Summary
Internal wall insulation is the retrofit measure that looks like a plastering job and is priced by plasterers as one, which is how it ends up under-priced. The board goes on the wall and gets skimmed, so a plasterer sees "boarding and skimming, £35/m²" and quotes it. What that figure leaves out is the insulation thickness Part L demands, the mechanical fixings the board manufacturer requires, the preparation of a wall that has probably had 150 years of paint and wallpaper on it, the moving of every socket, radiator and pipe on that wall, the returns into every window reveal, the junction with the floor and ceiling where moisture collects, and the Building Control notification. Done properly, IWI is a multi-trade job with the plasterer in the middle of it.
It is also the measure where getting the detailing wrong creates damp that was not there before. Solid brick walls dry to the inside; put an impermeable PIR board over them and the wall behind stays colder and wetter. Joist ends built into the wall sit in the cold zone behind the insulation. A missed vapour control layer at a reveal gives interstitial condensation in three winters. None of that is an argument against IWI, which is often the only practical way to insulate a solid-walled house, but every one of those details costs time and the price has to carry it. This guide gives the 2026 build-up for the two main systems, the preparation and services lines, the regulatory thickness, a worked terrace, and the grant-funded (PAS 2035) route where the pricing rules are different. For the technical design see internal wall insulation and internal wall insulation damp risk; for the comparison with external insulation see external vs internal wall insulation comparison and external wall insulation pricing guide.
Key Facts
- Target U-value — Approved Document L Volume 1 (2021), Table 4.3: an existing wall with a U-value worse than 0.70 W/m²K that is being renovated must be brought to 0.30 W/m²K where technically, functionally and economically feasible; an uninsulated 225 mm solid brick wall is about 2.0–2.1 W/m²K
- Thickness to hit 0.30 — on a 225 mm solid brick wall: PIR-backed insulated plasterboard 72.5 mm (60 mm PIR + 12.5 mm board) gives roughly 0.28–0.30 W/m²K; 62.5 mm gives about 0.33; 92.5 mm about 0.22. Confirm with the board manufacturer's U-value calculator for the actual wall
- Insulated plasterboard, materials — 2400 × 1200 mm boards: 62.5 mm £45–£60, 72.5 mm £50–£65, 92.5 mm £65–£85 per board in 2026, which is £16–£30/m² before waste; add 10–15% waste on a room with reveals
- Fixing — dot-and-dab adhesive plus mechanical insulation fixings (minimum five per board, or per manufacturer) at £0.30–£0.60 each; continuous adhesive ribbon at the perimeter and around every opening to stop air movement behind the board
- Stud system, materials — 47 × 50 mm or 47 × 75 mm studs at 600 mm centres, 25 mm air gap to the wall or a breather membrane, mineral wool or wood fibre between studs, a VCL (polythene 500 gauge or a variable-permeability membrane) on the warm side, 12.5 mm plasterboard; £22–£40/m² in materials
- Labour, insulated plasterboard — one plasterer and a labourer fix 20–30 m² a day including cutting reveals; skim 25–35 m² a day; £25–£45/m² labour
- Labour, stud system — a carpenter frames 15–25 m² a day; insulation and VCL 30–40 m² a day; boarding and skim as above; £40–£70/m² labour
- Preparation — strip wallpaper £3–£6/m²; hack off blown or damp plaster £10–£20/m² plus disposal; remove skirting, architraves, coving, picture rails £3–£8 per linear metre; make good any damp cause first (IWI over a wet wall is a failure)
- Reveals and returns — insulate every window and door reveal with 20–30 mm insulated board or the system's reveal board; £15–£30 per reveal; a wall with three windows has 12 reveal faces
- Services — each socket or switch extended forward £40–£80 (electrician; not notifiable under Part P as it is not a new circuit, unless in a bathroom); radiator off and refitted on extended tails £80–£150 (see radiator replacement); pipe runs boxed or rerouted at cost; a wall-mounted boiler on an external wall is a different job
- Floor and ceiling junctions — insulation returned 300–400 mm along the ceiling and party walls to limit thermal bridging; joist ends in the external wall inspected and the insulation cut around them with the VCL sealed; 0.5–1 hour per junction
- Skirting and trim refit — new skirting over the thicker wall £6–£12 per linear metre fitted; architraves and window boards extended or replaced £20–£50 per opening
- Building Control — renovation of a thermal element is notifiable; building notice £150–£300 depending on the authority, or a competent-person scheme where the installer is registered; see part l energy
- Grant-funded work — PAS 2035:2023 requires a retrofit assessment, a retrofit coordinator and a ventilation strategy; installers must be PAS 2030:2023 certified and TrustMark registered; the paperwork and the mandatory ventilation upgrade add £300–£800 per property
- Room loss — 75–100 mm off each insulated wall; say so on the quote and measure the furniture
- Materials markup — 15–25% on boards, adhesive, fixings, membranes and plaster; the same discipline as any other plastering job
- Half-day minimum — £150–£220; a single chimney breast is still a half-day with the reveals
Quick Reference Table
Spending too long on quotes? squote turns a 2-minute voice recording into a professional quote.
