Summary
A ceiling replacement is the job the customer wants to be a skim and the plasterer knows is a strip-out. The call usually comes after a leak has brought part of a lath-and-plaster ceiling down, after a surveyor has reported a sagging ceiling, or because a customer has lived with cracks and bellies for years and is finally decorating. In each case the pricing question is the same: can the existing ceiling stay (overboard), or does it come down (strip, reboard, skim)? The answer is in the condition of the existing ceiling and the joists above it, and it is worth a survey visit, because the two jobs are £20–£40/m² apart and the customer will compare your figure with someone who quoted the cheaper one without looking.
A strip-out is dusty, heavy, slow, and full of things the quote has to carry: the skip, the asbestos sample, the noggins where board edges land between joists, the light fittings and downlighters, the coving, the loft insulation above a top-floor ceiling, and the day's cleaning. The boarding and skim at the end is the part the plasterer prices confidently; everything before it is where the margin goes. This guide gives the 2026 build-up for strip-and-reboard and for overboarding, the fire and Part L points that decide the board specification, the joist and services lines, a worked example, and a note on the heritage case where a lath-and-plaster ceiling should be repaired rather than replaced. For the technical method see plasterboard fixing and dot and dab, plasterboard types and taping and jointing techniques; for the repair alternative see lath and plaster repair pricing guide.
Key Facts
- Strip and reboard, labour — £35–£60/m² for two operatives: strip 0.5–1 hour per 10 m², clear and bag, check and nog the joists, board at 20–30 m² a day, skim at 25–35 m² a day
- Strip and reboard, materials — 12.5 mm plasterboard £8–£12/m² (2400 × 1200 board £10–£14, 2.88 m²), 38 mm plasterboard screws at 230 mm centres (about 20 per m²), scrim or paper tape, jointing compound, bonding agent at the perimeter, multi-finish 1.5 bags per 12 m²: £12–£18/m² all in with 10% waste
- Overboard a sound ceiling — £30–£50/m² supplied, fitted and skimmed; board screwed through the existing ceiling into the joists (locate them first; 50–60 mm screws through lath and plaster), 12–15 mm lost in height
- Waste — lath and plaster 25–40 kg/m²; plasterboard 10–12 kg/m²; a 6-yard skip (£250–£350) takes about 20 m² of lath-and-plaster ceiling with the laths; mixed-waste skip rates apply, and anything with asbestos is separate hazardous waste
- Asbestos — a textured coating applied before 2000 is sampled before it is disturbed (£30–£80, 1–3 days); some pre-1980 ceilings are asbestos insulating board (AIB), which is licensed work — see asbestos containing materials acm and artex removal pricing guide
- Fire resistance — Approved Document B Volume 1, Table B4: the upper floor of a two-storey house needs 30 minutes; floors in a three-storey house and separating floors in flats need 30 or 60 minutes to the full standard; 12.5 mm plasterboard with a 3 mm skim on timber joists at 450 mm centres gives a modified 30 minutes, 15 mm Type F (fire) board or two layers for the full specification — check the floor's existing construction before pricing a like-for-like reboard in a flat
- Board thickness and centres — 12.5 mm board on joists at up to 450 mm centres; 15 mm at up to 600 mm; older houses with joists at 400 mm are fine with 12.5 mm; a 1960s ceiling on 600 mm centres needs 15 mm or counter-battens
- Screw centres — 230 mm on ceilings (not the 300 mm used on walls), 150 mm at board ends; screws 10–13 mm in from the edge
- Noggins — every unsupported board edge needs a noggin; a 2400 × 1200 board on joists at 400 mm running across the room needs noggins at 1200 mm; 47 × 75 mm C16 at £2–£3 per metre, 30–45 minutes per 10 m² to fit
- Services — a pendant or batten holder re-hung £15–£30; downlighters re-fitted £15–£25 each and fire-rated hoods or fire-rated fittings required where the ceiling is part of a fire-resisting floor; smoke alarm re-fitted £15–£25; pipes and cables above are checked for damage and clipped; no new circuits, so not notifiable under Part P
