Summary
An HMO conversion is two jobs sold as one. The first is ordinary refurbishment: partitions, en-suites, a bigger kitchen, rewiring, decorating. The second is a compliance package that the landlord cannot let the property without, and that the local authority will inspect against. Builders who price the first and forget the second end up fitting fire doors and alarm systems for nothing after the HMO officer's visit. Builders who price the second properly tend to win the repeat work, because HMO landlords usually own more than one.
The money is in understanding what the licence conditions and the fire guidance actually require for this house, and separating that from what the landlord would like. A two-storey house with five occupants needs a Grade D1 LD2 alarm system, FD30S doors onto the hallway and stairs, and a protected route to the front door. A three-storey house with the same five occupants moves up to a Grade A system in most councils' standards, emergency lighting on the stairs, and possibly a sprinkler or alternative escape route if the layout is poor. The difference is £5,000–£10,000, and it is decided by the building, not by the client.
This guide gives the 2026 cost ranges for each element of a conversion, the licensing and planning thresholds that change the scope, the room sizes that decide the layout, and a worked example of a three-bedroom semi becoming a six-bedroom HMO. For the licensing framework itself see hmo licensing; for the fire standards in detail see hmo fire safety; for the labour pricing method see pricing labour.
Key Facts
- Mandatory licensing threshold — five or more people in two or more households sharing facilities, in any size of building; the three-storey test was removed in England on 1 October 2018. Many councils also run additional or selective licensing schemes that catch smaller HMOs, so check the council's scheme before quoting
- Minimum bedroom sizes (England) — 6.51 m² for one person over 10, 10.22 m² for two people over 10, 4.64 m² for a child under 10; floor area with headroom under 1.5 m is excluded. A "bedroom" that fails the figure cannot be licensed as one, however nicely it is finished
- Planning: C3 to C4 — a small HMO (3–6 unrelated occupants) is use class C4 and the change from C3 is permitted development unless the council has an Article 4 direction removing it (common in university towns and much of London). Seven or more occupants is sui generis and always needs planning permission
- Building Regulations — a conversion to an HMO is a material change of use under Regulation 5; the Part B fire requirements apply in full and Part E sound insulation applies to the walls and floors between rooms for residential purposes. A full plans or building notice application is required
- Fire alarm, two storeys, up to 6 occupants — Grade D1 LD2 to BS 5839-6:2019+A1:2020 (mains interlinked smoke detectors in the escape route and all habitable rooms, heat detector in the kitchen, with tamper-proof backup batteries); typically £800–£1,500 installed
- Fire alarm, larger or three-storey HMOs — Grade A (panel system to BS 5839-1 with detection to the LD2 or LD1 category the council's standard specifies); £2,500–£5,000 installed, plus £150–£300 a year servicing
- Fire doors — FD30S (30 minutes with smoke seals) to every bedroom, kitchen and living room opening onto the escape route; overhead closers; £350–£600 each supplied and fitted into existing frames, £550–£900 with a new fire-rated frame. See fire door installation and fire door installation pricing guide
- Protected escape route — hall, stairs and landing enclosed in 30-minute construction; glazed panels in doors or partitions replaced with fire-rated glass or boarded; under-stairs cupboards lined or emptied. Budget £1,500–£4,000 depending on how much existing fabric fails
- Emergency lighting — required on escape routes in three-storey and larger HMOs under most councils' standards, to BS 5266-1:2016; £80–£150 per bulkhead fitted, £400–£900 for a typical house
- Fire blanket and extinguisher — a fire blanket in every kitchen and usually a 6-litre foam or 2 kg CO₂ extinguisher on each landing; £40–£80 per item supplied
- Electrics — a satisfactory EICR is a licence condition; most conversions need a consumer unit upgrade (£450–£800), additional circuits for en-suite showers and a bigger kitchen, and Part P notification. Full rewires on 1970s–1980s stock run £4,500–£8,000. See electrical certificates eic mwc eicr explained