Try squote free →| Item | Regional (outside London/SE) | South East | London | Notes |
|---|---|---|---|---|
| Insulated plasterboard 62.5 mm, supplied, fitted, skimmed, per m² | £45–£70 | £52–£80 | £60–£95 | 0.33 W/m²K on solid brick |
| Insulated plasterboard 72.5–92.5 mm, per m² | £50–£80 | £58–£92 | £68–£110 | 0.22–0.30 W/m²K |
| Stud frame + mineral wool + VCL + board + skim, per m² | £60–£110 | £70–£125 | £80–£150 | Breathable option with wood fibre +20–30% |
| Preparation: strip paper, hack off defective plaster, per m² | £8–£25 | £10–£28 | £12–£32 | Plus skip |
| Window/door reveal, insulated and skimmed, per reveal face | £15–£30 | £18–£35 | £22–£42 | 20–30 mm reveal board |
| Socket or switch extended forward, each | £40–£80 | £45–£90 | £55–£110 | Electrician |
| Radiator off and refitted on extended tails | £80–£150 | £90–£170 | £110–£200 | Plumber; new brackets |
| Skirting replaced, per linear metre fitted | £6–£12 | £7–£14 | £9–£18 | MDF or softwood, unpainted |
| Window board replaced or extended, each | £25–£60 | £30–£70 | £35–£85 | |
| Building notice (council fee) | £150–£300 | £180–£350 | £200–£400 | Or competent-person scheme |
| Typical mid-terrace, 50 m² front and rear walls, all-in | £3,500–£6,500 | £4,200–£7,500 | £5,000–£9,000 | Excluding decoration |
| Decoration, mist coat and two coats, per m² | £8–£14 | £10–£16 | £12–£20 | Usually excluded |
Detailed Guidance
Which system, and what it does to the price
Insulated plasterboard (PIR-backed, dot-and-dab with mechanical fixings) is the fastest and thinnest route to 0.30 W/m²K and the one most domestic customers get. It needs a flat, sound, dry wall. Its weakness is that PIR is vapour-closed, so the wall behind it dries only outwards, and any moisture that gets behind the board (a missed perimeter ribbon, a leaking gutter outside) stays there. Use it on walls that are demonstrably dry, with the manufacturer's perimeter sealing and the reveals done.
Stud or batten system with mineral wool and a VCL is the route for uneven walls, walls with services that need a void, and walls where the customer or the surveyor wants a more vapour-open build-up. It is thicker (100–125 mm total), slower, and brings a carpenter in. With wood fibre instead of mineral wool and a lime or clay plaster finish it becomes the "breathable" system specified on older solid-wall houses; add 20–30% for the materials and the slower plastering.
Insulating plaster and thin aerogel boards exist for heritage walls where thickness is the constraint; they are £90–£180/m² and specialist, and are outside this guide.
The price difference between the systems is £15–£30/m², which on a 50 m² job is £750–£1,500. Quote the system by name and say why.
