Summary
The kitchen-diner knock-through is the most common structural job in UK domestic building and the one that most often goes wrong, because it looks simple. Two rooms become one, a steel goes in, the plasterer makes it disappear. What the customer does not see is that for the hour between the wall being cut and the beam being pinned up, the first floor, the roof and sometimes the chimney are sitting on acrow props and a few scaffold boards. That hour is where the job's risk lives.
This guide covers identifying whether a wall is load-bearing, what the engineer provides and why the builder must not substitute for them, the Building Control route, the propping sequence, forming the opening, bearings and padstones, fitting and fixing the beam, fire protection, and the finishing details that stop cracking afterwards. It assumes a conventional masonry house with timber floors; timber-frame, concrete-floor and steel-frame construction change the propping method and need the engineer's input on temporary works as well as permanent.
The two misconceptions that cause most trouble: first, that a wall running parallel to the joists cannot be load-bearing (it can carry a roof purlin strut, a chimney breast or a wall above); second, that "the engineer's calcs say a 203 × 133 UB so that is all I need to know". The calculation sheet also specifies the padstone size and grade, the bearing length, the bolting of twin beams, the lateral restraint and often the propping requirement. Every item on it is part of the design.
Key Facts
- Load-bearing indicators — the wall is on the ground floor and continues on the floor above; joists bear on it (they run at right angles to it); it carries a purlin strut or binder in the loft; it has a chimney breast; it is the spine wall of a two-up two-down or a terrace. Treat every wall as load-bearing until the engineer or a lifted floorboard proves otherwise.
- Structural engineer — required for any beam over an opening wider than about 1.2 m and for every knock-through. Fee £400–£900 for a single-beam domestic calculation, £900–£1,500 for a goalpost frame. Calculations to BS EN 1993-1-1 (steel) and BS EN 1996-1-1 (masonry bearing).
- Building Control — a building notice is accepted for this work by most local authorities; a full plans application takes longer but gives written approval of the design. Fees £300–£600 depending on authority and works value. Inspection is needed with the beam in and visible before it is boxed in.
- Beam grade — S275 or S355 structural steel to BS EN 10025; the engineer will state which. Universal Beams (UB) are the norm; Universal Columns (UC) where depth is restricted.
- Typical sizes — a 3 m opening in a two-storey house carrying one floor and a wall above commonly lands on a 203 × 133 × 25 or 203 × 133 × 30 UB; a 4 m opening carrying floor, wall and roof moves up to 254 × 146 or twin beams. These are illustrations only; the calculation governs.
- Bearing length — commonly 150 mm minimum each end on a padstone, more where the engineer calculates higher bearing stress. Never reduce it on site.
- Padstones — precast concrete C35/45 or a cast-in-situ block, or engineering bricks class B in a 1:3 mortar, sized by the engineer; typical 440 × 215 × 140 mm or 440 × 100 × 215 mm. The padstone spreads the beam reaction into the masonry below it.
- Twin beams — bolted together through the webs with M16 or M20 bolts and spacer tubes at centres given by the engineer (usually 600 mm), so they share the load and act as one.
- Props — Size 1 to Size 3 adjustable steel props (acrows), rated by extension: a Size 1 prop at full extension carries far less than at minimum extension. Props at no more than 1 m centres each side of the wall, on sole boards, plumb, with a continuous head board or Strongboy attachments.
- Strongboys — a Strongboy head holds up to about 340 kg each; it supports a few courses of masonry on one side, not a floor. Where the floor joists bear on the wall, the joists must be propped directly from below, both sides.
- Needles — for heavy loads (a chimney breast, a long wall above) a timber or steel needle through the wall above the beam line, propped both sides, carries the masonry while the opening is formed.
- Fire protection — Approved Document B Volume 1 requires 30 minutes for the floor and its supporting structure in a two-storey house, 60 minutes for a three-storey; achieved with one layer of 12.5 mm fire-rated plasterboard with joints staggered, or 15 mm board, or intumescent paint to the loaded thickness.
- Lateral restraint — the beam top flange must be restrained against buckling; joists bearing on it or a bolted timber plate usually provide it, but the engineer states the method.
- Cavity walls — an opening in an external cavity wall needs a cavity tray and weep holes over a lintel; an internal spine wall does not.
