Summary

Builders, kitchen fitters and loft converters live downstream of architects. The customer's "we've got drawings" means the design fee has already been spent, the planning application is in, and the tradesperson is now pricing against someone else's specification. Knowing what the architect was paid, for which stages, and what that fee did and did not include tells you how complete the information really is. A customer who paid £1,800 for "planning drawings" has a set of 1:100 elevations and no structural detail, no construction drawings, no specification and no Building Regulations package. Pricing that job as if it were fully designed is how a £75,000 extension becomes a £95,000 argument.

There is also a direct commercial angle. Tradespeople increasingly offer design-and-build: they sub-contract an architect or technologist, mark the fee up and present one price. To do that profitably you need to know the market rate for each stage, when a technologist is enough, when the job genuinely needs a registered architect (planning appeals, listed buildings, complex sites, party wall and rights-of-light disputes), and what the structural engineer, party wall surveyor and building control fees will add on top. This guide separates the stages, gives the fee bands for each, and explains the contractual terms (RIBA Domestic Professional Services Contract, stage payments, "additional services") that catch customers out.

Finally, the fee shapes the build sequence. Full-service appointments include contract administration under RIBA Stage 5, where the architect values the works, certifies stage payments and can instruct variations. Planning-only appointments leave the builder dealing directly with building control and the customer. Which one applies changes who you are answerable to on site and how you get paid.

Key Facts

Quick Reference Table

Spending too long on quotes? squote turns a 2-minute voice recording into a professional quote.

Try squote free →
Job Construction cost Planning drawings (Stage 3) Building Regs package (Stage 4) Full service (Stages 0–6)
Single-storey rear extension £50,000–£90,000 £1,500–£3,500 £2,500–£5,500 £6,000–£12,000
Two-storey rear/side extension £90,000–£160,000 £2,500–£5,000 £4,000–£8,000 £10,000–£20,000
Loft conversion with dormer £45,000–£75,000 £1,500–£3,000 £2,500–£4,500 £5,000–£9,000
Whole-house refurbishment £120,000–£250,000 £3,000–£6,000 £6,000–£12,000 £14,000–£30,000
Garage conversion £15,000–£30,000 £800–£1,800 £1,200–£2,500 £2,500–£5,000
New-build detached house £300,000–£600,000 £6,000–£15,000 £10,000–£25,000 £25,000–£55,000
Listed building alterations Varies £3,000–£8,000 (incl. heritage statement) £5,000–£12,000 12–20% of cost

Figures are 2024 regional England. London and the South East add 20–40%. Measured survey, structural engineer, planning and building control fees, party wall surveyors and CDM principal designer duties are usually extra.

Detailed Guidance

The three fee structures and when each is used

Percentage of construction cost is the traditional model and still common for full-service work. The architect quotes, say, 11% of the final construction cost. The advantage for the customer is that the fee tracks the scope; the disadvantage is that the architect is paid more when the build costs more, and the customer only learns the real fee when tenders come back. Watch for the definition of "construction cost": most contracts use the final account including variations but excluding VAT, fees and the customer's own purchases (kitchens, sanitaryware). A customer who assumes the fee is fixed at the feasibility estimate will be surprised when a £60,000 estimate becomes an £85,000 tender and the fee rises with it.

Fixed lump sum per stage is now the most common domestic structure. The architect prices each RIBA stage separately and the customer can stop after any stage. This is what a typical "£2,400 for planning drawings" quote is. The lump sum assumes a defined scope, usually one design option developed to planning and one round of revisions. Change the brief after planning and the Stage 4 fee is re-quoted.

Hourly or day rates are used for feasibility work, planning appeals, additional services, listed building consent negotiations and site visits beyond the agreed number. A full-service domestic appointment often has a fee cap for Stage 5 site attendance (for example "fortnightly site visits, 12 in total, additional visits at £140 per hour").

What each RIBA stage actually delivers

Tradespeople pricing from drawings need to know which stage the drawings represent.