- Loft insulation — a top-floor ceiling under a cold loft is part of the roof thermal element; where more than 50% of it is replaced, Approved Document L expects the insulation to be brought up to 0.16 W/m²K (270 mm mineral wool) if it is not already, and the insulation has to be lifted and re-laid anyway: £8–£15/m² to top up, and the vapour control and the loft hatch sealing are worth doing while it is open
- Coving — off and replaced (it rarely survives) at £8–£15 per linear metre fitted for gypsum or polystyrene profiles; ornate plaster cornice is a specialist line
- Decoration — mist coat and two coats £8–£14/m²; often excluded; a new skim needs 5–7 days to dry before painting
- Dust — strip-out dust is a COSHH matter (horsehair and lime in old plaster, respirable dust): FFP3 masks, the room sealed, an extractor in the window, and the customer out of the room; price 1–1.5 hours of sealing and cleaning per room
- Half-day minimum — £150–£220 for a patch or a small ceiling; a single ceiling is rarely less than two days with the strip, the board, the skim and the return
- Materials markup — 15–25% on board, screws, scrim, plaster and timber; skip at cost plus 10–15% or recharged at cost as a disbursement
Quick Reference Table
Spending too long on quotes? squote turns a 2-minute voice recording into a professional quote.
Try squote free →| Job | Regional (outside London/SE), per m² | South East, per m² | London, per m² | 12 m² bedroom, regional | 20 m² lounge, regional |
|---|---|---|---|---|---|
| Strip lath-and-plaster, reboard 12.5 mm, skim | £50–£90 | £58–£105 | £70–£120 | £600–£1,100 | £1,000–£1,800 |
| Strip old plasterboard, reboard, skim | £40–£70 | £46–£80 | £55–£95 | £500–£850 | £800–£1,400 |
| Overboard sound ceiling, skim | £30–£50 | £35–£58 | £42–£70 | £360–£600 | £600–£1,000 |
| Reboard with 15 mm Type F (fire) board, skim | +£5–£10 | +£6–£12 | +£7–£14 | +£60–£120 | +£100–£200 |
| Noggins, per m² of ceiling | £3–£6 | £3–£7 | £4–£8 | £36–£72 | £60–£120 |
| Skip, 6 yd (per 20 m² of lath and plaster) | £250–£350 | £280–£400 | £320–£480 | £250–£350 | £250–£350 |
| Asbestos sample (per sample) | £30–£80 | £35–£85 | £40–£90 | £30–£80 | £30–£80 |
| Light fitting re-hung, each | £15–£30 | £18–£35 | £22–£42 | ||
| Downlighter re-fitted with fire hood, each | £15–£25 + hood £8–£15 | ||||
| Loft insulation top-up to 270 mm, per m² | £8–£15 | £9–£17 | £11–£20 | £96–£180 | — |
| Coving replaced, per linear metre | £8–£15 | £10–£18 | £12–£20 | £110–£210 | £150–£270 |
| Decoration, per m² | £8–£14 | £10–£16 | £12–£20 | £96–£170 | £160–£280 |
| Patch repair (up to 1 m²), half-day minimum | £150–£220 | £170–£250 | £200–£300 |
Detailed Guidance
Strip or overboard: the survey decision
Overboarding is the right job when the existing ceiling is firmly fixed, flat enough to board over (a belly of more than 10–15 mm over 2 m will show through), dry, and free of anything that will keep moving. It is the wrong job when the ceiling is lath and plaster with the keys broken (push up gently: it moves, or it crunches), when there has been a leak and the plaster is soft, when the laths are rotten or the joists need looking at, or when the customer wants the ceiling height kept and the cornice saved. The survey checks:
- Key failure — press upward with a flat hand at several points; lath-and-plaster that moves or sounds hollow has lost its keys and is held by habit. Overboarding fixes a loose ceiling to the joists through the board and is acceptable where the laths are sound; where the plaster is sagging in bellies, strip it
- Moisture — any leak is fixed and the ceiling dry before either job; a damp reading in old plaster means it comes down
- Joists — from the loft or through a hole: sizes, centres, condition (rot at the wall ends, notching for pipes, beetle), level. A 1900s ceiling on 100 × 50 mm joists at 400 mm with a 4.2 m span is often sagging because the joists are undersized, and no board will cure it; see joist installation and joist span calculator
- Services — pendant, downlighters, smoke alarm, pipes above (a bathroom above means pipes and a leak history), cables
- Finish — textured coating (sample), cornice (keep?), coving (replace)
- Fire separation — a flat, an HMO or a three-storey house means the floor is fire-resisting and the specification is checked before anything is promised
Write the decision down with the reason. "Strip and reboard: existing lath-and-plaster ceiling has failed keys over approximately 40% of the area and bellies of 25 mm; overboarding would not be sound" protects the quote against the cheaper one.
