Summary

The kitchen-diner knock-through is the most common structural job in UK domestic building and the one that most often goes wrong, because it looks simple. Two rooms become one, a steel goes in, the plasterer makes it disappear. What the customer does not see is that for the hour between the wall being cut and the beam being pinned up, the first floor, the roof and sometimes the chimney are sitting on acrow props and a few scaffold boards. That hour is where the job's risk lives.

This guide covers identifying whether a wall is load-bearing, what the engineer provides and why the builder must not substitute for them, the Building Control route, the propping sequence, forming the opening, bearings and padstones, fitting and fixing the beam, fire protection, and the finishing details that stop cracking afterwards. It assumes a conventional masonry house with timber floors; timber-frame, concrete-floor and steel-frame construction change the propping method and need the engineer's input on temporary works as well as permanent.

The two misconceptions that cause most trouble: first, that a wall running parallel to the joists cannot be load-bearing (it can carry a roof purlin strut, a chimney breast or a wall above); second, that "the engineer's calcs say a 203 × 133 UB so that is all I need to know". The calculation sheet also specifies the padstone size and grade, the bearing length, the bolting of twin beams, the lateral restraint and often the propping requirement. Every item on it is part of the design.

Key Facts

Quick Reference Table

Spending too long on quotes? squote turns a 2-minute voice recording into a professional quote.

Try squote free →
Item Typical specification Who decides
Beam section (3 m, one floor plus wall) 203 × 133 UB, S275 Structural engineer
Beam section (4 m, floor plus wall plus roof) 254 × 146 UB or twin 203 × 133 Structural engineer
Bearing length each end 150 mm minimum Structural engineer
Padstone 440 × 215 × 140 mm C35/45 precast or class B engineering brick Structural engineer
Twin beam bolting M16 or M20 at 600 mm centres with spacer tubes Structural engineer
Prop spacing 1 m maximum centres, both sides Builder (temporary works)
Strongboy capacity About 340 kg per head Manufacturer rating
Fire protection, two storeys 30 minutes: 12.5 mm fire-rated plasterboard or intumescent paint Approved Document B Vol 1
Fire protection, three storeys 60 minutes: two layers of board or heavier intumescent build Approved Document B Vol 1
Building Control fee £300–£600 Local authority or approved inspector
Engineer's fee £400–£900 single beam Market (2026)
Total job, regional England £2,800–£5,500 single beam Market (2026)
Total job, London £4,000–£8,000 single beam Market (2026)

Detailed Guidance

Is it load-bearing?

Start in the loft and work down. A wall that carries a purlin strut, a binder or a ceiling joist splice is load-bearing from the roof. On the first floor, lift a board next to the wall: joists sitting on the wall plate, or lapped over it, mean the wall carries that floor. A wall that continues directly above the one being removed is load-bearing by definition, because it is carrying its own weight plus whatever it carries. A chimney breast in the wall makes it load-bearing and makes the job larger, because the breast cannot be left hanging without a gallows bracket or beam designed for it; see chimney breast removal pricing guide.

Walls that are often wrongly assumed to be non-load-bearing: the ground-floor wall between the front and back reception rooms in a Victorian terrace (it carries the first-floor joists and the wall above, and often a purlin strut); the kitchen-to-dining wall in a 1930s semi (it carries the first-floor bathroom wall); a 100 mm blockwork wall in a 1970s house that was built as a loadbearing partition. Walls that are usually not load-bearing: stud partitions running parallel to joists with nothing above; blockwork walls where the joists run parallel and the wall above is offset; walls added after the house was built. Even then, confirm by inspection, and treat it as load-bearing if there is any doubt.

The engineer's design and what it contains

The structural engineer visits (or works from a survey and photographs on simple jobs), identifies the loads from the floor, walls and roof, and produces a calculation sheet and usually a sketch. The sheet specifies the beam section and grade, the span, the bearing length at each end, the padstone size and material, any bolting of twin beams, the end plates or bearing plates if the beam sits on a column or a steel post, the lateral restraint, and the fire protection. Some engineers also specify the temporary works (propping); where they do not, the builder designs the propping and should ask the engineer to confirm it for anything above a straightforward two-storey house.

Do not change anything on the sheet without the engineer's written agreement. Building Control inspects against the calculation; a beam one size smaller because the merchant had it in stock, or a padstone replaced with a few bricks because the course height was awkward, fails the inspection and leaves the builder carrying the structural liability. The customer is paying for the engineer's professional indemnity insurance as much as for the calculation.

Building Control and notice

Submit the building notice or full plans application with the engineer's calculation before starting. A building notice is accepted by most authorities for domestic beam work and allows a start 48 hours after submission; a full plans application takes up to five weeks for a decision but gives approval of the design in writing. Private approved inspectors (registered building control approvers since 2024) offer the same service and are often quicker. Fees are £300–£600 depending on the authority and the declared value of the work. The inspector will want to see the beam installed, the padstones and bearings, and the beam before it is boxed in. Arrange that inspection before the plasterer is booked.

If the wall is a party wall, or the beam will bear into one, serve a Section 2 notice under the Party Wall etc. Act 1996 at least two months before starting, and do not start until the notice is consented to or an award is in place. A Section 6 notice applies if new foundations (for a post) are within 3 m of the neighbour's building and deeper than theirs. See party wall act.

Temporary support: the propping sequence

Clear both rooms. Isolate services in the wall and reroute them. Strip the plaster from both faces of the wall along the beam line and 300 mm above it, so the courses and any existing lintels can be seen.

