is absolute — the trench must be supported. Quick jobs use quick-install shoring (hydraulic shores, trench boxes).
What's the legal minimum trench inspection frequency?
CDM Reg 22(3) requires inspection by a competent person at the start of every shift, after any event likely to have affected its strength or stability (rain, frost, vibration), and after any unintentional fall of rock, earth or other material. Inspections must be recorded in writing.
What's a "competent person" under CDM?
Someone with sufficient training, skills, knowledge and experience to identify hazards and risks. For trench inspection this usually means a site manager or supervisor with CITB site management training and demonstrable experience of excavation work. SMSTS (Site Management Safety Training Scheme) is the typical baseline qualification.
Can a mini-digger collapse a trench wall?
Yes — vibration from tracking plant near the edge induces wall failure, particularly in loose granular soils. The HSE rule of thumb is to keep plant tracks at least the depth of the trench back from the edge (e.g. for a 2m trench, plant 2m clear). Heavier plant needs more clearance.
Regulations & Standards
Construction (Design and Management) Regulations 2015 (CDM 2015) — Regulation 22 (excavations), Regulation 23 (cofferdams)
Health and Safety at Work etc. Act 1974 — Overarching duty of care
Confined Spaces Regulations 1997 — Applicable to deep narrow trenches
PUWER 1998 — Provision and Use of Work Equipment Regulations (covers shoring as work equipment)
LOLER 1998 — Lifting Operations and Lifting Equipment Regulations (trench boxes lifted into place)
BS 5975:2019 — Code of practice for temporary works procedures
BS EN 13331-1, 13331-2 — Trench lining systems
BS 6164:2019 — Code of practice for health and safety in tunnelling
HSG150 — Health and safety in construction
HSG185 — Health and safety in excavations
HSG47 — Avoiding danger from underground services
HSE — HSG185 Health and Safety in Excavations — Principal HSE excavation guidance
HSE — Construction (CDM) Regulations 2015 — Regulation 22 in full
British Standards Institution — BS 5975 — Temporary works code of practice
Temporary Works Forum — Industry guidance on shoring and temporary works
GroundsureLine / LSBUD — Buried service plans before digging
Construction Plant-hire Association — Trench box hire and design data
cdm regulations groundworks — Overall CDM 2015 framework for groundworks
foundations — Foundation trench depth and support
site survey setting out — Locating buried services pre-dig
soakaway installation guide — Soakaway pit safety
soil types and bearing capacity — Ground type and stability