Summary

A shop fit-out is the job that turns a sole-trader builder into a contractor. The client is a business with a lease that starts the rent on a fixed date, a landlord with a licence to alter, a bank loan, and a shop-opening date on a poster. The programme is short (two to eight weeks), the trades are many (strip-out, shopfront, electrics, plumbing, mechanical, joinery, flooring, decoration, signage), and the regulatory paperwork is unlike a house extension. The builder who prices it as a big decorating job and the builder who prices it as a project with prelims, a programme and a contingency are quoting the same work at different numbers, and only one of them makes money.

This guide prices the fit-out by square metre band and by trade package, explains the preliminaries that a commercial job carries, lists the compliance items that must be priced and the consents that must be obtained before the first wall comes down, and shows a worked example for a 60 m² coffee shop. For the general differences of commercial work see commercial jobs; for the partitioning that most fit-outs involve see metal stud partition installation.

The pricing misconception is that a shop is a house with no bedrooms. It is a non-domestic premises under Approved Document B Volume 2, Approved Document M Volume 2 and Approved Document L Volume 2, under the Fire Safety Order, under the Equality Act 2010, and under a commercial lease that makes the tenant responsible for the landlord's building; every one of those adds a line to the price.

Key Facts

Quick Reference Table

Spending too long on quotes? squote turns a 2-minute voice recording into a professional quote.

Try squote free →
Package Basic (60 m²) Mid-range (60 m²) High-spec (60 m²)
Strip-out and skips £1,500–£3,000 £2,500–£5,000 £3,000–£6,000
Shopfront and door Existing retained, £500–£2,000 repairs £8,000–£15,000 £15,000–£35,000
Signage £1,000–£2,500 £2,500–£6,000 £5,000–£12,000
Partitions, ceilings and plastering £3,000–£6,000 £6,000–£12,000 £10,000–£20,000
Electrical and lighting £5,000–£9,000 £9,000–£18,000 £18,000–£35,000
Fire alarm and emergency lighting £2,000–£4,000 £3,000–£6,000 £4,000–£8,000
Plumbing and WCs £2,000–£4,000 £5,000–£12,000 £10,000–£20,000
Mechanical ventilation and heating £1,500–£4,000 £6,000–£15,000 £15,000–£35,000
Flooring £2,000–£4,000 £3,500–£7,000 £6,000–£12,000
Joinery and counters £1,500–£4,000 £5,000–£12,000 £12,000–£30,000
Decoration £1,500–£3,000 £2,500–£5,000 £4,000–£8,000
Fees (Building Regs, planning, FRA, surveys) £1,500–£3,000 £2,500–£5,000 £4,000–£8,000
Prelims (8–15%) £2,000–£5,000 £5,000–£12,000 £10,000–£25,000
Contingency (5–10%) £1,500–£3,500 £3,000–£8,000 £6,000–£15,000
Total before OH&P £26,000–£55,000 £64,000–£138,000 £122,000–£269,000
Per m² (including OH&P at 15–25%) £500–£1,100 £1,200–£2,900 £2,300–£5,600

The per-m² figures in the bottom row include the shopfront, fees and prelims; the headline bands in the Quick Answer exclude a new shopfront and fees, which is how most fit-out contractors quote the "fit-out" and why a client's per-m² expectation is lower than the bottom row.

Detailed Guidance

Scope: what the lease and the client's budget actually include

Before pricing, establish what the unit is being handed over as. A landlord's "shell" is bare walls, a concrete floor, capped services and no shopfront; a "Category A" or "white box" is plastered walls, a ceiling, lighting, a distribution board and a WC; a previous tenant's fit-out left in place is a strip-out job before anything else. The same client budget buys a very different shop from each, and the quote must say which it assumes.

Then establish what the client is supplying. Retail clients often buy their own display fixtures, counters, signage and coffee machines; the fit-out has to provide the services, the structure and the finishes for them, and the quote has to list every item the client supplies and every connection the builder makes. A coffee machine with a 32 A supply and a 15 mm water feed with a filter, a dishwasher with a drain and a grease trap, an extract canopy supplied by a kitchen company but installed by the fit-out contractor: each is a line with an owner.

