The labourer is the most under-priced person on most small sites. Bricklayers, roofers and groundworkers all price their gang around a labourer at "£120 cash" and then wonder why nobody reliable turns up on a Monday. The arithmetic does not work: £120 a day for 200 days is £24,000 a year before the van, the fuel, the boots and the 20 days a year lost to rain, and no holiday pay or sick pay on top. The National Living Wage for an employed worker is £12.71 an hour from April 2026, which is £101.68 for an 8-hour day before holiday pay (another 12.07%) and employers' National Insurance — so an employed labourer on the legal minimum already costs the employer close to £125 a day. A self-employed labourer charging the same £125 is subsidising the builder.
This guide builds a labourer's day rate from real 2026 costs, gives the regional market figures for general and skilled labour, explains the CIS and employment-status rules that decide who deducts what, and shows how a trade that hires a labourer should price them into a gang rate so the labourer is paid properly and the business still makes money. It is written for the labourer setting their own rate and for the tradesperson pricing a gang; the two sums are the same sum from opposite ends.
For the method behind every rate guide see pricing labour; for converting day and hourly figures see day rate to hourly rate calculator; for the gang rates that labourers sit inside see bricklayer day rate guide and roofer day rate guide.
Key Facts
- General labourer day rate, 2026 — £120–£180 regionally; £140–£200 South East; £160–£230 London, self-employed, 8 hours, own PPE and CSCS card
- Skilled or ticketed labourer — £170–£260: CPCS/NPORS dumper, roller, telehandler or excavator (under 10 t) tickets, abrasive wheels, confined space, banksman, asbestos awareness plus experience; a groundworks ganger is at the top of that range or above
- Hourly equivalent — £15–£28, derived from the day rate ÷ 8 hours; labourers are normally paid for the full day on site, not 6.5 billable hours like a trade quoting its own work
- National Living Wage (21+) — £12.71 an hour from 1 April 2026; the floor for employed labour, not a guide for self-employed rates
- Employed labourer true cost — NLW £101.68 a day + 12.07% holiday accrual + employers' NI at 15% above the £5,000 secondary threshold + pension auto-enrolment 3% + employers' liability insurance ≈ £125–£135 a day at the legal minimum
- CIJC Working Rule Agreement — the employed construction general operative rate sits a little above the NLW, with skilled-operative grades above that; useful as a floor for what a contractor pays employed labour
- Billable days — 200–215 a year for a labourer on a long contract; 180–200 for one picking up work from several trades with gaps between jobs
- Half-day minimum — £70–£110; a four-hour clear-up or a skip load is a half day with the travel
- Overtime — Saturdays at time-and-a-quarter to time-and-a-half, Sundays and bank holidays at double is the site norm; agree it before the first weekend
- CIS — a labour-only subcontractor working for a contractor is paid under the Construction Industry Scheme: 20% deducted if registered, 30% if not; domestic work direct for a homeowner is outside CIS; see cis tax explained
- Employment status — one builder, every day, told what to do and when, no right to send a substitute, no financial risk = employee for tax and employment rights, however the pay is labelled; HMRC's CEST tool gives a determination both sides can keep
- Agency labour — the agency charges the contractor £20–£32 an hour for a general operative and pays the worker a fraction; after 12 weeks the Agency Workers Regulations 2010 give equal pay and conditions with a comparable directly employed worker
- CSCS Green Labourer card — needs the Level 1 Award in Health and Safety in a Construction Environment (or equivalent) plus the CITB Health, Safety and Environment test; valid 5 years; most sites will not admit a labourer without one; see cscs card guide
- Manual handling — HSE guideline figures of 25 kg for a man and 16 kg for a woman lifting close to the body at waist height, reduced for reach, height and frequency; a 25 kg bag of cement is at the limit, not below it
- PPE — the employer or contractor provides PPE free of charge under the Personal Protective Equipment at Work Regulations 1992 (as amended 2022, which extended the duty to limb (b) workers); a self-employed labourer provides their own, which is in the rate
- Insurance — public liability £1–£2 million, £150–£400 a year for a labourer; most sites require it before a self-employed operative is allowed on
- VAT — compulsory registration above £90,000 taxable turnover; almost no labourer reaches it; see vat registration for tradespeople
- Working Time Regulations 1998 — 48-hour average week unless opted out in writing; 5.6 weeks' paid holiday for workers and employees; a genuinely self-employed labourer has neither
Quick Reference Table
Spending too long on quotes? squote turns a 2-minute voice recording into a professional quote.