Labour and materials build-up: strip and reboard, 12 m² bedroom
Two operatives, lath and plaster, 1900s terrace, joists at 400 mm, no textured coating, one pendant, loft above with 100 mm of old insulation:
| Step | Time (two operatives) | Materials |
|---|---|---|
| Seal the room, sheet the floor, isolate the lighting circuit, drop the pendant | 1 hr | Polythene, tape £10 |
| Lift and bag the loft insulation above; strip plaster and laths with bars and shovels; bag and carry to skip | 3–4 hr | Rubble bags £15 |
| Clean the joists of nails and plaster; check condition; fit noggins at board ends (3 rows × 3 m = 9 m) | 1.5 hr | 47 × 75 mm C16, 9 m, £25 |
| Board: 5 × 2400 × 1200 × 12.5 mm, staggered, 38 mm screws at 230 mm | 2 hr | Board £60, screws £8 |
| Re-lay and top up loft insulation to 270 mm (optional line, priced separately) | 1 hr | 170 mm top-up, 12 m² £90 |
| Scrim the joints, bonding agent at the perimeter, two-coat skim | 2.5 hr | Scrim £5, multi-finish 1.5 bags £16 |
| Re-hang pendant on a new ceiling rose; clean down; remove sheeting | 1 hr | Rose £5 |
| Total | 12–13 hours each, two days | £140 + 20% = £168 (excl. insulation) |
At £220–£300 a day each (see plasterer day rate guide), labour is £880–£1,200 for two days for two, which with materials, the skip (£300) and the asbestos sample (none here) gives a quote of £1,000–£1,400 at the regional band's top end for a bedroom with a loft above. A first-floor ceiling with a floor above (no insulation, no loft access) is quicker and sits at £700–£1,000. Those are the figures that reconcile with £50–£90/m².
The fire specification
The ceiling is the underside of a floor, and in Approved Document B the floor has a fire-resistance requirement that the ceiling lining helps meet:
- Two-storey house — the upper floor needs 30 minutes (Table B4), and a timber-joist floor with 12.5 mm plasterboard and a skim meets it; like-for-like reboarding is fine
- Three-storey house (including a loft conversion) — the floors forming the escape route need the full 30 minutes; the original 2019/2020 conversion drawings specified the ceiling (often 15 mm Type F or 12.5 mm Type F with a skim); replace with the same or better
- Flats and HMOs — the separating floor between flats needs 60 minutes (30 minutes in some conversions under earlier regulations); the ceiling is often a two-layer or 15 mm Type F lining with specified screw centres; a like-for-like reboard with 12.5 mm standard board would reduce it, which is a Building Regulations contravention. Get the specification from the building owner or the original approval, or specify to a tested system
- Downlighters — a recessed downlighter cuts a hole in the fire lining; fire-rated fittings or hoods are needed wherever the ceiling is fire-resisting, and in a flat that is every ceiling
See part b fire, building regs part b fire lining and compartmentation. The 15 mm Type F board is £5–£10/m² more than standard 12.5 mm; put it on the quote where it applies and say why.