RIBA stage What the customer receives What is missing for a builder
0–1 Strategic Definition / Preparation and Briefing Feasibility sketches, site appraisal, budget range Everything
2 Concept Design Plans, elevations and sections at 1:100; massing; initial planning strategy Structure, services, materials, details
3 Spatial Co-ordination (planning) Planning drawings: existing and proposed plans, elevations, sections, site plan at 1:1250/1:500, design and access statement where needed Construction details, specification, structural design, drainage design, U-values
4 Technical Design (Building Regs and construction) 1:50 construction plans, 1:20 and 1:5 details, written specification, door and window schedules, drainage layout, structural engineer's drawings co-ordinated, SAP/U-value calculations Nothing essential; this is the set to price from
5 Manufacturing and Construction Contract administration, site inspections, valuations, instructions n/a
6 Handover Snagging, final certificate, defects period administration n/a

The commercial trap is Stage 3. The customer has paid for "the drawings", planning permission is granted, and they ask three builders to quote. Each builder is guessing at foundation depth, steel sizes, insulation specification, roof build-up and drainage route. Quotes vary by 30% or more because each builder has priced a different building. Insist on a Stage 4 package, or price your own design development time and exclusions explicitly. See building control process for what building control will want to see.

Architect, technologist or architectural designer

The job dictates the professional, not the other way round.

For a tradesperson offering design-and-build, a technologist is usually the right sub-consultant for Stages 3–4 on ordinary domestic work; bring in an architect where planning risk is real.

What is usually excluded from a quoted fee

Read the services schedule. Common exclusions that become additional charges or separate appointments:

A customer's "the architect's fee was £9,000" may therefore represent £9,000 plus another £4,000–£7,000 of consultants and statutory fees they did not count.

How architects' fees affect the build contract and your cashflow

Under a full-service appointment, the architect administers a building contract, typically the JCT Minor Works or Home Owner contract, or the RIBA Domestic Building Contract. Practical consequences for the builder:

Pricing a design-and-build offer

Worked example for a single-storey rear extension with an £80,000 construction cost:

Item Cost to you Markup Price to customer
Measured survey (sub-consultant) £550 15% £633
Stage 3 planning drawings (technologist) £1,900 15% £2,185
Planning application fee £258 0% (disbursement) £258
Stage 4 Building Regs package £3,200 15% £3,680
Structural engineer £850 15% £978
Building control (approver) £780 0% (disbursement) £780
Your co-ordination time (12 hours at £45) £540 25% £675
Design package total £8,078 £9,189

Present the statutory fees as disbursements at cost; mark up the professional work and your time. The customer sees one number, you control the information you build from, and the technologist's drawings are co-ordinated with how you actually build rather than how a stranger assumed you would.

Frequently Asked Questions

Can I call myself an architect if I design extensions?

No. The title "architect" is reserved by the Architects Act 1997 for people on the ARB register, which requires a recognised Part 1, Part 2 and Part 3 qualification route or an ARB prescribed equivalent. You may describe yourself as offering "architectural design services", "architectural drawings" or "design and build". ARB actively pursues misuse, and insurers may refuse a claim where the title was used fraudulently.

Does a customer need an architect for a small extension?

Not legally. Planning and Building Regulations applications can be submitted by anyone, including the homeowner or the builder. For a permitted-development single-storey extension on a plain site, a technologist or competent plan drawer plus a structural engineer is normal. A registered architect earns their fee where planning risk, design complexity or heritage constraints exist, or where the customer wants contract administration.

Why do architects' quotes vary so much?

Scope and seniority. One quote covers Stage 3 only; another covers Stages 0–4 with a measured survey included; a third includes contract administration. One practice bills director time at £220 per hour; another uses a Part 2 assistant at £70. Ask every architect to break the quote down by RIBA stage and to list exclusions, then compare like with like.

Who is responsible if the drawings are wrong?

The architect or technologist owes a duty of reasonable skill and care and carries PII for exactly this. However, the builder is still responsible for building in accordance with the Building Regulations and for raising obvious errors. If a drawing shows a 150 mm steel over a 5 m opening and you build it, you share the liability. Query it in writing before you build it.

Should the builder be involved before Stage 4?

Ideally yes. Early contractor involvement at Stage 2–3 catches buildability and cost problems before they are drawn into the planning submission. Many architects resist it because it compromises competitive tendering; many customers are happy to appoint a preferred builder early in exchange for a transparent cost plan. A fixed-fee pre-construction agreement for your input (£400–£900) is a reasonable way to charge for that time.