Try squote free →| Charge | Regional (outside London/SE) | South East | London | Notes |
|---|---|---|---|---|
| General labourer, day | £120–£180 | £140–£200 | £160–£230 | 8 hours, own PPE, CSCS card |
| General labourer, hour | £15–£22 | £17–£25 | £20–£28 | Full hours on site |
| Skilled / ticketed labourer, day | £170–£240 | £190–£260 | £220–£300 | Plant tickets, abrasive wheels, confined space |
| Groundworks ganger, day | £220–£300 | £250–£340 | £280–£380 | Runs the gang, sets out, reads drawings |
| Half-day minimum | £70–£110 | £80–£120 | £95–£140 | Clear-ups, skip loads |
| Saturday | ×1.25–×1.5 | ×1.25–×1.5 | ×1.25–×1.5 | Agree in advance |
| Sunday / bank holiday | ×2 | ×2 | ×2 | |
| Employed labourer at NLW, true daily cost | £125–£135 | £125–£135 | £125–£135 | Wage + holiday + NI + pension + insurance |
| Agency general operative, charged to contractor, hour | £20–£28 | £22–£30 | £24–£32 | Worker receives roughly 60–70% |
| Labourer inside a 2+1 bricklaying gang | £130–£180 | £150–£200 | £170–£230 | See bricklayer guide |
Detailed Guidance
Building the day rate from your costs
The labourer's cost base is smaller than a trade's — no £3,000 of power tools, no mixer, often no van — but it is not nothing, and the income target has to be realistic for a job that is physically harder than most trades and shorter-lived. A self-employed general labourer outside London:
| Item | Annual figure |
|---|---|
| Target income before tax | £28,000 |
| Transport: car or small van, insurance, fuel to site, parking | £4,500 |
| Public liability insurance (£1–£2 million) | £250 |
| PPE: boots (2 pairs a year), hi-vis, gloves, helmet, eye and ear protection, wet-weather gear | £450 |
| CSCS card and renewals, HS&E test, plant ticket renewals averaged | £200 |
| Phone, accountant or software, bank | £700 |
| Pension contribution | £1,500 |
| Total to recover | £35,600 |
A labourer on steady work with a couple of regular trades, losing a week or two between jobs and 15 days a year to weather, has about 195 billable days. £35,600 ÷ 195 = £183 a day to earn £28,000 before tax. At £120 a day the income before tax is about £15,800 — below the National Living Wage for the same hours once the costs are out. At £150 it is about £21,700. The regional market range of £120–£180 therefore has a bottom end that only works for someone with no transport cost and no gaps, and a top end that produces an ordinary wage. Labourers who are told £120 is "the going rate" should do this sum with the person telling them.
Employed, self-employed, agency: who pays what
The same person on the same site can be paid three ways, and the day rate means something different in each.
Employed by the contractor. The contractor pays at least the National Living Wage (£12.71 an hour from April 2026), holiday pay at 5.6 weeks a year (12.07% of hours worked for irregular-hours workers under the 2024 holiday rules), employers' National Insurance at 15% on earnings above £5,000 a year, auto-enrolment pension at 3% minimum, and carries employers' liability insurance. An employed labourer at the minimum costs the contractor £125–£135 a day; one at the CIJC general operative rate costs more. The labourer gets sick pay (SSP), holiday, a pension and employment rights. See cis vs paye employed subcontractors and taking on staff for the employer's side of that sum.
Self-employed labour-only subcontractor. The labourer invoices a day rate; the contractor deducts CIS at 20% (registered) or 30% (unregistered) from the labour element and pays the rest; the labourer settles the balance through Self Assessment. No holiday, no sick pay, no pension unless they fund it — which is why the self-employed day rate has to be 30–50% above the employed daily wage to be equivalent. HMRC's view on status does not depend on the invoice: a labourer who works for one contractor continuously, is told what to do, when and where, cannot send someone else, and takes no financial risk is an employee, and the contractor is liable for the PAYE and NI that should have been paid. The CEST tool at gov.uk gives a status determination; keep the printout.
