Summary
Almost every notifiable job a tradesperson prices starts with the same question from the customer: do we need drawings for Building Control? The answer is that the Building Regulations give the applicant a choice. Deposit full plans and have them checked and approved before the first brick is laid, or serve a building notice, start in two days, and have the work inspected as it goes. Both end in a completion certificate if the work complies. They differ in cost, timing, certainty and who carries the risk if the design turns out to be wrong.
For a straightforward domestic job with a standard detail (a replacement boiler on a notice to Gas Safe, a new bathroom, a knock-through with a lintel from a manufacturer's span table, a small single-storey extension on a well-understood site) the building notice is quicker and cheaper and the inspector will tell you what they want at each stage. For anything structural that is not off a span table, anything with an unusual drainage or fire situation, anything where the customer wants the certainty of an approval before committing, or anything a mortgage lender or warranty provider will ask to see plans for, full plans is the right route and the one that protects the builder.
There is a third route for work done without any application, regularisation, and a private-sector alternative to the local authority for both routes, the initial notice through a registered building control approver. This guide sets out all four, the exclusions, the notices to give during the work, the fees, the 2023 changes to commencement and lapse, and how to advise a customer which to use.
Key Facts
- Legal basis — Building Act 1984 and the Building Regulations 2010 (as amended); Regulation 12 sets out when a notice or plans must be given, Regulation 13 the content of a building notice, Regulation 14 full plans, Regulation 16 the notices during the work, Regulation 17 completion certificates, Regulation 18 regularisation
- Building notice — written notice to the local authority at least two working days before work starts, with a site location plan and a description of the work; no plans are approved; the authority inspects the work as it proceeds and can require plans or calculations for particular elements (structural calculations for a steel, for example) at any stage
- Full plans — drawings, specification and, where relevant, structural calculations and drainage layout deposited for checking; the authority must approve or reject within five weeks, extendable to two months with the applicant's written agreement; approval can be conditional or in stages; a rejection must give reasons
- Protection of full plans — once plans are approved and the work is built to them, the authority cannot later require that element to be changed for non-compliance; with a building notice there is no such protection and non-compliant work found at inspection must be put right
- Building notice exclusions — cannot be used where the Regulatory Reform (Fire Safety) Order 2005 applies or will apply to the building (any non-domestic premises, and the common parts of flats and HMOs), or where requirement H4 (building over or within 3 m of a public sewer) applies; higher-risk buildings in England go through the Building Safety Regulator under a separate regime
- Competent person schemes — work self-certified by a registered installer (Gas Safe, NICEIC, NAPIT, FENSA, Certass, HETAS, OFTEC and others) needs no application at all; the installer notifies the scheme and the scheme notifies the authority (see competent person schemes list)
- Initial notice — the private alternative: a registered building control approver (formerly an approved inspector) gives an initial notice to the local authority jointly with the client; the authority has five working days to reject it; the approver then checks plans and inspects, and issues a final certificate; the initial notice also lapses if work has not commenced within three years
- Commencement, England, from 1 October 2023 — the Building Regulations etc. (Amendment) (England) Regulations 2023 define when work has commenced: for a new building, when the foundations and the structure up to and including damp-proof course level are complete; for other work (extensions, alterations), when 15% of the proposed work has been completed as described in the application; a notice must be given within five working days of commencement
- Lapse — for applications made on or after 1 October 2023 in England, a building notice, full plans application or initial notice lapses if the work has not commenced as defined within three years of the application; a new application is then needed under the regulations in force at that time
- Notices during the work (Regulation 16) — at least two days before commencement; at least one day before covering foundations excavations, foundation concrete, damp-proof course, oversite material, and drains or sewers; within five days after drains are backfilled or tested; within five days after completion; at least five days before occupation if the building is occupied before completion
- Completion certificate (Regulation 17) — the authority must issue a completion certificate or a notice of refusal within eight weeks of being told the work is complete (in England, since the 2023 amendments); the certificate is the document a solicitor asks for on sale
- Regularisation (Regulation 18) — for work carried out on or after 11 November 1985 without an application; the authority may require exposure, testing and remedial work before issuing a regularisation certificate; the fee is typically 120–150% of the building notice charge (see retrospective approval)
- Fees — set by each authority under the Building (Local Authority Charges) Regulations 2010; a full plans application has a plan charge and an inspection charge, a building notice a single charge usually equal to the two combined; a small domestic extension typically £500–£1,000 in total, a garage conversion or loft conversion £400–£900, minor works a fixed charge of £150–£400
- Planning is separate — neither route is a planning application; planning permission or permitted development is a separate question (see planning vs building regs)
- Wales — the Building Regulations 2010 apply with Welsh amendments and the same two routes; the 2023 English commencement and lapse rules do not apply in Wales, which has its own 2025 amendments with equivalent provisions for initial notices
- Scotland — different system: a building warrant from the local authority verifier must be obtained before work starts and a completion certificate accepted at the end (see building warrant scotland guide)
Quick Reference Table
Need to quote compliant work? squote includes relevant regulations in your quotes.