- Party walls — a beam bearing into a party wall, or cutting into one, is notifiable work under Section 2 of the Party Wall etc. Act 1996; two months' notice.
- Services — isolate and reroute gas, electrics and water in the wall before propping; a gas pipe in a wall being demolished needs a Gas Safe registered engineer to cap it.
- Skip and dust — a 3 m × 2.4 m single-skin brick wall is roughly 1.5 tonnes of rubble; a 100 mm block wall about 0.8 tonnes.
Quick Reference Table
Spending too long on quotes? squote turns a 2-minute voice recording into a professional quote.
Try squote free →| Item | Typical specification | Who decides |
|---|---|---|
| Beam section (3 m, one floor plus wall) | 203 × 133 UB, S275 | Structural engineer |
| Beam section (4 m, floor plus wall plus roof) | 254 × 146 UB or twin 203 × 133 | Structural engineer |
| Bearing length each end | 150 mm minimum | Structural engineer |
| Padstone | 440 × 215 × 140 mm C35/45 precast or class B engineering brick | Structural engineer |
| Twin beam bolting | M16 or M20 at 600 mm centres with spacer tubes | Structural engineer |
| Prop spacing | 1 m maximum centres, both sides | Builder (temporary works) |
| Strongboy capacity | About 340 kg per head | Manufacturer rating |
| Fire protection, two storeys | 30 minutes: 12.5 mm fire-rated plasterboard or intumescent paint | Approved Document B Vol 1 |
| Fire protection, three storeys | 60 minutes: two layers of board or heavier intumescent build | Approved Document B Vol 1 |
| Building Control fee | £300–£600 | Local authority or approved inspector |
| Engineer's fee | £400–£900 single beam | Market (2026) |
| Total job, regional England | £2,800–£5,500 single beam | Market (2026) |
| Total job, London | £4,000–£8,000 single beam | Market (2026) |
Detailed Guidance
Is it load-bearing?
Start in the loft and work down. A wall that carries a purlin strut, a binder or a ceiling joist splice is load-bearing from the roof. On the first floor, lift a board next to the wall: joists sitting on the wall plate, or lapped over it, mean the wall carries that floor. A wall that continues directly above the one being removed is load-bearing by definition, because it is carrying its own weight plus whatever it carries. A chimney breast in the wall makes it load-bearing and makes the job larger, because the breast cannot be left hanging without a gallows bracket or beam designed for it; see chimney breast removal pricing guide.
Walls that are often wrongly assumed to be non-load-bearing: the ground-floor wall between the front and back reception rooms in a Victorian terrace (it carries the first-floor joists and the wall above, and often a purlin strut); the kitchen-to-dining wall in a 1930s semi (it carries the first-floor bathroom wall); a 100 mm blockwork wall in a 1970s house that was built as a loadbearing partition. Walls that are usually not load-bearing: stud partitions running parallel to joists with nothing above; blockwork walls where the joists run parallel and the wall above is offset; walls added after the house was built. Even then, confirm by inspection, and treat it as load-bearing if there is any doubt.
The engineer's design and what it contains
The structural engineer visits (or works from a survey and photographs on simple jobs), identifies the loads from the floor, walls and roof, and produces a calculation sheet and usually a sketch. The sheet specifies the beam section and grade, the span, the bearing length at each end, the padstone size and material, any bolting of twin beams, the end plates or bearing plates if the beam sits on a column or a steel post, the lateral restraint, and the fire protection. Some engineers also specify the temporary works (propping); where they do not, the builder designs the propping and should ask the engineer to confirm it for anything above a straightforward two-storey house.
Do not change anything on the sheet without the engineer's written agreement. Building Control inspects against the calculation; a beam one size smaller because the merchant had it in stock, or a padstone replaced with a few bricks because the course height was awkward, fails the inspection and leaves the builder carrying the structural liability. The customer is paying for the engineer's professional indemnity insurance as much as for the calculation.
Building Control and notice
Submit the building notice or full plans application with the engineer's calculation before starting. A building notice is accepted by most authorities for domestic beam work and allows a start 48 hours after submission; a full plans application takes up to five weeks for a decision but gives approval of the design in writing. Private approved inspectors (registered building control approvers since 2024) offer the same service and are often quicker. Fees are £300–£600 depending on the authority and the declared value of the work. The inspector will want to see the beam installed, the padstones and bearings, and the beam before it is boxed in. Arrange that inspection before the plasterer is booked.
