Summary

Almost every notifiable job a tradesperson prices starts with the same question from the customer: do we need drawings for Building Control? The answer is that the Building Regulations give the applicant a choice. Deposit full plans and have them checked and approved before the first brick is laid, or serve a building notice, start in two days, and have the work inspected as it goes. Both end in a completion certificate if the work complies. They differ in cost, timing, certainty and who carries the risk if the design turns out to be wrong.

For a straightforward domestic job with a standard detail (a replacement boiler on a notice to Gas Safe, a new bathroom, a knock-through with a lintel from a manufacturer's span table, a small single-storey extension on a well-understood site) the building notice is quicker and cheaper and the inspector will tell you what they want at each stage. For anything structural that is not off a span table, anything with an unusual drainage or fire situation, anything where the customer wants the certainty of an approval before committing, or anything a mortgage lender or warranty provider will ask to see plans for, full plans is the right route and the one that protects the builder.

There is a third route for work done without any application, regularisation, and a private-sector alternative to the local authority for both routes, the initial notice through a registered building control approver. This guide sets out all four, the exclusions, the notices to give during the work, the fees, the 2023 changes to commencement and lapse, and how to advise a customer which to use.

Key Facts

Quick Reference Table

Need to quote compliant work? squote includes relevant regulations in your quotes.

Try squote free →
Factor Building notice Full plans Initial notice (private approver)
What is submitted Notice, site plan, description Drawings, specification, calculations, drainage Notice to the authority; plans to the approver
Notice period before start 2 working days None once approved; work can start before approval at the applicant's risk 5 working days for the authority to reject the notice
Checking before work None Full check, decision in 5 weeks (2 months by agreement) By the approver, to their own timescale
Protection if design wrong None; put it right at inspection Approved elements protected Approver's plans certificate gives similar protection
Can be used for non-domestic (fire order) buildings No Yes Yes
Can be used for building over or near a public sewer (H4) No Yes Yes
Structural calculations Can be demanded during the work Deposited with the plans Deposited with the approver
Fee structure Single charge Plan charge + inspection charge Approver's commercial fee
Final document Completion certificate from the authority Completion certificate from the authority Final certificate from the approver, copied to the authority
Lapse (England, applications from 1 Oct 2023) 3 years without commencement 3 years without commencement 3 years without commencement
Best for Small domestic jobs with standard details Structural, drainage, fire or anything the customer wants certainty on Larger projects, developers, where a single point of contact is wanted

Detailed Guidance

Decide whether an application is needed at all

Work that is self-certified under a competent person scheme needs no notice or plans: a boiler replacement by a Gas Safe engineer, a rewire or new circuit by a registered electrician, replacement windows by a FENSA or Certass installer, a stove by a HETAS installer. The installer's scheme notifies the authority and the certificate arrives in the post. Work that is exempt under Schedule 2 (a detached garage under 30 m², a porch under 30 m², most conservatories, a shed) needs nothing. Everything else that is "building work" under Regulation 3 (a new building, an extension, a material alteration such as a structural opening or a change to a fire-resisting element, work on a controlled service or fitting, a material change of use, insulation to a thermal element) needs one of the routes below. When in doubt, the authority's duty officer will tell you in a five-minute call, and that call costs nothing.

Building notice: when it is the right choice

The building notice suits work the inspector can assess on site against standard guidance. A rear extension with a lintel from a manufacturer's table, strip foundations to the depth the inspector asks for at the trench inspection, a standard insulation build-up and a drainage run the inspector can see before it is covered. The customer saves the cost of drawings for Building Regulations purposes (they may still want drawings for the builder and for planning) and the job starts two working days after the notice.

The risks are two. First, there is no approval, so if the inspector finds at the trench that the ground needs a deeper foundation or at the steel that the calculation is not what they expected, the work stops and is changed at the builder's cost unless the contract says otherwise. Second, the authority can demand plans and calculations for any element at any time (a structural engineer's calculation for a beam is routinely asked for), so the absence of plans does not mean the absence of design.

Put the design risk in the contract. A building notice job quoted at a fixed price should say that the price is based on foundations to a stated depth and standard details, and that Building Control requirements beyond those are a variation.

Full plans: when it is the right choice

Full plans suits anything where getting the design wrong is expensive to correct: structural steelwork, openings in load-bearing walls where the loads are not simple, foundations near trees or on made ground, a loft conversion with its fire strategy of protected stair and escape windows, a basement, any drainage arrangement involving a build-over agreement, anything where the fire order applies. It is compulsory for the fire-order buildings and the H4 sewer cases, and it is the only route that gives the customer an approval notice they can show a lender, an insurer or a warranty provider.

