Summary
Artex is the job that catches plasterers and decorators out on price, because the customer sees a ceiling they want flat and the tradesperson sees four different jobs depending on what the coating is made of and how it is going to be dealt with. The cheapest route, a skim over the top, is only appropriate where the coating is sound, well-bonded and not too deeply stippled. The most expensive route, removing an asbestos-containing coating, is a regulated activity with training, equipment, waste and paperwork that a plasterer who has not priced it before will lose money on. In between are overboarding and wet scraping, each with its own labour rate, materials list and risks.
The pricing discipline is therefore: identify the method first, then price the method. That means an asbestos test before the quote is firm, a stated assumption on the quote about what happens if the result is positive, and a per-metre rate for each method rather than a round number per room. This guide gives the 2026 labour and material build-up for each of the four methods, regional and London bands, a worked example for a typical house, and the compliance costs that have to be in the figure for asbestos-containing coatings. For the technical method (sampling, skim-over technique, wet stripping) see artex removal skim coating and skim over artex and old surfaces; for the asbestos rules in detail see asbestos in textured coatings and control of asbestos regs 2012.
Key Facts
- Presume asbestos before 2000 — textured coatings sold in the UK could contain chrysotile (white asbestos), typically 1–5% by weight, until the 1999 ban took effect; a coating in a property built or decorated before 2000 is presumed to contain asbestos until a laboratory sample says otherwise
- Sampling — £30–£80 per sample at a UKAS-accredited laboratory, 1–3 working days turnaround; one sample per ceiling or per distinct application. Quote the test as a separate line or absorb it in the survey visit
- Skim over, labour only — £15–£30/m²; a sound coating is sealed with a bonding agent, deep stipple is knocked back (not sanded) or filled with bonding coat, then two-coat skimmed; output 15–25 m² a day for one plasterer
- Overboard, supplied and fitted — £30–£50/m² including 12.5 mm plasterboard, screws, scrim and skim; output 20–30 m² a day for two; loses 12–15 mm of ceiling height and needs coving, light fittings and cornice dealt with
- Wet scrape, asbestos-free — £20–£40/m² including the skim afterwards; output 8–15 m² a day; the surface left behind needs a bonding coat and skim, so this is never cheaper than a skim-over unless the coating is failing
- Removal, asbestos-containing, non-licensed or NNLW — £40–£70/m² regionally, £55–£90/m² London, for wet removal by trained operatives with RPE (FFP3 minimum), disposable coveralls, polythene enclosure of the room, Class H vacuum, hazardous waste consigned to a licensed site, and the NNLW notification to HSE where it applies; plus the skim afterwards
- Licensed removal — where a licensed contractor is required (unusual for textured coatings, but required where the coating is badly deteriorated or the method would generate significant fibre release), £60–£120+/m² from the licensed contractor, with your reinstatement priced on top
- Hazardous waste — asbestos waste above 0.1% asbestos is hazardous waste under the Hazardous Waste (England and Wales) Regulations 2005; double-bagged in UN-approved red/clear asbestos bags, consignment note, licensed carrier and site; £150–£350 for a small collection or £30–£60 per bag at a site that accepts it
- Training — non-licensed asbestos work requires the operative to have had asbestos awareness and task-specific training (CAR 2012 regulation 10); a half-day course is £50–£120 per person and is a business overhead, not a job cost
- Dust and silica — dry sanding or scraping any textured coating is prohibited where asbestos is present and is poor practice everywhere; COSHH 2002 applies to the plaster dust and to any silica in the skim or bonding
- Height loss and services — overboarding drops the ceiling 12–15 mm; downlighters need longer fixings or fire hoods re-fitted; coving comes off and goes back on at £8–£15 per linear metre
- Decoration — mist coat and two coats on a new skim is £8–£14/m² for the decorator; quote it or exclude it, but say which
- Half-day minimum — £150–£200; a single small ceiling is still a van, a mix, a dust sheet and a return to clean up
- Materials markup — 15–25% on bonding agent, bonding coat, multi-finish, plasterboard, screws and scrim; the asbestos consumables (bags, coveralls, RPE, polythene) are priced per job at cost plus 25–40% because they are single-use
- Consumer Rights Act 2015 — reasonable price where none is agreed; a quote that states the method and the assumption on asbestos content is what protects you when the sample comes back positive
Quick Reference Table
Spending too long on quotes? squote turns a 2-minute voice recording into a professional quote.