If the wall is a party wall, or the beam will bear into one, serve a Section 2 notice under the Party Wall etc. Act 1996 at least two months before starting, and do not start until the notice is consented to or an award is in place. A Section 6 notice applies if new foundations (for a post) are within 3 m of the neighbour's building and deeper than theirs. See party wall act.
Temporary support: the propping sequence
Clear both rooms. Isolate services in the wall and reroute them. Strip the plaster from both faces of the wall along the beam line and 300 mm above it, so the courses and any existing lintels can be seen.
Where the joists bear on the wall, prop the joists directly from below on both sides: a head board (150 × 50 mm or scaffold board, doubled on longer runs) under the joists about 600 mm back from the wall face, carried on props at no more than 1 m centres standing on sole boards on the floor. Check the ground floor can take the load; a suspended timber floor over a void needs its own props down to the oversite or a spreader to a sleeper wall. On a solid concrete ground floor, a single sole board is enough.
Where the wall continues above and the joists run parallel, the masonry itself needs carrying. For a few courses between the beam line and the floor above, Strongboys slotted into a raked-out bed joint at 600 mm centres, each on its own prop, will hold it; a Strongboy carries about 340 kg, so count the masonry it is holding. For a heavier wall above, or a chimney breast, pass a needle (a 150 × 150 mm timber, or a short steel section) through a hole cut above the beam line and prop it both sides. Needles at about 1 m centres along the wall, each propped both sides, is standard.
Tighten every prop to a firm bearing, plumb, with a pin through the adjustment holes. Do not over-tighten; the aim is to take the load as it comes, not to jack the house. Check the props again after the first hour of cutting, because dust and vibration loosen them.
Forming the opening
Mark the opening on the wall, including the extra width for the bearings at each end and the padstone depth. Cut the bearing pockets first, at both ends, and build the padstones in on a full mortar bed, level and at the same height each end, allowing the mortar to cure (24 hours for a precast padstone on a cement mortar bed, longer for a cast-in-situ block). Then cut the opening from the top down, course by course, removing the masonry between the pockets and keeping the top course clean to receive the beam. A wall saw or a disc cutter with water suppression on the cut lines gives a straight reveal; a hammer and bolster takes the rest.
Keep the cut above the beam line clean and level so the beam can be bedded with a dry pack and no voids. Leave the masonry below the opening in place as long as possible; it stiffens the wall while the beam goes in.
Fitting the beam
A 203 × 133 × 25 UB is about 25 kg per metre, so a 3.5 m beam is around 90 kg: two people and a lifting plan, or a Genie-type lift on longer or heavier sections. Twin beams are bolted together on the floor before lifting where access allows, with the spacer tubes between the webs. Lift the beam onto the padstones and check the bearing length each end against the engineer's figure. Pack it up to the masonry above with slate or steel shims at the bearings so the beam is in contact with the padstone across its full width, then dry-pack the gap between the top flange and the masonry above with a stiff 1:3 sand and cement mix rammed in hard, in sections, so the wall above is carried on the beam and not on the props. Leave the dry pack to cure (24 hours minimum) before easing the props.
Release props gradually, starting from the ends, and watch for movement at the bed joints above the beam; any cracking during de-propping means the dry pack has not taken the load and the props go straight back in.
Lateral restraint is provided as the engineer specifies: usually the joists bearing on the beam and either bolted to a timber plate on the top flange or sitting on hangers welded or bolted to the web. Where the joists run parallel, a bolted timber plate to the top flange and noggins to the first joist give the restraint.
Fire protection and finishing
Box the beam in with a timber or metal framework and one layer of 12.5 mm fire-rated plasterboard (two layers of 12.5 mm or one of 15 mm for 60 minutes), joints staggered and all edges supported; or apply intumescent paint to the specified loaded thickness, with the manufacturer's certificate for 30 or 60 minutes. Skim and decorate. A beam flush with the ceiling is usually hidden by letting the joists into it on hangers; a beam below the ceiling becomes a downstand that is boxed and skimmed.