The authority has five weeks to decide. A conditional approval lets the work start while a detail (often the structural calculations or the drainage) is agreed. A rejection gives reasons and the plans can be amended and resubmitted, usually without a further plan charge. Work may lawfully start before the decision, with two days' notice as for a building notice, but anything built before approval that then has to change is at the applicant's cost.

The notices during the work

Whichever route, the inspection stages are the same and the builder is the one on site to give them. In England the 2023 amendments added a formal commencement notice; the rest is long-standing Regulation 16:

  1. Commencement — at least two days before starting. In England, for applications from 1 October 2023, also a notice within five working days after the work reaches the commencement definition (foundations and structure to DPC for a new building; 15% of the described work for other work).
  2. Foundation excavation — before concrete goes in.
  3. Foundation concrete — before it is covered.
  4. Damp-proof course — before it is covered.
  5. Oversite — before the floor goes down over it.
  6. Drains — before they are covered, and again within five days of backfilling or when ready for test.
  7. Completion — within five days of finishing.
  8. Occupation before completion — at least five days before anyone moves in.

Missing a stage gives the inspector the right to require the work to be opened up under Regulation 16, which on a covered drain run is a day's labour. Phone or email the stage notices and keep the record.

Commencement and lapse since October 2023 (England)

Before 1 October 2023 an application lapsed only if the authority chose to serve a notice after three years. For applications made since then, the three-year lapse is automatic and "commenced" has a definition. For a new building it means the foundations and the structure up to and including the DPC. For other work it means that 15% of the work described in the application has been completed; the applicant states in the application what that 15% is. An extension that has been dug and concreted but with nothing above the footings may not have "commenced" if the application said otherwise. Serve the commencement notice within five working days of reaching the point, and keep a dated photograph.

The practical effect is that a customer who got a full plans approval in 2024 and starts in 2027 may find the approval has lapsed and the work must comply with the regulations in force when the new application is made, which may mean a different Part L.

Completion certificates and what they are worth

The completion certificate says that, as far as the authority could ascertain from its inspections, the work complies. It is not a warranty and it does not cover what the inspector did not see, but a solicitor on sale will ask for it and a mortgage lender will want it. Since the 2023 amendments the authority must either issue it or refuse it within eight weeks of being told the work is complete; chase it if it has not arrived. Where it is refused the reasons are given and the work is corrected and re-inspected.

A regularisation certificate for work done without an application carries less weight and often comes with a list of conditions (opening up, testing, additional insulation) because the inspector never saw the hidden work.

Advising the customer and pricing the job

Tell the customer which route you recommend and why, in the quote. On a building notice job, itemise the authority's charge (usually paid by the customer direct) and state the assumed foundation depth and standard details. On a full plans job, price the drawings and the structural calculations separately from the build, with the authority's plan and inspection charges shown, and allow four to six weeks between submission and start. Never let a customer believe that a building notice avoids the need for a structural engineer where a steel is involved; it only moves the moment at which the inspector asks for the calculation.

Frequently Asked Questions

Can a building notice be used for a loft conversion?

Yes, in a single dwelling, and many are done that way, but a loft conversion is the job where full plans is most often the better advice: the fire strategy (protected stair enclosure, fire doors, escape windows, smoke alarms), the floor fire resistance, the steelwork and the stair all interact, and an inspector finding at second fix that the stair enclosure does not meet Approved Document B is an expensive conversation. If the house is a flat or a maisonette the common parts fall under the fire order and full plans is compulsory.

Does the customer or the builder make the application?

Either can, and the application is made in the name of the person carrying out the work or the owner. The fee is usually paid by the owner. On a building notice the builder is normally the one giving the stage notices. Put in the contract who does what, because a missed stage notice is the builder's problem on site whoever signed the form.

What if work starts without any application?

The authority can serve a notice requiring the work to be removed or altered under Section 36 of the Building Act 1984 within twelve months of completion, can prosecute the person carrying out the work under Section 35, and the owner is left with a property that cannot be sold cleanly without a regularisation certificate. Regularisation is available for work since 11 November 1985, at a higher fee and with the authority entitled to open up the work.

Is an approved inspector the same as the local authority?

The private route (now a registered building control approver under the Building Safety Act 2022 regime, with registered building inspectors from April 2024) performs the same function and issues a final certificate instead of a completion certificate. The authority keeps a reserve enforcement role. The initial notice must be accepted by the authority before work starts, and if the approver's engagement ends before the final certificate the work reverts to the authority, often with a regularisation-style process for what has been built.