Agency. The contractor pays the agency £20–£32 an hour; the agency employs (or engages through an umbrella) the labourer, who sees perhaps £13–£18 of it. After 12 weeks in the same role the Agency Workers Regulations 2010 give the labourer the same basic pay and conditions as a directly employed comparator. Agency labour is the expensive, flexible option for a contractor; it is rarely the best-paid option for the labourer.
Pricing a labourer into a gang or a job
For the trade hiring the labourer, the question is what to charge the customer for them. The labourer's day rate is a cost; it goes on the quote with an uplift like any other cost, not at face value.
Worked example — a two-week single-storey extension, bricklayer and labourer, outside London:
Labourer, self-employed, 10 days × £150 = £1,500
On-costs if employed instead (holiday, NI, pension,
EL insurance, ~22%) = £330 (not applicable if self-employed)
Uplift to cover supervision, days lost to weather
the labourer still invoices, and margin: 20% = £300
------
Charged to customer for the labourer = £1,800 (£180/day)
A labourer charged to the customer at £150 when they cost £150 has earned the business nothing and exposed it to the rained-off day the labourer still invoices. In a bricklaying gang the labourer appears inside the gang rate (£650–£900 regionally for 2+1), not as a separate line; on a domestic job for a homeowner the simplest honest presentation is "labour: 2 people × 10 days" with a blended daily figure. Never show a customer the labourer's actual rate and the bricklayer's actual rate side by side with no uplift — it invites the question "why am I paying for two?" and the answer is in the output, not the rate.
Skilled labour and tickets
The gap between £120 and £250 a day is tickets and the responsibility that comes with them:
| Ticket or skill | What it adds | Typical uplift on general rate |
|---|---|---|
| CPCS or NPORS forward-tipping dumper | Moves spoil and materials without the trade stopping | +£20–£40/day |
| Telehandler (CPCS A17 / NPORS N010) | Loading out a roof or a scaffold lift | +£30–£50/day |
| 360° excavator under 10 t | Footings, drainage, muck-away loading | +£40–£70/day; often priced as a plant operator, not a labourer |
| Abrasive wheels (PUWER training) | Cutting blocks, paving, steel on site | +£5–£15/day |
| Confined space (low/medium risk) | Drainage chambers, tanks | +£30–£60/day |
| Banksman / vehicle marshal | Deliveries, muck-away, crane days | +£10–£20/day |
| Asbestos awareness (Cat A) | Required on most refurb sites | Expected, not paid extra |
| Groundworks ganger | Sets out, reads drawings, runs 3–6 operatives | £220–£380/day |
The ticket itself costs £100–£600 and a day or two off the tools; a labourer should recover that inside a year from the uplift or it was the wrong ticket. Contractors who want a dumper driven and a block saw run should expect to pay for a skilled labourer, not a general one with a ticket they "picked up".
Weather, travel and the unpaid days
A labourer on an outdoor trade loses the same weather days as the trade — 15–25 a year — and unlike the bricklayer has no indoor work to fall back on. Three ways this is handled, and only one is fair: the labourer is paid for a rained-off day they turned up for (the trade's rate should carry it); the labourer is sent home unpaid at 8am (common, and the reason the day rate must be higher than the employed wage); or a half-day is paid for a turn-up. Agree it before the job. Travel to a site more than 30–40 minutes away is either in a higher rate or a mileage line; a labourer asked to be on a London site at 7:30 from the Home Counties is spending £15–£25 a day on the train, which is why the London rate carries a premium beyond the cost of living.
Putting it in writing
A one-page agreement protects both the labourer and the trade: the day rate, hours (8 on site, excluding breaks), what counts as a half day, overtime multipliers, who provides PPE and tools (self-employed: the labourer; employed: the employer, free of charge), travel, weather, CIS status and UTR, public liability cover, notice to end the arrangement, and that the labourer is free to work for others and may send a substitute — which, if it is true, is the clearest evidence of self-employment. See quotes vs estimates for the parallel on the customer side.
Frequently Asked Questions
What is a fair day rate for a labourer in 2026?