Part L and the top-floor ceiling
A ceiling under a cold loft is the inside face of the roof thermal element. Approved Document L Volume 1 treats renovation of more than 50% of a thermal element as triggering the upgrade requirement — for a pitched roof with insulation at ceiling level, 0.16 W/m²K, which is about 270 mm of mineral wool. Where the existing insulation is 100 mm or less, the top-up is cheap while the insulation is already lifted (£8–£15/m²), and Building Control would expect it if the work is notified. Reboarding a single ceiling in a house is usually not notified, but a competent plasterer prices the top-up as an option and recommends it; see loft insulation and part l energy.
Overboarding build-up
Where the ceiling is sound: locate the joists (a stud finder, or probe with a bradawl along a line; mark both ends on the wall), remove the coving and drop the fittings, screw 12.5 mm board through the existing ceiling into the joists with screws long enough to get 25 mm into the timber (50–60 mm through lath and plaster), stagger the joints, scrim, skim. 20–30 m² a day for two including the skim. The price (£30–£50/m²) is lower because there is no strip, no skip and no dust, and it is the right job for a plasterboard ceiling with cracked joints or a lath-and-plaster ceiling that is flat and firm. Note the 12–15 mm height loss and that the ceiling rose, the smoke alarm and every downlighter need re-fitting.
Heritage ceilings: repair, do not replace
A lath-and-plaster ceiling with a run cornice, a ceiling rose or any decorative plasterwork, in a listed building or a conservation area, is a repair job: the keys are re-formed from above with a lime-based or resin-bonded repair, the plaster is consolidated, and the cornice is preserved. Stripping it in a listed building without consent is an offence under the Planning (Listed Buildings and Conservation Areas) Act 1990. Price it from lath and plaster repair pricing guide and bring in a conservation plasterer where the cornice matters.
What goes on the quote
- Strip and reboard or overboard, with the reason from the survey
- The board specification (12.5 mm standard, 15 mm Type F, two layers) and why
- The skip and the asbestos sample as lines
- Services: fittings re-hung, downlighters and fire hoods, smoke alarm
- Loft insulation top-up as a priced option on a top-floor ceiling
- Coving: new, replaced like for like, or excluded
- Decoration excluded unless priced, and the 5–7 day drying time before painting
- The room cleared by the customer, the lighting circuit off for the day, and a day rate for anything found (rotten joist ends, a second ceiling above the first, a leaking pipe)
- Payment: materials deposit on anything over £800; balance on completion
Frequently Asked Questions
How much does it cost to replace a ceiling?
In 2026, £600–£1,100 for a 12 m² bedroom and £1,000–£1,800 for a 20 m² lounge outside London, to strip a lath-and-plaster ceiling, reboard with 12.5 mm plasterboard and skim, including the skip. Overboarding a sound ceiling without stripping it is roughly half that. Add coving, light fittings, loft insulation and decoration as separate items. London is 30–40% more.
Can I plasterboard over a lath-and-plaster ceiling?
Yes, if it is flat, firmly fixed and dry. The board is screwed through the old ceiling into the joists (which have to be found first) with 50–60 mm screws, and the old ceiling is sandwiched tight. It does not work on a ceiling that is sagging in bellies or where the laths are rotten, and it drops the ceiling by 12–15 mm. Where the old ceiling is loose over more than a small area, strip it.
Do I need Building Control to replace a ceiling?
Not usually for a like-for-like reboard of a single ceiling in a house. The exceptions: a ceiling that forms part of a fire-resisting floor (flats, HMOs, three-storey houses), where the replacement must maintain the fire resistance and may need to be demonstrated; and a top-floor ceiling where more than half the roof thermal element is being renovated, which brings in the Part L insulation upgrade. If in doubt, a building notice (£150–£300) covers it.
