Summary

The downstairs toilet is one of the most requested small jobs in UK housing and one of the easiest to under-price. Customers see a WC, a basin and a tiny room and expect a bathroom-fitter's half-day. In reality it is a drainage job, a plumbing job, an electrical job, a ventilation job and a decorating job in a space too small for two trades to work in at once, and it is notifiable building work. The under-stairs cloakroom in a 1930s semi routinely takes a plumber and a multi-trader four to six working days between them, plus a wait for Building Control.

This guide prices the job the way it is actually built: a drainage line, a plumbing line, a first- and second-fix electrical line, ventilation, room formation where needed, finishes and the compliance costs. It covers the two routes to the drains, gravity and macerator, and the decision between them. For the macerator installation itself see macerator saniflo installation and for pricing a macerator as a stand-alone job see macerator toilet installation pricing guide. For the en-suite equivalent see en suite pricing guide.

Drainage is the variable that decides the price. If the soil stack or an inspection chamber is within a few metres of the proposed WC and the fall works, the drainage is a morning's work. If the only route is under a solid floor to a chamber at the front of the house, it is two days of excavation, a new chamber and a concrete repair, and the whole quote doubles. Survey the drains before you price anything else.

Key Facts

Quick Reference Table

Spending too long on quotes? squote turns a 2-minute voice recording into a professional quote.

Try squote free →
Component Scope Typical price (ex VAT, 2026)
Drainage survey and Building Control notice Trace drains, lift chamber cover, building notice fee £250–£550
Gravity drainage, short run to existing stack or chamber Up to 3 m of 110 mm pipe, boss or chamber connection, test £350–£700
Gravity drainage, new run under solid floor Excavate, bed, lay, new inspection chamber, backfill, reinstate £900–£2,000
Macerator route Unit supplied and fitted, 22 mm discharge pipework, dedicated circuit £600–£1,200
WC supply and fit Close-coupled pan and cistern, seat, 15 mm cold supply £300–£650
Cloakroom basin supply and fit Basin, tap, trap, 32 mm waste, hot and cold £250–£600
Undersink water heater (where no hot run) 2–5 litre unit, supplied, fitted and wired £250–£450
Ventilation Fan, ducting, external grille, overrun timer, wiring £180–£400
Electrics Light, switch, fan circuit, test and certificate £250–£500
Room formation Stud walls, plasterboard, door and lining £1,200–£2,500
Finishes Floor (vinyl or tiles), splashback, painting, skirting £400–£1,000
Waste disposal Mini skip or bagged waste £80–£250

Detailed Guidance

Step 1 — survey the drains before you quote

Lift the nearest inspection chamber cover and establish where the foul drain runs, its depth and its direction of fall. Then identify the soil stack. The three routes, in order of cost:

  1. Boss connection into the existing soil stack — the proposed WC is within about 2 m of the stack on the same side of the house. A strap boss or a cut-in boss pipe at the right height, 110 mm pipe at 1:40, done in a morning. Allow £350–£700.
  2. New branch into an existing inspection chamber — the WC is within a few metres of a chamber, usually through a suspended timber floor or along an external wall. A new 110 mm branch into the chamber, rodding access preserved, pipe bedded in pea gravel outside or clipped under the floor inside. Allow £500–£1,000.
  3. New drain run and chamber under a solid floor — the typical under-stairs cloakroom in a house with a concrete ground floor and the drains at the back. Break out the slab, excavate a trench at the correct fall, lay 110 mm pipe on 100 mm granular bed, build a new 450 mm inspection chamber at the junction, backfill and reinstate the concrete and damp-proof membrane. Two days for two people, £900–£2,000.

If none of those is feasible at reasonable cost, the macerator is the answer. The customer needs to know the limitations: a pumped 22 mm discharge with a maximum lift and horizontal run set by the manufacturer (commonly around 5 m vertical or 100 m horizontal, but not both), a noise on every flush, a service item that can fail, and the Approved Document G requirement that the house keeps a gravity WC elsewhere.

Step 2 — room formation and layout

Most downstairs toilets go under the stairs, into the end of a hall, or into a corner of a utility room. Where the room already exists (a former pantry or cupboard) the formation cost is just a door change. Where walls have to be built:

For a new dwelling or a Category 1 compliant layout, Approved Document M requires the WC to be on the entrance storey with a clear 900 mm × 1,500 mm space, but this does not apply retrospectively to an existing house. State in the quote that the room is sized to fit the available space and will not meet Part M accessible dimensions unless the customer asks for them.

Step 3 — plumbing and sanitaryware

A close-coupled WC with a dual-flush cistern is the standard choice; a back-to-wall pan with a concealed cistern saves 100–150 mm of depth and suits a tight room but costs more (see back to wall vs close coupled toilet comparison). Cloakroom basins are small (350–450 mm) and often wall-hung or corner mounted; check the tap hole and waste position before ordering.