Try squote free →| Factor | Building notice | Full plans | Initial notice (private approver) |
|---|---|---|---|
| What is submitted | Notice, site plan, description | Drawings, specification, calculations, drainage | Notice to the authority; plans to the approver |
| Notice period before start | 2 working days | None once approved; work can start before approval at the applicant's risk | 5 working days for the authority to reject the notice |
| Checking before work | None | Full check, decision in 5 weeks (2 months by agreement) | By the approver, to their own timescale |
| Protection if design wrong | None; put it right at inspection | Approved elements protected | Approver's plans certificate gives similar protection |
| Can be used for non-domestic (fire order) buildings | No | Yes | Yes |
| Can be used for building over or near a public sewer (H4) | No | Yes | Yes |
| Structural calculations | Can be demanded during the work | Deposited with the plans | Deposited with the approver |
| Fee structure | Single charge | Plan charge + inspection charge | Approver's commercial fee |
| Final document | Completion certificate from the authority | Completion certificate from the authority | Final certificate from the approver, copied to the authority |
| Lapse (England, applications from 1 Oct 2023) | 3 years without commencement | 3 years without commencement | 3 years without commencement |
| Best for | Small domestic jobs with standard details | Structural, drainage, fire or anything the customer wants certainty on | Larger projects, developers, where a single point of contact is wanted |
Detailed Guidance
Decide whether an application is needed at all
Work that is self-certified under a competent person scheme needs no notice or plans: a boiler replacement by a Gas Safe engineer, a rewire or new circuit by a registered electrician, replacement windows by a FENSA or Certass installer, a stove by a HETAS installer. The installer's scheme notifies the authority and the certificate arrives in the post. Work that is exempt under Schedule 2 (a detached garage under 30 m², a porch under 30 m², most conservatories, a shed) needs nothing. Everything else that is "building work" under Regulation 3 (a new building, an extension, a material alteration such as a structural opening or a change to a fire-resisting element, work on a controlled service or fitting, a material change of use, insulation to a thermal element) needs one of the routes below. When in doubt, the authority's duty officer will tell you in a five-minute call, and that call costs nothing.
Building notice: when it is the right choice
The building notice suits work the inspector can assess on site against standard guidance. A rear extension with a lintel from a manufacturer's table, strip foundations to the depth the inspector asks for at the trench inspection, a standard insulation build-up and a drainage run the inspector can see before it is covered. The customer saves the cost of drawings for Building Regulations purposes (they may still want drawings for the builder and for planning) and the job starts two working days after the notice.
The risks are two. First, there is no approval, so if the inspector finds at the trench that the ground needs a deeper foundation or at the steel that the calculation is not what they expected, the work stops and is changed at the builder's cost unless the contract says otherwise. Second, the authority can demand plans and calculations for any element at any time (a structural engineer's calculation for a beam is routinely asked for), so the absence of plans does not mean the absence of design.
Put the design risk in the contract. A building notice job quoted at a fixed price should say that the price is based on foundations to a stated depth and standard details, and that Building Control requirements beyond those are a variation.
Full plans: when it is the right choice
Full plans suits anything where getting the design wrong is expensive to correct: structural steelwork, openings in load-bearing walls where the loads are not simple, foundations near trees or on made ground, a loft conversion with its fire strategy of protected stair and escape windows, a basement, any drainage arrangement involving a build-over agreement, anything where the fire order applies. It is compulsory for the fire-order buildings and the H4 sewer cases, and it is the only route that gives the customer an approval notice they can show a lender, an insurer or a warranty provider.
The authority has five weeks to decide. A conditional approval lets the work start while a detail (often the structural calculations or the drainage) is agreed. A rejection gives reasons and the plans can be amended and resubmitted, usually without a further plan charge. Work may lawfully start before the decision, with two days' notice as for a building notice, but anything built before approval that then has to change is at the applicant's cost.
The notices during the work
Whichever route, the inspection stages are the same and the builder is the one on site to give them. In England the 2023 amendments added a formal commencement notice; the rest is long-standing Regulation 16:
- Commencement — at least two days before starting. In England, for applications from 1 October 2023, also a notice within five working days after the work reaches the commencement definition (foundations and structure to DPC for a new building; 15% of the described work for other work).
- Foundation excavation — before concrete goes in.
- Foundation concrete — before it is covered.
- Damp-proof course — before it is covered.
- Oversite — before the floor goes down over it.
- Drains — before they are covered, and again within five days of backfilling or when ready for test.
- Completion — within five days of finishing.
- Occupation before completion — at least five days before anyone moves in.
Missing a stage gives the inspector the right to require the work to be opened up under Regulation 16, which on a covered drain run is a day's labour. Phone or email the stage notices and keep the record.
Commencement and lapse since October 2023 (England)
Before 1 October 2023 an application lapsed only if the authority chose to serve a notice after three years. For applications made since then, the three-year lapse is automatic and "commenced" has a definition. For a new building it means the foundations and the structure up to and including the DPC. For other work it means that 15% of the work described in the application has been completed; the applicant states in the application what that 15% is. An extension that has been dug and concreted but with nothing above the footings may not have "commenced" if the application said otherwise. Serve the commencement notice within five working days of reaching the point, and keep a dated photograph.