The preparation line is not optional
An IWI quote that starts at the boarding assumes a wall that is ready. It rarely is. Walk the wall and price:
- Damp — any sign of rising or penetrating damp is dealt with first, by the cause (gutters, ground levels, pointing, a failed DPC), and the wall left to dry. A moisture meter reading above 16–18% WME at skirting level is a stop; see internal wall insulation damp risk
- Plaster condition — blown lime plaster comes off; sound plaster can stay under a dot-and-dab board but not under a stud system that needs to see the wall. £10–£20/m² to hack off, and a 6-yard skip (£250–£350) takes about 25 m² of old plaster
- Wallpaper and paint — stripped, because adhesive dabs do not stick to vinyl paper or distemper
- Trim — skirting, architraves, dado and picture rails, coving: off, and either refitted (rarely possible over the new thickness) or replaced
- Fixings in the wall — curtain poles, TV brackets, shelves, alarms: everything comes off and goes back on with longer fixings or pattresses, each a line
A realistic preparation figure is £10–£25/m² plus the skip. It is the line most often left off and most often argued about afterwards.
Reveals, junctions and the VCL
The thermal and moisture performance of IWI is decided at the edges. Price these as time, because they are:
- Window and door reveals — 20–30 mm insulated reveal board, cut to leave the frame clear, taped and sealed to the main board; 0.5–0.75 hour per face. A bay window with six faces is half a day
- Floor junction — the board stops at the floor; the VCL or the adhesive ribbon is continuous; the skirting goes over it. On a suspended timber floor, the joist ends built into the external wall sit in the cold zone: inspect them (rot, beetle), and either cut the insulation around each and seal, or lift boards and insulate between the joists for 400 mm from the wall. 1–2 hours per joist end wall
- Ceiling junction — return 300–400 mm of insulated board along the ceiling and 400–600 mm along the party wall to reduce the thermal bridge, or accept the bridge and warn about mould in the corners; the return is 1–2 m² per room
- VCL — on a stud system, the polythene or variable membrane is lapped 100 mm, taped at every lap and every penetration, and sealed to floor and ceiling; a socket box through it is a hole unless the system uses a service void. 0.1 hour per m² for the taping
BS 5250:2021 is the standard for the condensation risk; for a solid wall with PIR board the risk calculation (BS EN ISO 13788 Glaser method, or a hygrothermal model for anything unusual) is the manufacturer's to supply and yours to follow. See vapour control layers and interstitial condensation.
Services: the lines that make IWI a multi-trade job
Every item on the wall moves forward by the insulation thickness:
| Item | Who | Cost each |
|---|---|---|
| Socket, switch, TV or data outlet extended forward | Electrician | £40–£80 |
| Light switch on an insulated wall | Electrician | £40–£80 |
| Radiator removed, tails extended, refitted on new brackets | Plumber | £80–£150 |
| Pipework surface-run on the wall: boxed within the system or rerouted | Plumber | £60–£200 |
| Gas meter, consumer unit, boiler on the wall | Specialist | Price separately; often a reason to insulate a different wall |
| Window board | Joiner | £25–£60 |
| Curtain pole, blind, TV bracket refitted with new fixings | Any | £15–£30 |
A front bedroom wall with a radiator, two double sockets and a window is £200–£400 of services before any boarding. Count them on the survey.
Worked example: Victorian mid-terrace, front and rear walls
Two-storey, two rooms deep. External walls to insulate: front lounge 11 m², front bedroom 10 m², rear kitchen 9 m², rear bedroom 9 m², bathroom 5 m², landing/stair wall 6 m². Total 50 m² net of openings. Six windows, one door. 72.5 mm insulated plasterboard, dot-and-dab with five fixings per board, reveals in 25 mm reveal board, skim throughout.