Try squote free →| Method | Regional (outside London/SE), per m² | South East, per m² | London, per m² | 12 m² ceiling, regional | Notes |
|---|---|---|---|---|---|
| Asbestos sample (per sample) | £30–£80 | £35–£85 | £40–£90 | £30–£80 | UKAS laboratory; 1–3 days |
| Skim over intact coating | £15–£30 | £18–£35 | £22–£42 | £250–£450 | Sound, well-bonded coating only |
| Overboard and skim, supplied and fitted | £30–£50 | £35–£58 | £42–£70 | £450–£700 | 12.5 mm board; coving and lights extra |
| Wet scrape asbestos-free and skim | £20–£40 | £24–£46 | £28–£55 | £350–£600 | Bonding coat usually needed |
| Non-licensed/NNLW removal of asbestos coating | £40–£70 | £48–£80 | £55–£90 | £500–£900 | Trained operatives, RPE, enclosure, waste |
| Skim after asbestos removal | £15–£25 | £18–£30 | £22–£35 | £200–£350 | Separate line |
| Licensed contractor removal | £60–£120+ | £70–£140 | £85–£160 | £800–£1,500+ | Rare for coatings; contractor's price |
| Hazardous waste collection | £150–£350 per collection | £180–£380 | £200–£450 | £150–£350 | Or £30–£60 per bag at a licensed site |
| Coving off and refit, per linear metre | £8–£15 | £10–£18 | £12–£20 | £120–£220 | Overboarding only |
| Decoration, mist coat + two coats | £8–£14 | £10–£16 | £12–£20 | £100–£170 | Often excluded |
Detailed Guidance
Step one: the sample sets the price
A quote for Artex removal before a sample result is a quote for one of two completely different jobs, and the difference is £300–£500 on a bedroom ceiling. The sequence that avoids the argument:
- Survey visit — identify every textured surface, note the pattern, the condition (sound, flaking, water-stained, previously painted), the ceiling height, the fittings and the coving. Take a sample from each distinct application using the wet method: dampen the surface, score a 2–3 cm piece into a sealable bag, seal the sample point with PVA or tape, and label it. See artex removal skim coating for the full sampling method and asbestos sampling for the precautions
- Laboratory — £30–£80 per sample. Charge the customer for it as a line on the survey invoice or as a line on the quote; it is not free, and the result belongs to them
- Quote with the result — either a firm price for the method the result allows, or a quote with two priced options ("if the sample is negative, £X; if positive, £Y") where the customer wants a figure before the result
A coating that has previously been painted with several coats of emulsion is often better sealed than a bare one, but paint does not remove the asbestos, and sanding painted Artex to a key releases fibres just the same.
Pricing a skim-over
The skim-over is appropriate when the coating is sound, firmly bonded, dry and not stippled so deeply that the finish coat cannot cover it. The labour build-up for one plasterer on a 12 m² ceiling:
| Item | Time / quantity | Cost |
|---|---|---|
| Sheet up, knock back high points (scraper, no abrasive), clear | 0.5 hr | — |
| Bonding agent to the whole surface (two coats on a heavy stipple) | 0.5 hr, 1 litre | £8–£12 |
| Bonding coat to fill deep pattern where needed | 1 hr, half a bag | £6–£10 |
| Two-coat skim, trowel up | 2.5 hr, 1.5 bags multi-finish | £15–£22 |
| Clean up, remove sheets | 0.5 hr | — |
| Total | 5 hr, materials £30–£45 |
At a plasterer's day rate of £220–£300 (see plasterer day rate guide) the labour is £140–£200, materials with 20% markup £36–£54, and the charged price £250–£450 for the ceiling, which is the £15–£30/m² band at 12 m². Where the coating is deeply combed or fan-patterned a bonding coat across the whole ceiling adds half a day and a bag, and the figure moves to the top of the band. Note that skim-over does not remove any asbestos; the coating stays in place, sealed, and the customer must be told so that it goes on their records.
Pricing an overboard
Overboarding is the method when the coating is unstable, water-damaged or so deep that a skim cannot hide it, and the customer does not want it removed. Two operatives, 12 m² ceiling:
| Item | Time / quantity | Cost |
|---|---|---|
| Locate joists, mark, remove coving, drop light fitting | 1 hr | — |
| 12.5 mm plasterboard 2400 × 1200, 5 boards with waste | 2 hr | £45–£65 |
| Screws 38 mm at 230 mm centres, scrim, jointing | 0.5 hr | £10–£15 |
| Two-coat skim | 2.5 hr, 1.5 bags | £15–£22 |
| Refit coving (or new), re-hang light with longer fixings | 1 hr | £20–£60 |
| Total | 7 hr for two (14 labour hours), materials £90–£160 |
Charged at £450–£700 for the ceiling, or £30–£50/m² with the coving and fittings as separate lines. Use 38 mm screws into the joists through the existing board and coating (not into the coating alone), and screw at 230 mm centres on a ceiling; see plasterboard types and plasterboard quantities. Where the ceiling forms part of a fire-separating floor (a flat, or a three-storey house) the board and its fixing must maintain the fire resistance under Approved Document B; a 12.5 mm board over an existing lath-and-plaster or plasterboard ceiling generally improves it, but check before promising anything. Overboarding leaves the asbestos in place; record that on the invoice.
