Summary
A shop fit-out is the job that turns a sole-trader builder into a contractor. The client is a business with a lease that starts the rent on a fixed date, a landlord with a licence to alter, a bank loan, and a shop-opening date on a poster. The programme is short (two to eight weeks), the trades are many (strip-out, shopfront, electrics, plumbing, mechanical, joinery, flooring, decoration, signage), and the regulatory paperwork is unlike a house extension. The builder who prices it as a big decorating job and the builder who prices it as a project with prelims, a programme and a contingency are quoting the same work at different numbers, and only one of them makes money.
This guide prices the fit-out by square metre band and by trade package, explains the preliminaries that a commercial job carries, lists the compliance items that must be priced and the consents that must be obtained before the first wall comes down, and shows a worked example for a 60 m² coffee shop. For the general differences of commercial work see commercial jobs; for the partitioning that most fit-outs involve see metal stud partition installation.
The pricing misconception is that a shop is a house with no bedrooms. It is a non-domestic premises under Approved Document B Volume 2, Approved Document M Volume 2 and Approved Document L Volume 2, under the Fire Safety Order, under the Equality Act 2010, and under a commercial lease that makes the tenant responsible for the landlord's building; every one of those adds a line to the price.
Key Facts
- Per m² bands — basic £350–£700; mid-range £700–£1,400; high-specification £1,400–£2,800; restaurant and café kitchens push the top of each band because of the mechanical extract, grease management and drainage.
- Typical unit — a high-street shop of 40–120 m² sales area plus 10–40 m² back of house; a 60 m² unit at mid-range is £42,000–£84,000.
- Shopfront — a new aluminium framed glazed shopfront with a door at £8,000–£20,000 for a 5 m frontage; a timber shopfront in a conservation area £15,000–£35,000; a roller shutter £2,500–£6,000.
- Signage — fascia sign £1,500–£6,000 (illuminated at the top); a projecting sign £400–£1,200; planning consent for an illuminated sign under the Town and Country Planning (Control of Advertisements) (England) Regulations 2007.
- Electrical — a new distribution board, 40–80 lighting and power points, a lighting scheme to 500–750 lux for retail sales areas (CIBSE guidance) and an Electrical Installation Certificate to BS 7671:2018+A2:2022: £8,000–£20,000 for a 60 m² unit.
- Fire alarm — BS 5839-1:2017 category L2 or L3 for most shops with a staff area, M (manual) for the smallest; £1,500–£4,500 installed with a commissioning certificate.
- Emergency lighting — BS 5266-1:2016; £60–£140 per luminaire, 6–15 per unit, plus the certificate.
- Fire risk assessment — required under the Regulatory Reform (Fire Safety) Order 2005 before the shop opens; £200–£500 for a small unit (see fire risk assessment pricing guide).
- Accessible WC — Approved Document M Volume 2 and BS 8300-2:2018; a unisex accessible WC with the 1,500 × 2,200 mm minimum room, grab rails, a drop-down rail, an outward-opening door and an alarm: £4,000–£9,000.
- Level access and the door — a level threshold or a ramp at 1:12 maximum (1:15 preferred), an 800 mm minimum clear door width (1,000 mm preferred), and the door entrance to Approved Document M; the Equality Act 2010 duty to make reasonable adjustments sits with the business.
- Ventilation — Approved Document F Volume 2; a café or food unit needs a kitchen extract canopy with grease filters and a duct to a safe discharge, which is the single item most likely to need planning consent for the external duct and most likely to blow the budget: £6,000–£25,000.
- Floor — commercial vinyl or LVT at £35–£70 per m² laid; polished concrete or resin £60–£120 per m²; the sub-floor condition is the unknown.
- Partitions and ceilings — metal stud partitions at £60–£120 per m² boarded and skimmed; a suspended ceiling at £35–£65 per m²; a plasterboard ceiling at £45–£80 per m².