The practical effect is that a customer who got a full plans approval in 2024 and starts in 2027 may find the approval has lapsed and the work must comply with the regulations in force when the new application is made, which may mean a different Part L.
Completion certificates and what they are worth
The completion certificate says that, as far as the authority could ascertain from its inspections, the work complies. It is not a warranty and it does not cover what the inspector did not see, but a solicitor on sale will ask for it and a mortgage lender will want it. Since the 2023 amendments the authority must either issue it or refuse it within eight weeks of being told the work is complete; chase it if it has not arrived. Where it is refused the reasons are given and the work is corrected and re-inspected.
A regularisation certificate for work done without an application carries less weight and often comes with a list of conditions (opening up, testing, additional insulation) because the inspector never saw the hidden work.
Advising the customer and pricing the job
Tell the customer which route you recommend and why, in the quote. On a building notice job, itemise the authority's charge (usually paid by the customer direct) and state the assumed foundation depth and standard details. On a full plans job, price the drawings and the structural calculations separately from the build, with the authority's plan and inspection charges shown, and allow four to six weeks between submission and start. Never let a customer believe that a building notice avoids the need for a structural engineer where a steel is involved; it only moves the moment at which the inspector asks for the calculation.
Frequently Asked Questions
Can a building notice be used for a loft conversion?
Yes, in a single dwelling, and many are done that way, but a loft conversion is the job where full plans is most often the better advice: the fire strategy (protected stair enclosure, fire doors, escape windows, smoke alarms), the floor fire resistance, the steelwork and the stair all interact, and an inspector finding at second fix that the stair enclosure does not meet Approved Document B is an expensive conversation. If the house is a flat or a maisonette the common parts fall under the fire order and full plans is compulsory.
Does the customer or the builder make the application?
Either can, and the application is made in the name of the person carrying out the work or the owner. The fee is usually paid by the owner. On a building notice the builder is normally the one giving the stage notices. Put in the contract who does what, because a missed stage notice is the builder's problem on site whoever signed the form.
What if work starts without any application?
The authority can serve a notice requiring the work to be removed or altered under Section 36 of the Building Act 1984 within twelve months of completion, can prosecute the person carrying out the work under Section 35, and the owner is left with a property that cannot be sold cleanly without a regularisation certificate. Regularisation is available for work since 11 November 1985, at a higher fee and with the authority entitled to open up the work.
Is an approved inspector the same as the local authority?
The private route (now a registered building control approver under the Building Safety Act 2022 regime, with registered building inspectors from April 2024) performs the same function and issues a final certificate instead of a completion certificate. The authority keeps a reserve enforcement role. The initial notice must be accepted by the authority before work starts, and if the approver's engagement ends before the final certificate the work reverts to the authority, often with a regularisation-style process for what has been built.
Regulations & Standards
Building Act 1984 — Sections 35 and 36 enforcement; Section 47 initial notices; the Act under which the regulations are made
Building Regulations 2010 (SI 2010/2214, as amended) — Regulation 12 giving of a building notice or deposit of plans; Regulation 13 particulars of a building notice; Regulation 14 full plans; Regulation 16 notices of commencement and completion; Regulation 17 completion certificates; Regulation 18 regularisation; Regulation 46A commencement (England)
Building Regulations etc. (Amendment) (England) Regulations 2023 (SI 2023/911) — the definition of commencement, the three-year lapse and the eight-week completion certificate duty in England from 1 October 2023
Building (Registered Building Control Approvers etc.) (England) Regulations 2024 — the private building control route in England
Building (Local Authority Charges) Regulations 2010 — how authorities set their charges
Regulatory Reform (Fire Safety) Order 2005 — the buildings for which a building notice cannot be used
Building Safety Act 2022 — the regime for higher-risk buildings and the registration of building control approvers and inspectors
Building (Scotland) Regulations 2004 and the Building (Scotland) Act 2003 — the building warrant system in Scotland
GOV.UK — Building regulations approval — the government's plain-English guide to the two routes
legislation.gov.uk — The Building Regulations 2010 — Regulations 12 to 18 in full
legislation.gov.uk — The Building Regulations etc. (Amendment) (England) Regulations 2023 — commencement and lapse provisions
Planning Portal — Building control applications — making an application online to any English or Welsh authority
LABC — Building notice or full plans? — local authority building control guidance on choosing
Welsh Government — Building regulations guidance — the Welsh position
building control — how Building Control works and what inspectors look for
completion certificates — what the certificate covers and chasing it
approved inspectors — the private building control route
retrospective approval — regularisation for unauthorised work
labc vs self certify — when a competent person scheme replaces the application
building regs overview — the Parts and what triggers them
planning vs building regs — the two separate consents
building over a sewer build over agreement — the H4 case where full plans is compulsory