Pricing a wet scrape (asbestos-free)
When the sample is negative and the customer wants the coating gone, wet stripping is a steam or warm-water soak and scrape, which is slow and messy, and it leaves a surface that needs a bonding coat before the skim. Output 8–15 m² a day for one operative plus a half-day for the bonding coat and skim. At £20–£40/m² a 12 m² ceiling is £350–£600 including the skim. It is rarely cheaper than a skim-over, so sell it only where the coating is failing or where the customer wants the original ceiling back (lath and plaster, ornate cornice). Protect the floor completely; the scrapings are wet plaster slurry and they get everywhere.
Pricing removal where asbestos is present
Removal of a textured coating that contains asbestos is generally non-licensed work under CAR 2012, provided it is done by trained operatives using methods that keep fibre release low (wet, by hand, small areas at a time). It becomes notifiable non-licensed work (NNLW) when the coating is removed in a way that breaks it up more, or where the material is badly degraded, and NNLW requires notification to HSE before the work, medical surveillance of the operatives and a record of the work. The decision is the contractor's under HSE's NNLW guidance; if you are not sure, treat it as NNLW or bring in a licensed contractor. See notifiable non licensed work nnlw and hse licensed removal asbestos.
The cost build-up for a 12 m² ceiling, two trained operatives:
| Item | Cost |
|---|---|
| Polythene enclosure of the room, floor and walls, airlock at the door | £40–£70 materials, 1 hr |
| Disposable coveralls (Type 5/6), FFP3 RPE, gloves, overshoes — per person per shift | £15–£25 each |
| Wetting agent / steam, hand scrapers, Class H vacuum (hire £40–£80/day if not owned) | £30–£80 |
| Removal: wet, scrape into bags at the point of work, 8–12 m² a day for two | 1–1.5 days |
| Asbestos waste bags (red inner, clear outer), labels, tape | £20–£40 |
| Waste: 3–5 bags from a 12 m² ceiling, consigned to a licensed site | £150–£350 |
| Decontamination, air clearance visual, clean down with Class H | 1 hr |
| NNLW notification (online, no fee) and records, where it applies | 0.5 hr admin |
| Bonding coat and skim (separate line) | £200–£350 |
At two operatives for 1.5 days at £220–£300 each, labour is £660–£900; consumables and waste £300–£600; the removal alone comes to £500–£900 (£40–£70/m²) and the skim is £200–£350 on top. London adds parking, the extra cost of waste disposal and a higher day rate: £55–£90/m². Any quote below £35/m² for removing an asbestos-containing coating is a quote that leaves out the training, the RPE, the waste or all three.
Worked example: three-bedroom semi, all ceilings
Customer wants flat ceilings throughout: lounge 18 m², kitchen/diner 16 m², hall and landing 10 m², three bedrooms 12 + 10 + 8 m², bathroom 5 m². Total 79 m². Samples: six taken, two positive (the two front bedrooms, done in the 1970s), four negative (re-coated in the 1990s with an asbestos-free product).
Samples, 6 × £45 = £270
Positive ceilings, 22 m², non-licensed wet removal
× £55 (incl. enclosure, RPE, waste) = £1,210
Positive ceilings, bonding coat and skim, 22 m² × £20 = £440
Negative ceilings, 57 m², skim over intact coating × £22 = £1,254
Bathroom (5 m² of the 57) deep stipple: bonding coat
uplift = £60
Coving removal and refit, lounge, 17 lin m × £10 = £170
Light fittings dropped and re-hung, 7 × £20 = £140
--------
Quote, excluding decoration £3,544
Decoration excluded (mist + 2 coats, 79 m² × £11 = £869 if
required)
Programme: 6 days — removal 2, skimming 3.5, snagging 0.5
The positive ceilings are 28% of the area and 47% of the price. That is the figure the sample protects.
What goes on the quote
- The method for each ceiling, by name, and the sample reference it was based on
- A statement that a skim-over or overboard leaves the coating in place and that the customer should keep the sample certificate with the house papers
- Waste: whose responsibility, and that asbestos waste is consigned (give the consignment note number on the invoice)
- Decoration and coving: included or excluded
- The day rate for extras (a second coating found under the first, a ceiling that will not take a skim because the coating is loose)
- Payment: materials deposit on anything over £800; stage payment after removal and before skimming on larger jobs
Frequently Asked Questions
How much does it cost to remove Artex from a ceiling?