- Joinery — a sales counter from £1,500 for a basic MDF and laminate unit to £8,000 or more for a bespoke piece; wall display £150–£500 per metre.
- Decoration — £10–£18 per m² of wall and ceiling area for a two-coat emulsion on new plaster; feature finishes extra.
- Plumbing — a sink, a staff WC and a water heater at £2,000–£5,000; a café with a three-sink kitchen, a dishwasher and a grease trap at £5,000–£12,000.
- Building Regulations — a full plans application or a building notice for a change of use, structural alterations, the accessible WC, the fire precautions and the services; £500–£2,000 in fees. A change of use between use classes (the 2020 Use Classes Order put shops, cafés and offices together in Class E) may need no planning consent but still needs Building Regulations for the material change.
- Planning — needed for a new shopfront, external alterations, the extract duct, and all signage above a size or any illuminated signage; £300–£600 in fees plus drawings; 8 weeks.
- Licence to alter — the landlord's written consent under the lease to any alteration; the landlord's surveyor's fees (£500–£2,000) are usually paid by the tenant.
- CDM 2015 — the client is a commercial client; with more than one contractor the client must appoint a principal designer and a principal contractor in writing; a construction phase plan is required for every project; F10 notification to HSE where the project exceeds 30 working days with more than 20 workers at any one time, or 500 person-days.
- Asbestos — a refurbishment and demolition survey under the Control of Asbestos Regulations 2012 before strip-out of any building built before 2000; £300–£800.
- Prelims — 8–15% of the trade total for the site set-up, welfare, skips, hoarding, scaffold, temporary works, programme management and the contract administration.
- Contingency — 5–10% on a refurbishment of an existing unit; what is behind the old shopfront and under the old floor is not known until it is stripped.
- Overhead and profit — 15–25% on direct cost for a main contractor carrying the subcontractors; the lower figure on larger, cleaner jobs.
- Payment — stage payments against a programme or a JCT Minor Works contract with interim valuations; a retention of 3–5% released at practical completion and at the end of the defects period; the Construction Act 1996 (as amended 2009) gives the right to stage payments and adjudication on any construction contract that is not with a residential occupier.
- VAT — standard 20%; the client reclaims it if VAT registered, which is why commercial quotes are shown net.
Quick Reference Table
Spending too long on quotes? squote turns a 2-minute voice recording into a professional quote.
Try squote free →| Package | Basic (60 m²) | Mid-range (60 m²) | High-spec (60 m²) |
|---|---|---|---|
| Strip-out and skips | £1,500–£3,000 | £2,500–£5,000 | £3,000–£6,000 |
| Shopfront and door | Existing retained, £500–£2,000 repairs | £8,000–£15,000 | £15,000–£35,000 |
| Signage | £1,000–£2,500 | £2,500–£6,000 | £5,000–£12,000 |
| Partitions, ceilings and plastering | £3,000–£6,000 | £6,000–£12,000 | £10,000–£20,000 |
| Electrical and lighting | £5,000–£9,000 | £9,000–£18,000 | £18,000–£35,000 |
| Fire alarm and emergency lighting | £2,000–£4,000 | £3,000–£6,000 | £4,000–£8,000 |
| Plumbing and WCs | £2,000–£4,000 | £5,000–£12,000 | £10,000–£20,000 |
| Mechanical ventilation and heating | £1,500–£4,000 | £6,000–£15,000 | £15,000–£35,000 |
| Flooring | £2,000–£4,000 | £3,500–£7,000 | £6,000–£12,000 |
| Joinery and counters | £1,500–£4,000 | £5,000–£12,000 | £12,000–£30,000 |
| Decoration | £1,500–£3,000 | £2,500–£5,000 | £4,000–£8,000 |
| Fees (Building Regs, planning, FRA, surveys) | £1,500–£3,000 | £2,500–£5,000 | £4,000–£8,000 |
| Prelims (8–15%) | £2,000–£5,000 | £5,000–£12,000 | £10,000–£25,000 |
| Contingency (5–10%) | £1,500–£3,500 | £3,000–£8,000 | £6,000–£15,000 |
| Total before OH&P | £26,000–£55,000 | £64,000–£138,000 | £122,000–£269,000 |
| Per m² (including OH&P at 15–25%) | £500–£1,100 | £1,200–£2,900 | £2,300–£5,600 |
The per-m² figures in the bottom row include the shopfront, fees and prelims; the headline bands in the Quick Answer exclude a new shopfront and fees, which is how most fit-out contractors quote the "fit-out" and why a client's per-m² expectation is lower than the bottom row.