What is the dust like, and is old plaster dangerous?
A lath-and-plaster strip-out is the dustiest job in domestic plastering: lime, horsehair, soot and a century of loft dust. It is not usually hazardous in the asbestos sense (lime plaster and laths contain no asbestos), but any textured coating on the surface from before 2000 must be sampled first, and some pre-1980s ceilings are asbestos insulating board, which is licensed work. Seal the room, run an extractor, wear FFP3 masks, and keep the customer out until it is cleaned.
How long before I can paint a new ceiling?
A two-coat skim is touch-dry in a day and ready for a mist coat (watered-down emulsion) after 5–7 days in a heated, ventilated room, longer in winter. Painting too soon traps moisture and the paint peels. Put the drying time on the quote so the decorator is booked for the right week.
Regulations & Standards
Building Regulations 2010, Approved Document B, Volume 1: Dwellings (2019 edition incorporating 2020 and 2022 amendments) — Table B4 fire resistance of floors; recessed light fittings in fire-resisting ceilings
Building Regulations 2010, Regulation 23 and Approved Document L, Volume 1: Dwellings (2021) — renovation of thermal elements; 0.16 W/m²K for a pitched roof insulated at ceiling level
Building Regulations 2010, Approved Document A — structure; joist sizing where joists are replaced or strengthened
Building Regulations 2010, Approved Document P — electrical safety; re-fixing existing fittings is not notifiable
Control of Substances Hazardous to Health Regulations 2002 (SI 2002/2677) — respirable dust from strip-out; RPE
Control of Asbestos Regulations 2012 (SI 2012/632) — textured coatings and AIB ceilings; presumption and sampling
Construction (Design and Management) Regulations 2015 (SI 2015/51) — domestic client duties pass to the contractor
Planning (Listed Buildings and Conservation Areas) Act 1990 — consent for works to listed buildings including historic ceilings
BS EN 520:2004+A1:2009 — gypsum plasterboards; definitions, requirements and test methods (Type F fire boards)
BS 8212:1995 — code of practice for dry lining and partitioning using gypsum plasterboard
BS EN 13914-2:2016 — design, preparation and application of internal plastering
BS EN 1995-1-2:2004 (Eurocode 5) — structural fire design of timber structures; the basis of plasterboard contribution to floor fire resistance
BS 476-21:1987 and BS EN 1365-2:2014 — fire resistance tests for floors (legacy and current test methods)
Consumer Rights Act 2015 (s.49–s.52) — reasonable care and skill; reasonable price where none agreed
HM Government — Approved Document B, Volume 1: Dwellings — Table B4 floor fire resistance and recessed fittings
HM Government — Approved Document L, Volume 1: Dwellings (2021) — thermal element renovation and roof U-values
HSE — Construction dust: controlling the risks — strip-out dust control and RPE
HSE — Asbestos: where it can be found in buildings — textured coatings and insulating board ceilings
British Gypsum — White Book: ceiling linings, fixing centres and fire performance — board thickness by joist centres, 230 mm screw centres, Type F board fire data
Historic England — Lath and plaster ceilings: repair rather than replace — conservation approach to historic plaster
lath and plaster repair pricing guide — repairing rather than replacing, and the heritage case
plasterboard fixing and dot and dab — fixing method, screw centres and board layout
plasterboard types — standard, Type F, moisture and acoustic boards and when each applies
plasterboard quantities — board, screw and plaster take-off
skim coat pricing guide — the skim pricing used in the build-up
artex removal pricing guide — pricing the textured coating that is often on the ceiling coming down
part b fire — floor fire resistance in houses, flats and HMOs
building regs part b fire lining — fire-rated lining systems and tested specifications
loft insulation — topping up to 270 mm while the ceiling is down
joist installation — joist replacement and strengthening where the survey finds a structural cause
plasterer day rate guide — the day rate the per-metre figures are built from
coving installation pricing guide — replacing the coving afterwards