In 2026, £250–£450 to skim over a sound asbestos-free coating on a 12 m² ceiling, £450–£700 to overboard it, and £500–£900 plus £200–£350 for the skim where the coating contains asbestos and is removed by trained operatives as non-licensed work, all outside London. London is 25–40% more. The asbestos test (£30–£80 per sample) comes first and decides which of those jobs it is.
Can a plasterer remove Artex that contains asbestos?
Yes, if the work is non-licensed or NNLW and the plasterer and their operatives have had asbestos awareness and task-specific training, use wet methods, wear FFP3 RPE and disposable coveralls, enclose the work area, and dispose of the waste as hazardous waste through a licensed carrier. The requirement is in the Control of Asbestos Regulations 2012 (regulations 10, 11 and 16 in particular). Where the coating is badly deteriorated or the method would generate significant dust, it is a licensed contractor's job.
Is it cheaper to skim over Artex than to remove it?
Almost always. Skimming over a sound coating is £15–£30/m²; removal with asbestos present is £40–£70/m² plus the skim. The skim-over leaves the coating sealed in place, which is legal and safe while it stays undisturbed, but the customer should be told it is still there, because the next tradesperson who drills a downlighter hole needs to know.
Do I need to notify HSE to remove Artex?
Not for most textured-coating removal, which is non-licensed work with no notification. Where the method or the condition of the coating pushes the work into NNLW, you notify HSE online before starting (no fee), keep a register of the work and the operatives, and the operatives need medical surveillance every three years. HSE's NNLW decision guidance sets out which is which; if in doubt, notify.
What do I do with the waste?
Textured-coating waste containing asbestos is hazardous waste. Double-bag it in asbestos bags (labelled red inner, clear outer), keep it wet, and either arrange a collection by a licensed hazardous-waste carrier (£150–£350) or take it to a site licensed to accept it (£30–£60 per bag) with a consignment note. Never put it in a general skip or household waste; see asbestos waste disposal.
Regulations & Standards
Control of Asbestos Regulations 2012 (SI 2012/632) — the duty to assess, the training requirement (reg 10), the licensing threshold (reg 8), NNLW notification (reg 9), control measures and RPE (reg 11), waste (reg 24)
HSE Approved Code of Practice L143 (2nd edition, 2013) — Managing and working with asbestos: the ACoP supporting CAR 2012
HSE HSG210 — Asbestos essentials — task sheets for non-licensed work including textured decorative coatings; method, equipment and PPE
HSE HSG247 — Asbestos: the licensed contractors' guide — where licensed removal applies
Hazardous Waste (England and Wales) Regulations 2005 (SI 2005/894) — asbestos waste classification, consignment notes, registered carriers
Control of Substances Hazardous to Health Regulations 2002 (SI 2002/2677) — plaster and silica dust from scraping and sanding
Health and Safety at Work etc. Act 1974 — general duties to operatives and the household
Construction (Design and Management) Regulations 2015 (SI 2015/51) — domestic client duties pass to the contractor; asbestos in the pre-construction information
Building Regulations 2010, Approved Document B (Volume 1: Dwellings) — fire resistance of ceilings forming part of separating floors, relevant to overboarding
BS 8000-0:2014+A1:2024 — workmanship on construction sites; general principles
BS EN 13914-2:2016 — design, preparation and application of internal plastering
BS EN 520:2004+A1:2009 — gypsum plasterboards; definitions, requirements and test methods
Consumer Rights Act 2015 (s.49–s.52) — reasonable care and skill; reasonable price where none agreed
HSE — Asbestos essentials task sheets (non-licensed work) — methods, PPE and equipment for textured coatings
HSE — Notifiable non-licensed work (NNLW) — which work must be notified and how
HSE — Managing and working with asbestos: L143 — the Approved Code of Practice under CAR 2012
Control of Asbestos Regulations 2012 — the statutory text
GOV.UK — Dispose of hazardous waste — consignment notes and registered carriers
UKAS — Find an accredited laboratory — asbestos bulk sample analysis
artex removal skim coating — the technical method: sampling, skim-over, overboard and wet-strip step by step
skim over artex and old surfaces — bonding agents, bonding coat and skim technique over textured coatings
asbestos in textured coatings — the asbestos content, identification and legal position of textured coatings
control of asbestos regs 2012 — CAR 2012 duties, training and the licensed / NNLW / non-licensed tiers
notifiable non licensed work nnlw — when removal becomes NNLW and what notification involves
asbestos waste disposal — bagging, consignment notes and licensed sites
asbestos survey pricing guide — pricing the sampling and survey visit
skim coat pricing guide — skim pricing per m² for the finish after removal
plasterer day rate guide — the day rate the per-metre figures are built from
artex asbestos — the decorator's view of pre-2000 textured coatings