Detailed Guidance
Scope: what the lease and the client's budget actually include
Before pricing, establish what the unit is being handed over as. A landlord's "shell" is bare walls, a concrete floor, capped services and no shopfront; a "Category A" or "white box" is plastered walls, a ceiling, lighting, a distribution board and a WC; a previous tenant's fit-out left in place is a strip-out job before anything else. The same client budget buys a very different shop from each, and the quote must say which it assumes.
Then establish what the client is supplying. Retail clients often buy their own display fixtures, counters, signage and coffee machines; the fit-out has to provide the services, the structure and the finishes for them, and the quote has to list every item the client supplies and every connection the builder makes. A coffee machine with a 32 A supply and a 15 mm water feed with a filter, a dishwasher with a drain and a grease trap, an extract canopy supplied by a kitchen company but installed by the fit-out contractor: each is a line with an owner.
Consents and compliance: the items that stop the job
Price and programme these before the strip-out:
- Landlord's licence to alter: the lease will require written consent for structural alterations, the shopfront, services penetrations and signage; the landlord's surveyor reviews the drawings and the tenant pays the fee. Allow four to eight weeks.
- Planning: a new shopfront, external changes, the extract duct and the signage; eight weeks from a valid application. Advertisement consent is a separate application for illuminated or large signs.
- Building Regulations: a change of use, structural work, the accessible WC, fire precautions (compartmentation, escape, alarm, emergency lighting), the electrics and the mechanical ventilation. Use a full plans application for anything beyond a simple refit so the fire strategy is approved before the partitions go up; a registered building control approver is often quicker than the local authority for commercial work.
- Asbestos: a refurbishment and demolition survey before strip-out in any pre-2000 building; a licensed removal if it finds anything licensed.
- CDM 2015: appoint the principal designer and principal contractor in writing where there is more than one contractor (there always is), prepare the construction phase plan, and notify HSE on an F10 where the thresholds are met; a six-week fit-out with a dozen trades passes the 500 person-day threshold easily.
- Fire risk assessment: the client's duty before opening; most fit-out contractors arrange it and charge it.
- Electrical certification: an Electrical Installation Certificate for the new installation and an EICR for any retained part; the insurer and the landlord will ask.
- Food premises registration: a café registers with the local authority 28 days before opening; the kitchen layout has to satisfy the environmental health officer, who will look at the hand-wash basin, the surfaces, the extract and the grease trap.
Building the price: packages, prelims, contingency, margin
Price each trade package as a measured item: strip-out by the skip and the day; partitions and ceilings by the m²; electrics by the point and the fitting with the board, the alarm and the emergency lighting as lump sums; plumbing by the fitting; mechanical by the system; flooring by the m²; joinery by the item; decoration by the m². Get subcontract quotes for the shopfront, the alarm, the mechanical and the joinery; do not estimate them.
Add prelims at 8–15% of the trade total: welfare (a site toilet and a mess area are legal requirements under CDM 2015 Schedule 2, even on a shop), hoarding to the shopfront, scaffold or a tower for the fascia, skips, temporary power and lighting, the site manager's or the contractor's own time managing the trades, the programme, the health and safety file and the contract administration. On a short fit-out the prelims are a large share because the fixed costs do not shrink with the programme.