Supply pipework is 15 mm cold to both, with an isolation valve on each (see isolation valves). Hot water to the basin is the detail most often forgotten: if the nearest hot run is on the far side of the house, a dead-leg of 10 m delivers cold water for a minute and wastes energy. Either run the hot and accept it, or fit a small undersink electric water heater on its own fused spur. Price both and let the customer choose.

Where a macerator is used, it needs its own 15 mm cold, a dedicated 13 A fused spur with RCD protection, a 22 mm (or 32 mm per manufacturer) discharge in solvent-weld pipe with a non-return valve, and an air admittance valve or vent. The unit sits behind the pan and adds about 200 mm to the depth.

Step 4 — ventilation and electrics

A cloakroom with an openable window meets Approved Document F without a fan, though most customers want one anyway. Without a window, an intermittent extract fan of at least 6 l/s is required, ducted to outside, with a humidistat or timer overrun of about 15 minutes where it is switched with the light. Internal rooms with no external wall need ducting through a ceiling void or an adjoining room, which is the costly version: allow £250–£400 for fan, duct run and external grille.

Electrically, a downstairs toilet without a bath or shower is not a special location, so standard accessories and IP ratings apply, but a new lighting or fan circuit, and certainly a macerator spur taken as a new circuit, is notifiable work under Approved Document P in England unless done by a registered competent person who self-certifies. Price an electrician for a day including testing and the Minor Works or Electrical Installation Certificate (see testing commissioning).

Step 5 — finishes

Finishes are where the quote can be tuned to budget. A sheet vinyl floor (£25–£45/m² supplied and fitted), a painted wall with a tiled splashback behind the basin (£80–£200), emulsion to walls and ceiling and a coat of satinwood on the door and skirting is the economical specification at £400–£600 for the whole room. A fully tiled cloakroom with a porcelain floor and a feature wall runs £900–£1,500 (see wall tiling pricing guide). Agree the finish level at survey; it moves the total by £1,000.

Worked example: under-stairs cloakroom, gravity to existing chamber, formed in existing cupboard

Item Price
Drainage survey, building notice fee (LA £320), two inspections £450
New 110 mm branch, 4 m through suspended floor to existing chamber, air test £750
Close-coupled WC and seat, supplied and fitted £480
Cloakroom basin, mixer tap, trap and waste, supplied and fitted £420
Hot and cold supplies from utility room, isolation valves £260
Extract fan with overrun, ducted through external wall, wiring £320
Lighting point, switch, test and Minor Works Certificate £280
Replace cupboard door with 686 mm internal door, lining and handle £300
Sheet vinyl floor 1.3 m², splashback tiling, painting, skirting £520
Waste disposal £120
Total £3,900

Labour across plumber, electrician and multi-trader is roughly 5 working days at £1,700–£2,000; materials at trade are about £1,100; the building notice is a pass-through cost. That leaves a gross margin in the mid-20s per cent, which is where this job should sit given the number of interfaces and the chance that the drain route is not what the chamber suggested.

Frequently Asked Questions

Does a downstairs toilet need Building Regulations approval?

Yes. Installing a new WC with new drainage is controlled work under Approved Documents H1 (foul drainage), F (ventilation) and G4 (sanitary conveniences), and in most cases Part P if a new electrical circuit is installed. A building notice is the usual route for this scale of work; the inspector will want to see the drain connection before it is covered and will carry out a completion inspection. Doing the work without notification leaves the homeowner without a completion certificate, which surfaces when they sell. Price the fee and the inspection visits into the quote and say so (see building control).

Can I always use a macerator instead of digging up the floor?

Not always. Approved Document G allows a macerator WC only where the dwelling also has a WC that discharges by gravity to a drain, and the unit must comply with BS EN 12050-3. Many Building Control bodies also expect the macerator to be the second WC, not the only one. Where the house already has a gravity bathroom upstairs, a macerator downstairs is acceptable, but tell the customer about noise, servicing and the restriction on what can be flushed before they choose it.

How small can the room be?

In an existing house there is no statutory minimum. A WC needs about 800 mm width to sit on comfortably and 600 mm clear in front of the pan; a basin alongside pushes the width to 900–1,000 mm, or the basin goes on the end wall. Compact pans with a 600 mm projection and corner basins make 800 × 1,400 mm workable. New dwellings have to provide the Approved Document M Category 1 space of 900 × 1,500 mm clear of the door swing.

Does the cloakroom need a fan if it has a window?

Not under Approved Document F, provided the window opens. In practice a small fan on the light switch with an overrun is cheap insurance against condensation and odour and most customers want one. Where there is no window, a fan of at least 6 l/s ducted to outside is mandatory.

Why is the quote so different between two houses with the same size room?

The drains. A WC 2 m from the soil stack is a morning's pipework; a WC on the opposite side of a solid-floored house from the nearest chamber is two days of excavation and a new chamber. Everything else in a downstairs toilet is broadly fixed. Explain this at survey and show the drainage as its own line so the customer understands where the money went.