£120–£180 a day outside London and the South East for a self-employed general labourer with their own PPE and a CSCS card, £160–£230 in London, and £170–£260 for a labourer with plant tickets or running a groundworks gang. The bottom of those ranges only works for someone with no transport cost and no gaps between jobs; £150–£180 regionally is what a reliable labourer should expect from a trade that wants them back.
Is £120 a day legal for a labourer?
For a genuinely self-employed labourer there is no minimum, so yes — but it is poor pay once their costs are out, and a labourer who is in practice an employee is entitled to the National Living Wage (£12.71 an hour from April 2026) for every hour worked, plus holiday pay, whatever the day rate says. At £120 for a 9-hour day with a half-hour break, the hourly rate is £14.12, above the NLW, but with no holiday pay included; for a 10-hour day it is £12, below it.
Do I have to deduct CIS from a labourer?
If you are a contractor (a builder paying for construction work) and the labourer is a self-employed subcontractor, yes: 20% from the labour element if they are registered with HMRC, 30% if not, paid over monthly with a CIS return. A homeowner paying a labourer directly is not a contractor and deducts nothing. A labourer who is really your employee is not under CIS at all — they go on PAYE.
How many bricks or blocks should a labourer keep a bricklayer supplied with?
A good labourer keeps one bricklayer loaded out at 500–600 facings a day plus the mortar, or two bricklayers on blockwork — which is why the 2+1 gang is the standard unit. A labourer serving three bricklayers on facework is the reason the gang is slow, not the bricklayers.
Should a labourer charge for the van?
If they bring one and it carries the gang's tools, the mixer or the fuel, yes — either in the rate or as a separate daily figure of £20–£40. A labourer arriving by car to a site where the trade provides everything is charging for their labour only, and the rate reflects that.
Regulations & Standards
National Minimum Wage Act 1998 and the National Minimum Wage Regulations 2015 (SI 2015/621) — National Living Wage for workers aged 21 and over; rate set each April
Income Tax (Construction Industry Scheme) Regulations 2005 (SI 2005/2045) — deductions at source from labour-only subcontractors
Income Tax (Earnings and Pensions) Act 2003 — employment status for tax; PAYE liability where a worker is an employee in substance
Employment Rights Act 1996 — rights of employees and workers; status tests applied by tribunals
Working Time Regulations 1998 (SI 1998/1833) — 48-hour average week, rest breaks, 5.6 weeks' paid holiday for workers
Employment Rights (Amendment, Revocation and Transitional Provision) Regulations 2023 — 12.07% holiday accrual for irregular-hours and part-year workers from leave years starting April 2024
Agency Workers Regulations 2010 (SI 2010/93) — equal treatment after 12 weeks in the same role
Pensions Act 2008 — automatic enrolment; 3% minimum employer contribution
Employers' Liability (Compulsory Insurance) Act 1969 — compulsory from the first employee
Health and Safety at Work etc. Act 1974 — general duties to employees and the self-employed
Manual Handling Operations Regulations 1992 (SI 1992/2793) — assessment and reduction of manual handling risk; HSE guideline weights
Personal Protective Equipment at Work Regulations 1992 (SI 1992/2966, as amended 2022) — PPE provided free to employees and limb (b) workers
Provision and Use of Work Equipment Regulations 1998 (SI 1998/2306) — training for abrasive wheels, plant and powered equipment
Construction (Design and Management) Regulations 2015 (SI 2015/51) — skills, knowledge and training; site induction
Construction Industry Joint Council Working Rule Agreement — employed operative pay grades, for context
Value Added Tax Act 1994 — £90,000 registration threshold
National Minimum Wage and National Living Wage rates — gov.uk; current hourly rates by age
Construction Industry Scheme (CIS) — HMRC; who deducts, at what rate
Check employment status for tax (CEST) — HMRC's status tool
Agency workers: your rights — gov.uk; the 12-week rule
HSE — Manual handling at work: a brief guide (INDG143) — guideline lifting weights
CSCS — Labourer card — requirements for the Green card
pricing labour — the cost-based pricing method and baseline rates by trade
day rate to hourly rate calculator — converting between day rate, hourly rate and billable hours
bricklayer day rate guide — the 2+1 gang rate the labourer sits inside
roofer day rate guide — gang pricing on a roofing job
builder day rate guide — the general builder's rate, which prices labourers into every job