Add a contingency at 5–10% for the unknowns: the floor that is not level, the drain that does not connect, the wall that turns out to carry the floor above, the landlord's surveyor's late request. State on the quote that the contingency is held and only spent with the client's agreement; it builds trust and the unspent part is credited.
Add overhead and profit at 15–25% on the direct cost. A main contractor on a fit-out carries the subcontractors' payment risk, the programme risk and the defects liability; 15% is thin on a small job.
Programme and the price of being late
A fit-out has a hard end date because the rent-free period ends and the opening is advertised. Price the programme as part of the quote: a realistic number of weeks, the long-lead items (the shopfront at 4–8 weeks from survey, the extract canopy at 3–6 weeks, bespoke joinery at 4–8 weeks, the signage at 3–4 weeks after consent), and the dependencies (the alarm cannot be commissioned until the ceilings are in; the floor cannot be laid until the plumbing is tested). A client who wants a six-week job in four weeks pays for the overtime and the weekend working; put it in as an option, not as an assumption.
Liquidated damages for late completion are common in commercial contracts and should be resisted or capped on a job where the long-lead items are outside the builder's control. Use a standard form (JCT Minor Works Building Contract for most shop fit-outs) rather than the client's bespoke terms.
Worked example: a 60 m² coffee shop, mid-range
Existing shop unit, Category A, with a retained shopfront that needs a new door, a back-of-house of 15 m², a rear yard for the extract discharge, pre-2000 building.
- Strip-out, asbestos survey and skips: £4,200.
- Shopfront door and glazing repairs: £3,500. Signage, fascia and projecting, illuminated: £4,800 (plus the advertisement consent).
- Partitions to form the kitchen, the accessible WC and a store; plasterboard ceiling to the sales area, suspended ceiling to the kitchen; skim and tape: £9,500.
- Electrical: new 3-phase distribution, 60 points, 24 track spots and feature pendants, kitchen power including a 32 A supply for the coffee machine, data points, Electrical Installation Certificate: £14,500.
- Fire alarm (L2) and emergency lighting, commissioned and certificated: £4,600.
- Plumbing: accessible WC to Approved Document M with a Doc M pack, staff WC, kitchen with hand-wash basin, double sink, dishwasher, grease trap, water heater and the coffee machine feed with filter: £9,800.
- Mechanical: kitchen extract canopy with grease filters, ducted to the rear yard with a fan and silencer, make-up air, plus heating and cooling by a split air-conditioning system: £13,500.
- Flooring: LVT to the sales area, safety vinyl to the kitchen and WCs, with the sub-floor levelled: £5,400.
- Joinery: serving counter with a back bar, a condiment station and a bench seat: £9,200.
- Decoration: £3,200.
- Fees: Building Regulations full plans, planning and advertisement consent, fire risk assessment, landlord's surveyor: £4,300.
- Trade total: £86,500. Prelims at 10%: £8,650. Contingency at 7%: £6,050. Direct cost: £101,200. Overhead and profit at 18%: £18,200. Price: £119,400 net of VAT, about £1,990 per m² including the fees and the mechanical package, or £1,500 per m² on the fit-out trades alone. Programme seven weeks from strip-out, with the shopfront door and the canopy on order before the start.
Frequently Asked Questions
Does a shop fit-out need Building Regulations approval?
Almost always. A change of use (even within Class E, where planning consent may not be needed) is a material change of use under the Building Regulations 2010 where the building becomes a shop or a café from something else; structural alterations, the new WC, the fire precautions, the electrics in a non-domestic building and the mechanical ventilation are all controlled work. A full plans application is the right route so that the fire strategy, the means of escape and the accessible WC are approved on paper before they are built. Only a like-for-like refit with no change to the layout, the services or the fire precautions avoids it, and even then the electrical work needs certification.