Preparation: strip paper, remove trim, hack off 15 m² defective
plaster, 50 m² × £14 = £700
Skip, 6 yd = £300
Insulated plasterboard 72.5 mm, 50 m² + 12% waste = 56 m²,
£21/m² + 20% = £1,411
Adhesive, fixings (5/board × 20 boards), perimeter sealant,
scrim, £180 + 20% = £216
Reveal board, 25 mm, 7 openings, £95 + 20% = £114
Fixing labour, 50 m² × £22 = £1,100
Reveals, 24 faces × £20 = £480
Ceiling/party-wall returns, 6 rooms × 1.5 m² × £40 = £360
Skim, 50 m² + returns 9 m² = 59 m² × £16 = £944
Electrician: 9 sockets/switches × £55 = £495
Plumber: 5 radiators × £110 = £550
Skirting, 38 lin m × £9 = £342
Window boards, 6 × £40 = £240
Building notice = £220
--------
Quote, excluding decoration £7,472
Decoration excluded (59 m² × £11 = £650 if required)
Programme: 9–10 working days; rooms taken one at a time
Room loss: 75 mm on each insulated wall
Fifty square metres at £7,472 is £149/m² all-in, against the £50–£80/m² boarding figure. The difference is the preparation, reveals, returns, services and trim, which are two-thirds of the job and are what the customer is comparing when they compare a £4,000 quote with this one.
Grant-funded IWI: PAS 2035 changes the pricing
Where the work is funded through a government or supplier scheme (ECO, the Warm Homes schemes, local authority grants; see warm homes plan grant guide), the whole-house retrofit standard PAS 2035:2023 applies: a retrofit assessor surveys the property, a retrofit coordinator designs the measures and the ventilation, and the installer must hold PAS 2030:2023 certification and TrustMark registration. The scheme pays a fixed or capped rate per m² (usually below open-market prices), the paperwork is £300–£800 of unpaid time per property unless the coordinator's fee covers it, and a ventilation upgrade (trickle vents, extract fans to Approved Document F) is mandatory with IWI. Do not quote grant work at private rates, and do not quote private work with grant-scheme corners cut. See ventilation strategy and part f ventilation.
Quoting, warranties and what to put in writing
- The system and thickness, and the U-value it is designed to achieve on that wall
- The condensation-risk basis (manufacturer's calculation for a solid brick wall with the stated internal conditions)
- The preparation included, and what is excluded (damp treatment, structural repair)
- Services, by count, and who does them
- Room loss in mm
- Building Control route and fee
- Programme, room by room, and that the rooms must be clear
- Payment: 30–40% materials deposit on an order over £1,000; stage payment at the end of boarding; balance on completion
- Consumer Contracts Regulations 2013: 14-day cancellation right on a contract agreed in the home; see quotes vs estimates
Frequently Asked Questions
How much does internal wall insulation cost per m²?
In 2026, £45–£80/m² supplied, fitted and skimmed for insulated plasterboard outside London, £60–£110/m² for a stud and mineral-wool system, for the boarding alone. Add preparation (£10–£25/m²), reveals (£15–£30 per face), services (£40–£150 per item) and trim, and a whole-house job comes to £120–£180/m² of wall all-in. A mid-terrace front and back is typically £3,500–£6,500 regionally for the boarding, £6,000–£9,000 with everything.
What thickness of insulation does Part L require?
Approved Document L (Volume 1, 2021) requires an existing wall worse than 0.70 W/m²K to be brought to 0.30 W/m²K when it is renovated, where feasible. On a 225 mm solid brick wall that is roughly 72.5 mm of PIR-backed insulated plasterboard (60 mm PIR), or about 100 mm of mineral wool in a stud system. Where 0.30 cannot be achieved because of room size or a heritage constraint, the regulation accepts the best practicable improvement, documented to Building Control.
Do I need Building Control for internal wall insulation?
Yes, where more than 50% of the surface of the wall is being insulated, because that is a renovation of a thermal element under Regulation 23 and Approved Document L. Either submit a building notice (£150–£300) or use an installer registered with a competent-person scheme that covers wall insulation. Grant-funded work goes through PAS 2035 and TrustMark, which handles the notification.
Can internal wall insulation cause damp?
