Summary

MVHR has gone from a niche Passivhaus-only technology to the default ventilation strategy on most new-build homes built to current airtightness standards, and it's increasingly specified on deep retrofit projects. For pricing purposes, that means two very different jobs sit under the same product category: a straightforward new-build first-fix (ducts run into an open structure before boarding, with easy access to every room) and a retrofit install (ducts threaded through an occupied house, ceilings opened and made good, access constrained by existing joists and services). Pricing the two the same is the single most common way builders lose margin on MVHR work.

Unlike air source heat pumps (see air source heat pump pricing guide) there is currently no government grant scheme (no BUS-equivalent) specifically for MVHR, and no MCS certification is required to install it — this keeps the customer-facing price closer to the raw cost build-up than heat pump pricing, without a grant to net off against. The main cost drivers are the unit itself, the ducting system (materials and, more significantly, labour to route it), and commissioning — the balancing and testing step that Building Control requires evidence of before signing off Part F compliance.

This guide covers unit and ducting cost, labour by property size and access difficulty, and a full worked pricing example showing the build-up from raw cost to quoted price. For the technical installation process — duct sizing, commissioning procedure, and Part F flow rates by room — see mvhr installation.

Key Facts

Quick Reference Table

Spending too long on quotes? squote turns a 2-minute voice recording into a professional quote.

Try squote free →
Scenario Property Installer Cost (materials + labour) Quoted Price to Customer (ex VAT)
New-build, straightforward first-fix 2-bed flat/small house £2,300–£3,100 £2,900–£3,900
New-build, straightforward first-fix 3-bed semi £2,800–£3,700 £3,500–£4,700
New-build, straightforward first-fix 4–5 bed detached £3,600–£4,800 £4,500–£6,100
Retrofit, moderate access (loft + boxing) 3-bed semi £4,000–£5,300 £5,000–£6,700
Retrofit, difficult access (ceilings opened, making good) 3-bed semi £5,200–£6,900 £6,500–£8,700
Retrofit, large property or Passivhaus-grade spec 4–5 bed £6,600–£8,600 £8,300–£10,900

Quoted price assumes a typical contractor margin of 20–30% applied to the installer's own cost base (materials plus labour, before profit). Margin varies by business overhead and market position — see the worked example below for how the build-up works.

Detailed Guidance

Why new-build and retrofit are priced so differently

On a new build, MVHR ducting is installed at first-fix stage, before ceilings are boarded — every room is fully accessible, duct runs can follow the most efficient path through joist voids, and there's no existing decoration to protect or make good. On a retrofit into an occupied or recently-refurbished house, the same duct network has to be threaded through existing ceiling voids, often meaning ceilings are opened in strips, existing services (electrics, other pipework) are worked around, and every opened section needs to be made good (plastering, redecoration) afterwards. The materials cost barely changes between the two scenarios — the labour cost roughly doubles, and a making-good allowance needs adding on top.

Unit sizing and cost

The MVHR unit is sized to the design flow rate — see mvhr installation for the Part F flow-rate calculation by room. As a pricing rule of thumb: a unit rated 30–60 L/s normal flow covers most 3-bed houses; 60–90 L/s covers larger 4–5 bed homes. Premium and Passivhaus-certified units cost significantly more (£1,800–£3,200 trade) but deliver higher heat recovery efficiency (often 90%+) and lower specific fan power — worth presenting as an upgrade tier to customers focused on running costs or energy performance, rather than defaulting every quote to the premium tier.

Ducting — the real cost driver on retrofit

Materials for a semi-rigid ducting kit (manifold-based, one duct per room, per mvhr installation) typically run £550–£900 for a standard house, plus £150–£350 for rigid trunking, insulated external runs and terminal grilles. On a new build, fitting this kit is a relatively quick first-fix job for an experienced installer. On retrofit, the same kit takes considerably longer to install because routes have to be worked out around existing structure, and every metre threaded through a confined loft or ceiling void adds time that doesn't show up in the materials cost at all — this is where retrofit quotes go wrong if priced from a new-build labour assumption.

Labour cost build-up

Specialist MVHR installers (or general installers with BPEC Domestic Ventilation training) typically cost £180–£260 per person per day as a labour cost base (this is the tradesperson's own cost of time — wage-equivalent or subcontract rate — not the day rate charged to the customer, which includes margin). A straightforward new-build 3-bed install runs 2.5–4 days for a two-person gang across design, first-fix ducting, terminal fitting, and commissioning. A retrofit into an occupied house with ceiling access issues commonly runs 4–7 days for the same size property once making-good time is included.