Who is the CDM client and what does it mean for the price?
The business commissioning the fit-out is a commercial client under CDM 2015 and carries the client duties: appointing the principal designer and principal contractor in writing, allowing adequate time and resources, and making sure the construction phase plan exists before work starts. In practice the client has never heard of CDM and the contractor takes the principal contractor role and often arranges the principal designer (an architect or a designer on the project). The price includes the construction phase plan, the welfare facilities, the site induction and the health and safety file, and the F10 notification where the thresholds are met; it is a few hundred pounds of time on a small job and part of the prelims.
How long does a shop fit-out take?
A basic refit of an existing unit is two to four weeks on site; a mid-range fit-out with a new shopfront and a kitchen is five to eight weeks on site plus the four to eight weeks of consents and lead times before it; a high-specification fit-out is eight to fourteen weeks on site. The consents are the usual delay: a client who signs the lease and expects to open in six weeks has usually not allowed for planning on the shopfront or the landlord's licence to alter.
What margin should a builder put on a fit-out?
Overhead and profit of 15–25% on direct cost, on top of prelims of 8–15% and a contingency of 5–10%. The prelims and the contingency are costs, not margin; a builder who takes 15% on a fit-out with no prelims line is working for less than a day rate. The margin reflects the risks the main contractor carries: paying subcontractors before the client pays, the programme, the defects liability, and the retention held for six or twelve months after completion.
Regulations & Standards
Building Regulations 2010 — material change of use, structural alterations, fire precautions, services
Approved Document B Volume 2: Buildings other than dwellings — means of escape, compartmentation, fire alarm and emergency lighting in non-domestic premises
Approved Document M Volume 2: Buildings other than dwellings — access, entrances, accessible WCs
Approved Document L Volume 2: Buildings other than dwellings — lighting efficacy, heating and cooling controls, fabric standards
Approved Document F Volume 2: Buildings other than dwellings — ventilation of non-domestic premises and kitchen extract
BS 8300-2:2018 — Design of an accessible and inclusive built environment. Buildings
BS 5839-1:2017 — Fire detection and fire alarm systems for buildings. Non-domestic premises
BS 5266-1:2016 — Emergency lighting. Code of practice
BS 7671:2018+A2:2022 — Requirements for Electrical Installations; Electrical Installation Certificate
BS 9999:2017 — Fire safety in the design, management and use of buildings
Regulatory Reform (Fire Safety) Order 2005 — fire risk assessment before occupation
Equality Act 2010 — reasonable adjustments for disabled customers and staff
Town and Country Planning (Use Classes) (Amendment) (England) Regulations 2020 — Class E commercial, business and service use
Town and Country Planning (Control of Advertisements) (England) Regulations 2007 — advertisement consent for signage
CDM Regulations 2015 — client, principal designer and principal contractor duties; F10 notification; welfare
Control of Asbestos Regulations 2012 — refurbishment and demolition survey before strip-out
Housing Grants, Construction and Regeneration Act 1996 (as amended 2009) — payment terms and adjudication on commercial construction contracts
Food Safety and Hygiene (England) Regulations 2013 — food premises registration and kitchen requirements
Approved Document B, Volume 2: Buildings other than dwellings — fire safety in non-domestic premises
Approved Document M, Volume 2: Buildings other than dwellings — accessible entrances and WCs
Planning Portal — change of use and shopfronts — when planning and advertisement consent are needed
HSE — CDM 2015 for commercial clients — client, principal designer and principal contractor duties and F10
Fire safety risk assessment: offices and shops — GOV.UK — sector guide for the fire risk assessment
Food Standards Agency — register a food business — registration 28 days before opening
commercial jobs — how commercial work differs from domestic in regulation and contract
metal stud partition installation — partitions that form the kitchen, WC and store
fire risk assessment pricing guide — the assessment required before opening
utility room fit out pricing guide — a smaller fit-out priced by the same method