Where the joists bear on the wall, prop the joists directly from below on both sides: a head board (150 × 50 mm or scaffold board, doubled on longer runs) under the joists about 600 mm back from the wall face, carried on props at no more than 1 m centres standing on sole boards on the floor. Check the ground floor can take the load; a suspended timber floor over a void needs its own props down to the oversite or a spreader to a sleeper wall. On a solid concrete ground floor, a single sole board is enough.

Where the wall continues above and the joists run parallel, the masonry itself needs carrying. For a few courses between the beam line and the floor above, Strongboys slotted into a raked-out bed joint at 600 mm centres, each on its own prop, will hold it; a Strongboy carries about 340 kg, so count the masonry it is holding. For a heavier wall above, or a chimney breast, pass a needle (a 150 × 150 mm timber, or a short steel section) through a hole cut above the beam line and prop it both sides. Needles at about 1 m centres along the wall, each propped both sides, is standard.

Tighten every prop to a firm bearing, plumb, with a pin through the adjustment holes. Do not over-tighten; the aim is to take the load as it comes, not to jack the house. Check the props again after the first hour of cutting, because dust and vibration loosen them.

Forming the opening

Mark the opening on the wall, including the extra width for the bearings at each end and the padstone depth. Cut the bearing pockets first, at both ends, and build the padstones in on a full mortar bed, level and at the same height each end, allowing the mortar to cure (24 hours for a precast padstone on a cement mortar bed, longer for a cast-in-situ block). Then cut the opening from the top down, course by course, removing the masonry between the pockets and keeping the top course clean to receive the beam. A wall saw or a disc cutter with water suppression on the cut lines gives a straight reveal; a hammer and bolster takes the rest.

Keep the cut above the beam line clean and level so the beam can be bedded with a dry pack and no voids. Leave the masonry below the opening in place as long as possible; it stiffens the wall while the beam goes in.

Fitting the beam

A 203 × 133 × 25 UB is about 25 kg per metre, so a 3.5 m beam is around 90 kg: two people and a lifting plan, or a Genie-type lift on longer or heavier sections. Twin beams are bolted together on the floor before lifting where access allows, with the spacer tubes between the webs. Lift the beam onto the padstones and check the bearing length each end against the engineer's figure. Pack it up to the masonry above with slate or steel shims at the bearings so the beam is in contact with the padstone across its full width, then dry-pack the gap between the top flange and the masonry above with a stiff 1:3 sand and cement mix rammed in hard, in sections, so the wall above is carried on the beam and not on the props. Leave the dry pack to cure (24 hours minimum) before easing the props.

Release props gradually, starting from the ends, and watch for movement at the bed joints above the beam; any cracking during de-propping means the dry pack has not taken the load and the props go straight back in.

Lateral restraint is provided as the engineer specifies: usually the joists bearing on the beam and either bolted to a timber plate on the top flange or sitting on hangers welded or bolted to the web. Where the joists run parallel, a bolted timber plate to the top flange and noggins to the first joist give the restraint.

Fire protection and finishing

Box the beam in with a timber or metal framework and one layer of 12.5 mm fire-rated plasterboard (two layers of 12.5 mm or one of 15 mm for 60 minutes), joints staggered and all edges supported; or apply intumescent paint to the specified loaded thickness, with the manufacturer's certificate for 30 or 60 minutes. Skim and decorate. A beam flush with the ceiling is usually hidden by letting the joists into it on hangers; a beam below the ceiling becomes a downstand that is boxed and skimmed.

Make good the reveals, extend the skirting and the floor, and leave the customer with the engineer's calculation, the Building Control completion certificate (issued after the final inspection) and the intumescent paint certificate if used. Expect hairline cracking at the beam-to-wall junction over the first heating season; a flexible filler and a repaint after 12 months is normal and should be in the quote wording.

Frequently Asked Questions

Can a builder do the calculation instead of an engineer?

No. The Building Regulations do not require a particular profession, but Building Control will expect calculations prepared by someone competent, and that means a chartered or incorporated structural engineer carrying professional indemnity insurance. A builder who sizes a beam from a merchant's table takes on the liability if it fails. The engineer's fee is the cheapest part of the job and it is the part that protects the builder.

Do I need Building Regulations approval for an internal wall?

Yes, where the wall is load-bearing. Removing or altering a load-bearing wall is building work under the Building Regulations 2010 because it affects the structure. Removing a non-load-bearing partition is not usually controlled work, but if it affects fire separation (a protected stairway in a three-storey house, for example) or means of escape it is. The completion certificate is what the customer's solicitor will ask for on sale.

How long does the job take?

A straightforward single beam between two rooms is two to three days for a two-person team: day one to strip, prop, cut the pockets and build the padstones; day two to form the opening, fit the beam and dry pack; day three to de-prop, box in and clear. Plastering and decorating follow. A goalpost frame, a beam into a cavity wall or a chimney breast adds one to three days. Lead time for the steel is usually three to seven days from the fabricator once the calculation is in hand.

What happens if the walls above crack while the props are in?

Stop and check the propping. Cracking at the bed joints above the opening during cutting means the masonry is moving, so either the props are not taking the load (loose, off plumb, on a soft floor) or the Strongboys are overloaded. Put more props in, re-tighten, and only continue once the movement has stopped. Minor hairline cracking in plaster on the floor above is common and cosmetic; a stepped crack in the brickwork is not.

Can the beam be hidden in the ceiling?

Often, by letting the floor joists into the web on joist hangers so the top of the beam sits level with the top of the joists. The engineer must design for it, because a beam sized to sit under the joists and one sized to sit between them carry load differently, and the hangers must be rated for the joist reaction. It usually adds £400–£800 to the job for the hangers, the extra cutting and the loss of the simplest bearing, and leaves a flush ceiling with no downstand.