Consents and compliance: the items that stop the job

Price and programme these before the strip-out:

Building the price: packages, prelims, contingency, margin

Price each trade package as a measured item: strip-out by the skip and the day; partitions and ceilings by the m²; electrics by the point and the fitting with the board, the alarm and the emergency lighting as lump sums; plumbing by the fitting; mechanical by the system; flooring by the m²; joinery by the item; decoration by the m². Get subcontract quotes for the shopfront, the alarm, the mechanical and the joinery; do not estimate them.

Add prelims at 8–15% of the trade total: welfare (a site toilet and a mess area are legal requirements under CDM 2015 Schedule 2, even on a shop), hoarding to the shopfront, scaffold or a tower for the fascia, skips, temporary power and lighting, the site manager's or the contractor's own time managing the trades, the programme, the health and safety file and the contract administration. On a short fit-out the prelims are a large share because the fixed costs do not shrink with the programme.

Add a contingency at 5–10% for the unknowns: the floor that is not level, the drain that does not connect, the wall that turns out to carry the floor above, the landlord's surveyor's late request. State on the quote that the contingency is held and only spent with the client's agreement; it builds trust and the unspent part is credited.

Add overhead and profit at 15–25% on the direct cost. A main contractor on a fit-out carries the subcontractors' payment risk, the programme risk and the defects liability; 15% is thin on a small job.

Programme and the price of being late

A fit-out has a hard end date because the rent-free period ends and the opening is advertised. Price the programme as part of the quote: a realistic number of weeks, the long-lead items (the shopfront at 4–8 weeks from survey, the extract canopy at 3–6 weeks, bespoke joinery at 4–8 weeks, the signage at 3–4 weeks after consent), and the dependencies (the alarm cannot be commissioned until the ceilings are in; the floor cannot be laid until the plumbing is tested). A client who wants a six-week job in four weeks pays for the overtime and the weekend working; put it in as an option, not as an assumption.

Liquidated damages for late completion are common in commercial contracts and should be resisted or capped on a job where the long-lead items are outside the builder's control. Use a standard form (JCT Minor Works Building Contract for most shop fit-outs) rather than the client's bespoke terms.

Worked example: a 60 m² coffee shop, mid-range

Existing shop unit, Category A, with a retained shopfront that needs a new door, a back-of-house of 15 m², a rear yard for the extract discharge, pre-2000 building.

Frequently Asked Questions

Does a shop fit-out need Building Regulations approval?

Almost always. A change of use (even within Class E, where planning consent may not be needed) is a material change of use under the Building Regulations 2010 where the building becomes a shop or a café from something else; structural alterations, the new WC, the fire precautions, the electrics in a non-domestic building and the mechanical ventilation are all controlled work. A full plans application is the right route so that the fire strategy, the means of escape and the accessible WC are approved on paper before they are built. Only a like-for-like refit with no change to the layout, the services or the fire precautions avoids it, and even then the electrical work needs certification.

Who is the CDM client and what does it mean for the price?

The business commissioning the fit-out is a commercial client under CDM 2015 and carries the client duties: appointing the principal designer and principal contractor in writing, allowing adequate time and resources, and making sure the construction phase plan exists before work starts. In practice the client has never heard of CDM and the contractor takes the principal contractor role and often arranges the principal designer (an architect or a designer on the project). The price includes the construction phase plan, the welfare facilities, the site induction and the health and safety file, and the F10 notification where the thresholds are met; it is a few hundred pounds of time on a small job and part of the prelims.

How long does a shop fit-out take?

A basic refit of an existing unit is two to four weeks on site; a mid-range fit-out with a new shopfront and a kitchen is five to eight weeks on site plus the four to eight weeks of consents and lead times before it; a high-specification fit-out is eight to fourteen weeks on site. The consents are the usual delay: a client who signs the lease and expects to open in six weeks has usually not allowed for planning on the shopfront or the landlord's licence to alter.

What margin should a builder put on a fit-out?

Overhead and profit of 15–25% on direct cost, on top of prelims of 8–15% and a contingency of 5–10%. The prelims and the contingency are costs, not margin; a builder who takes 15% on a fit-out with no prelims line is working for less than a day rate. The margin reflects the risks the main contractor carries: paying subcontractors before the client pays, the programme, the defects liability, and the retention held for six or twelve months after completion.