Commissioning — a mandatory line item, not an optional extra

Commissioning (measuring flow at every terminal with an anemometer or vane hood, balancing supply against extract to within Part F tolerance, and completing the commissioning sheet for Building Control) is a distinct, non-negotiable step covered in detail in mvhr installation. Budget half a day to a full day of specialist time depending on house size and terminal count — this should always appear as its own line in the quote, both because it genuinely takes real time with test equipment, and because it's the evidence Building Control will ask for at sign-off.

Where builders lose money on MVHR

Pricing Walkthrough — 3-Bed Semi, New-Build First-Fix

This example shows the build-up from the installer's actual cost to the price quoted to the customer. All figures below "Subtotal (installer cost)" are what the job costs the installer to deliver — the tradesperson's own cost, not what's charged. Margin is applied on top to reach the quoted price.

Item Cost
MVHR unit (45 L/s, mid-range) £950
Semi-rigid ducting + manifold kit (12 terminals) £680
Rigid trunking, external terminals, insulation £220
Consumables (filters, clips, sealant, brackets) £90
Design & duct layout (0.5 day) £110
First-fix ducting install (2 days, gang of 2 @ £220/day/person) £880
Second-fix, terminal fitting (1 day, gang of 2) £440
Commissioning, balancing, Part F certificate (0.5 day) £220
Subtotal (installer cost) £3,590
Margin (25%) £900
Quoted price to customer (ex VAT) £4,490

This sits within the £3,500–£4,700 new-build 3-bed range in the reference table above. For the equivalent retrofit scenario, add roughly £1,500–£3,000 to the installer cost subtotal for extended labour (ceiling access, additional first-fix days) and making-good (plastering and redecoration of opened sections), pushing the installer cost to roughly £5,000–£6,500 and the quoted price, at the same 25% margin, to approximately £6,300–£8,100 — consistent with the retrofit rows in the reference table.

VAT and the customer-facing total

The figures above are stated ex VAT, consistent with how most trade quotes are built up before the final invoice total. Confirm whether the property qualifies for a reduced VAT rate (5%) under the energy-saving materials relief rules current at the time of quoting — this can apply to some ventilation and energy efficiency installations, but eligibility and scope change periodically, so verify current HMRC guidance before applying a reduced rate to a quote.

Frequently Asked Questions

Is MVHR eligible for any government grant, like the Boiler Upgrade Scheme for heat pumps?

Not currently. Unlike air source heat pumps, ground source heat pumps, and biomass boilers, there is no dedicated national grant scheme for MVHR installation as of 2026. The full quoted price is generally payable by the customer without a grant to net off, which should be communicated clearly at quote stage since customers researching heat pump grants sometimes assume a similar scheme exists for ventilation.

Why is retrofit MVHR so much more expensive than new-build?

Almost entirely labour, not materials. New-build ducting is installed into an open structure before ceilings go up — every route is accessible. Retrofit means threading the same duct network through existing ceiling voids, working around services already in place, and making good every section of ceiling or wall opened up to route ducts. The unit and ducting materials cost is nearly identical between the two scenarios; the labour and making-good cost is what diverges.

Do I need MCS certification to install MVHR and quote for it?

No — MCS certification is not a requirement for MVHR installation, unlike heat pumps where it's mandatory to access the Boiler Upgrade Scheme grant. Many installers hold BPEC Domestic Ventilation training as a recognised competency standard, which is worth mentioning in a quote as a trust signal even though it isn't a legal requirement to carry out the work.

Can MVHR be retrofitted into any existing house?

Technically yes, but cost-effectiveness depends heavily on the property's air permeability. In a leaky existing house (above roughly 10 m³/h.m² @ 50 Pa, typical of an unrenovated older property), uncontrolled infiltration through gaps in the building fabric overwhelms the heat MVHR recovers, delivering poor value for the install cost. Retrofit MVHR performs best when combined with an airtightness upgrade (draught-proofing, insulation works) — see mvhr installation for the air permeability threshold detail.

What ongoing costs should I flag to the customer beyond the installation price?

Filter replacement (roughly £15–£30 per filter set, changed every 3–6 months depending on filter grade and local air quality) is the main recurring cost, along with an annual heat exchanger check. This isn't part of the installer's cost build-up for the quote itself, but flagging it at quote stage avoids a customer feeling misled about total cost of ownership later.

Regulations & Standards