Summary

Decking is the highest-margin garden landscaping job available to a competent carpenter — and also the most commonly bodged. The visible part (the boards) is easy. The invisible part (the sub-frame, foundations, joist sizing, ground preparation, fixing detail) is what separates a deck that lasts 25 years from one that sags, twists, and rots within five.

The major pricing tier is set by material. Softwood is the volume material — UK tanalised pine or spruce, ~£15–£25/m² for the boards alone. Hardwood (oak, balau, ipe) is the premium look, ~£55–£120/m² for boards. Composite (Trex, Millboard, Hyperion, Ecodek) is the maintenance-free contemporary option, ~£55–£130/m² for boards. The sub-frame for any of these costs roughly the same — treated C24 joists at 47×150mm on concrete pad foundations is £30–£60/m² in materials and another 2–3 hours per m² in labour.

Where most cowboys lose money is treating the deck as a 1-day job for a £50 day-rate price. A 20m² deck done properly is 4–6 days for a 2-person crew including foundations, sub-frame, boards, balustrade, and clear-up. Underquoting this is endemic and the customer ends up with a bouncy, twisted, rapidly-rotting deck.

This guide covers material selection, sub-frame design, regulatory requirements (planning, Part K, Part A), and a worked pricing breakdown.

Key Facts

Quick Reference Table

Spending too long on quotes? squote turns a 2-minute voice recording into a professional quote.

Try squote free →
Material Boards (£/m² supply) Sub-frame (£/m² supply) Labour (£/m²) Total installed (£/m²) Lifespan
Treated softwood (standard) £15–£25 £25–£40 £40–£75 £80–£140 12–20 yrs
Premium softwood (larch, redwood) £25–£42 £25–£40 £45–£80 £100–£165 20–30 yrs
Hardwood (oak, balau, iroko) £55–£100 £30–£50 £60–£110 £160–£260 25–40 yrs
Hardwood (ipe, cumaru — premium) £75–£130 £30–£50 £65–£120 £190–£310 30–50 yrs
Composite uncapped £45–£75 £35–£60 £60–£100 £150–£235 20–25 yrs
Composite capped (premium) £75–£130 £35–£65 £65–£105 £180–£300 25–35 yrs
Aluminium-frame composite system £75–£130 £55–£90 £65–£110 £200–£330 30–40 yrs
Job size Material mix Typical price (2026)
Small deck 10m² Softwood £900–£1,500
Small deck 10m² Capped composite £1,800–£3,200
Medium deck 20m² Softwood £1,700–£3,000
Medium deck 20m² Hardwood £3,400–£5,500
Medium deck 20m² Capped composite £3,800–£6,200
Large deck 35m² with balustrade + steps Capped composite £7,500–£12,000
Raised deck 25m² with steps + balustrade (over 600mm) Hardwood £6,000–£10,500

Detailed Guidance

What to ask the customer at quote

  1. Use case — entertaining/BBQ (size for table + chairs), kids play, hot tub (separate structural design), garden seating area
  2. Material preference — show samples; composite is much more expensive but no maintenance
  3. Height above ground — drives sub-frame complexity, balustrade requirement, planning
  4. Garden coverage — does the proposed deck exceed 50% of garden area? Planning issue under GPDO
  5. Position — close to house (consider DPC level), in middle of garden (full sub-frame), against fence (joist hanger to neighbour structure not allowed)
  6. Access — wheelbarrow/skip route, dig spoil disposal
  7. Existing surface — grass (full sub-frame), concrete (pads not needed), patio (build over or strip)

Sub-frame design — the bit that matters

A bad sub-frame ruins any deck regardless of board cost. Key rules:

Joist sizing (per BS 5268-7 / BS EN 1995-1-1):

Foundations:

Bearers and posts:

Joist hangers and connections:

Cross-bracing and noggins:

Composite vs timber — when to recommend each

Recommend softwood when:

Recommend hardwood when:

Recommend capped composite when:

Don't recommend uncapped composite — fading, staining, scratching issues; capped is worth the £10–£20/m² premium.

Balustrade — Part K requirements

Building Regulations Part K (Protection from falling, collision and impact) applies to decks. Trigger thresholds:

Material options:

Steps and access

Steps to and from the deck price separately:

Planning permission and Building Regulations

Planning permission required when:

Building Regulations approval required when:

Always advise customer to check with Planning department. Quote should state "subject to planning permission / Building Regs approval if required."

Drainage and ground preparation

Common pitfalls

Pricing breakdown for a typical job

A 20m² capped composite deck, ground-level (no balustrade), 4 steps to lawn, single side return:

Item Cost
Capped composite boards (Trex Enhance or similar) 20m² × £45/m² £900
Treated softwood C24 joists (47×150mm) 50m × £8/m £400
Treated softwood C24 bearers (75×150mm) 12m × £14/m £168
Concrete pads (12 × £20) £240
Postcrete (10 × £10) £100
Steel post anchors (Simpson) 8 × £12 £96
Joist hangers + fasteners £85
Hidden clip system (composite) £150
Stainless screws (sub-frame fixing) £40
Composite fascia trim 14m × £18/m £252
Composite steps (4 × £130) £520
Weed membrane + vents £40
Sundries (DPC, brackets, sealant) £35
Skip 6-yard (excavation spoil) £290
Labour: 2 carpenters × 4 days @ £260/day £2,080
Travel & overhead £120
Subtotal £5,516
Markup at 22% £1,213
Total to customer £6,729

Round to £6,700. Per-m² = £335 — at top end of composite range due to steps + fascia. Compare against £150/m² × 20m² = £3,000 — that's a softwood equivalent. The customer chooses the spec.

Frequently Asked Questions

Do I need planning permission for a deck under 300mm?

In most cases no — under GPDO 2015 it's permitted development if (a) <300mm above ground level, (b) doesn't exceed 50% of the garden coverage when added to other outbuildings/extensions, (c) not in a conservation area / Article 4 / listed building. Always check with local Planning before quoting to protect the customer (and yourself).

How long does a softwood deck really last?

Properly built with C24 tanalised joists, stainless screws, DPC at post bases, and customer applying annual decking oil: 15–25 years. Built badly (untreated joists in contact with soil, mild-steel screws, no maintenance): 5–8 years. The difference is sub-frame quality and aftercare, not board grade.

Why is composite decking so much more than timber?

Material cost. Composite boards are 3–5× the material cost of softwood. Once you factor in the no-maintenance lifetime cost (no annual oil, no sanding, no re-staining, no board replacement), the 25-year total ownership cost of composite is often lower than softwood. But the upfront install price is 2–3× higher.

Can I lay decking over an existing concrete patio?

Yes — and it's cheaper because you skip the foundations. Lay a treated softwood batten sub-frame (47×75mm minimum) directly on the concrete on DPC pads, with 5mm gaps for drainage. Joists at 400mm centres. Check the concrete is level and falls away from house — if not, use packers.

What's the difference between capped and uncapped composite?

Uncapped composite is just compressed wood-flour + polymer; absorbs moisture, fades, stains, and surface degrades within 5–8 years. Capped composite has a polymer shell bonded around the core; UV-stable, stain-resistant, slip-rated, 25-year warranty common. Always quote capped — the £10–£20/m² premium is worth it.

Regulations & Standards