Make good the reveals, extend the skirting and the floor, and leave the customer with the engineer's calculation, the Building Control completion certificate (issued after the final inspection) and the intumescent paint certificate if used. Expect hairline cracking at the beam-to-wall junction over the first heating season; a flexible filler and a repaint after 12 months is normal and should be in the quote wording.
Frequently Asked Questions
Can a builder do the calculation instead of an engineer?
No. The Building Regulations do not require a particular profession, but Building Control will expect calculations prepared by someone competent, and that means a chartered or incorporated structural engineer carrying professional indemnity insurance. A builder who sizes a beam from a merchant's table takes on the liability if it fails. The engineer's fee is the cheapest part of the job and it is the part that protects the builder.
Do I need Building Regulations approval for an internal wall?
Yes, where the wall is load-bearing. Removing or altering a load-bearing wall is building work under the Building Regulations 2010 because it affects the structure. Removing a non-load-bearing partition is not usually controlled work, but if it affects fire separation (a protected stairway in a three-storey house, for example) or means of escape it is. The completion certificate is what the customer's solicitor will ask for on sale.
How long does the job take?
A straightforward single beam between two rooms is two to three days for a two-person team: day one to strip, prop, cut the pockets and build the padstones; day two to form the opening, fit the beam and dry pack; day three to de-prop, box in and clear. Plastering and decorating follow. A goalpost frame, a beam into a cavity wall or a chimney breast adds one to three days. Lead time for the steel is usually three to seven days from the fabricator once the calculation is in hand.
What happens if the walls above crack while the props are in?
Stop and check the propping. Cracking at the bed joints above the opening during cutting means the masonry is moving, so either the props are not taking the load (loose, off plumb, on a soft floor) or the Strongboys are overloaded. Put more props in, re-tighten, and only continue once the movement has stopped. Minor hairline cracking in plaster on the floor above is common and cosmetic; a stepped crack in the brickwork is not.
Can the beam be hidden in the ceiling?
Often, by letting the floor joists into the web on joist hangers so the top of the beam sits level with the top of the joists. The engineer must design for it, because a beam sized to sit under the joists and one sized to sit between them carry load differently, and the hangers must be rated for the joist reaction. It usually adds £400–£800 to the job for the hangers, the extra cutting and the loss of the simplest bearing, and leaves a flush ceiling with no downstand.
Regulations & Standards
Building Regulations 2010 — structural alterations are building work; notification required
Approved Document A: Structure — structural safety of alterations; basis for Building Control inspection
Approved Document B Volume 1: Dwellings — fire resistance of floors and their supporting structure (30 minutes two-storey, 60 minutes three-storey)
BS EN 1993-1-1 (Eurocode 3) — design of steel structures; beam calculation
BS EN 1996-1-1 (Eurocode 6) — design of masonry structures; bearing stress under padstones
BS EN 1991-1-1 (Eurocode 1) — actions on structures; floor and roof loading
BS EN 10025 — hot rolled products of structural steels; S275 and S355 grades
BS 5975:2019 — Code of practice for temporary works procedures and the permissible stress design of falsework (propping and needling)
Party Wall etc. Act 1996 — Section 2 notice for work to a party wall; Section 6 for adjacent excavation
CDM Regulations 2015 — domestic client duties pass to the contractor; a method statement for the propping and cutting is expected
Gas Safety (Installation and Use) Regulations 1998 — gas pipes in the wall must be capped by a Gas Safe registered engineer
Approved Document A: Structure — Building Regulations structural requirements
Approved Document B, Volume 1: Dwellings — fire resistance periods for structural elements
Planning Portal — internal walls and Building Regulations — when approval is required for removing walls
HSE — structural stability during alterations and demolition — temporary works and propping guidance
Institution of Structural Engineers — finding an engineer — register of chartered structural engineers
LABC — removing a load-bearing wall — local authority building control guidance for homeowners and builders
steel beam installation — the permanent works in more detail: padstones, bolting and fire protection
steel beam installation pricing guide — pricing the beam, the engineer and Building Control
structural engineer pricing guide — what the calculation costs and what it includes
building control — building notice versus full plans and the inspection sequence
party wall act — notices where the wall or bearing is shared with a neighbour
chimney breast removal pricing guide — where the wall contains a chimney breast