It can, if the detailing is wrong. The wall behind the insulation is colder and dries less to the inside; a missed vapour control layer, an unsealed board perimeter or a joist end left in the cold zone can give interstitial condensation, mould at the corners and rot. The protection is a dry wall before you start, continuous sealing of the board or VCL, insulated reveals, returns at the ceiling and party walls, and a ventilation strategy for the room. BS 5250:2021 is the standard; see internal wall insulation damp risk.
Is it cheaper than external wall insulation?
Per square metre, yes: IWI is £45–£110/m² for the boarding against £90–£150/m² for a render-finished EWI system, and it needs no scaffold or planning consent. But IWI loses room space, disrupts every room, and has the services and condensation detailing costs above; EWI keeps the wall warm and dry and does the whole house from outside. On a solid-walled house with usable outside walls, EWI is usually the better measure and the dearer quote. See external vs internal wall insulation comparison.
Regulations & Standards
Building Regulations 2010, Regulation 23 and Approved Document L, Volume 1: Dwellings (2021 edition) — renovation of thermal elements; threshold 0.70 W/m²K and target 0.30 W/m²K for walls (Table 4.3); notification
Building Regulations 2010, Approved Document F, Volume 1 (2021) — ventilation provision when insulating; background and extract ventilation
Building Regulations 2010, Approved Document C — resistance to moisture; interstitial condensation
BS 5250:2021 — management of moisture in buildings; code of practice (condensation risk, VCL position)
BS EN ISO 13788:2012 — hygrothermal performance of building components; interstitial condensation calculation (Glaser)
BS EN ISO 6946:2017 — building components; thermal resistance and transmittance calculation (U-values)
BS EN 13950:2014 — gypsum plasterboard thermal/acoustic insulation composite panels (insulated plasterboard)
BS EN 520:2004+A1:2009 — gypsum plasterboards
BS EN 13162:2012+A1:2015 — factory-made mineral wool products
BS EN 13165:2012+A2:2016 — factory-made rigid polyurethane (PIR/PUR) foam products
BS 8212:1995 — code of practice for dry lining and partitioning using gypsum plasterboard
PAS 2035:2023 and PAS 2030:2023 — retrofitting dwellings for energy efficiency; specification and installer requirements for grant-funded work
Building Regulations 2010, Approved Document P — electrical work in dwellings; extending accessories is non-notifiable outside special locations
Consumer Rights Act 2015 and Consumer Contracts (Information, Cancellation and Additional Charges) Regulations 2013 (SI 2013/3134) — reasonable price; 14-day cancellation
Construction (Design and Management) Regulations 2015 (SI 2015/51) — domestic client duties pass to the contractor
HM Government — Approved Document L, Volume 1: Dwellings (2021) — renovation of thermal elements, Table 4.3
HM Government — Approved Document F, Volume 1: Dwellings (2021) — ventilation when insulating existing dwellings
BSI — PAS 2035:2023 Retrofitting dwellings for improved energy efficiency — the retrofit standard for funded work
TrustMark — Retrofit and PAS 2030 registration — installer requirements for grant schemes
Energy Saving Trust — Solid wall insulation — typical costs and savings for internal and external systems
Historic England — Energy efficiency and historic buildings: insulating solid walls — moisture risk and breathable systems on older walls
internal wall insulation — IWI types, condensation risk at joist ends, VCL requirements and planning implications
internal wall insulation damp risk — why IWI causes damp when the detailing is wrong, and how to avoid it
external vs internal wall insulation comparison — choosing between EWI and IWI on a solid-walled house
external wall insulation pricing guide — the EWI pricing for comparison
solid wall — solid wall construction and insulation options
vapour control layers — VCL specification and installation
interstitial condensation — the mechanism and the BS 5250 calculation
part l energy — Part L for existing dwellings, thermal elements and notification
warm homes plan grant guide — grant routes that fund IWI and the PAS 2035 requirements
plasterer day rate guide — the day rate behind the per-metre figures
insulated plasterboard vs standard — board selection and fixing