- Gas — an annual Landlord Gas Safety Record (CP12) is required; the boiler usually needs upsizing for six showers; £2,500–£4,500 for a 35–40 kW combi or a system boiler with a 210–250-litre unvented cylinder
- Kitchen — most councils' amenity standards require a minimum kitchen area and one set of cooking facilities (four rings, oven, grill) per five occupants, plus worktop, storage and a sink per five; a six-bed HMO usually needs a second cooker or a larger kitchen, £6,000–£12,000
- Bathrooms — a WC and bath or shower for every five occupants, with a separate WC where there are five or more; en-suites at £3,500–£6,000 each including the first and second fix, tanking and tiling. See en suite pricing guide
- Partitions — a stud partition with 12.5 mm plasterboard both sides and 100 mm acoustic insulation, decorated, £120–£180 per m² of wall; add a 30-minute rating with fire-rated board where the partition forms part of the escape route
- Licence fee — £500–£1,500 per HMO for five years depending on the council, paid by the landlord but often asked about at quote stage
- Management regulations — the Management of Houses in Multiple Occupation (England) Regulations 2006 require the manager to keep fire precautions, means of escape, water, gas and electrics in good order; the landlord's obligations, but they shape the specification
- Contingency and margin — 10–15% contingency on a conversion of an older house; 15–25% overhead and profit on the whole job; the HMO officer's inspection often adds items after the first fix
Quick Reference Table
Spending too long on quotes? squote turns a 2-minute voice recording into a professional quote.
Try squote free →| Element | Typical 2026 cost | Notes |
|---|---|---|
| FD30S fire door into existing frame, fitted with closer and intumescent strips | £350–£600 each | Frame must be sound and 30+ mm deep |
| FD30S door and new fire-rated frame | £550–£900 each | Where the existing frame is out of square or too thin |
| Grade D1 LD2 alarm system, 2-storey, 6 rooms | £800–£1,500 | Mains interlinked, heat detector in kitchen |
| Grade A fire alarm system, 3-storey | £2,500–£5,000 | Panel, sounders, detection; annual servicing extra |
| Emergency lighting, 4–6 bulkheads | £400–£900 | 3-hour maintained or non-maintained to BS 5266-1 |
| Protected route upgrades (lining, glazing, under-stairs) | £1,500–£4,000 | Depends on existing fabric |
| Consumer unit upgrade and EICR | £600–£1,100 | Part P notifiable |
| Full rewire, 3-bed house | £4,500–£8,000 | Often needed on pre-1990 stock |
| Boiler upsizing or unvented cylinder | £2,500–£4,500 | Six showers in a morning |
| En-suite shower room, per room | £3,500–£6,000 | Including tanking and tiling |
| Stud partition, acoustic, decorated, per m² | £120–£180 | Fire-rated board on escape route |
| Kitchen enlargement or second cooker | £6,000–£12,000 | To council amenity standard |
| Per lettable room, all-in (building trades) | £8,000–£15,000 | Excludes furniture and fees |
| 3-bed to 6-bed conversion, all-in | £35,000–£80,000 | Regional; London +25–40% |
Detailed Guidance
Start with the council's HMO standards, not the landlord's drawing
Every licensing authority in England publishes its own HMO amenity and fire safety standards, usually based on the LACORS Housing Fire Safety guidance (2008) and the government's HMO licensing guidance. They differ on detail: some require a Grade A alarm for any HMO over two storeys, some accept Grade D1 LD1 up to three storeys with a good escape route, some insist on emergency lighting on every staircase. The council's document is the specification you are pricing against, and it is free. Download it, read the section for the storey count and occupancy the landlord is aiming for, and list every item it requires. That list becomes the first half of your quote.
The second step is the layout. Measure every proposed bedroom against the 6.51 m² and 10.22 m² minimums, excluding any floor area under a sloping ceiling where the headroom is below 1.5 m. A box room of 6.2 m² is not a lettable room, whatever the landlord has been told, and a loft room with a dormer may only count the central strip. If the layout only works by failing the room sizes, say so at quote stage. It is cheaper for everyone than a refused licence.
Fire doors and the protected route
The core of HMO fire safety in a conventional house is a protected route: the hall, stairs and landings enclosed in 30-minute fire-resisting construction with FD30S doors onto them from every room, so that a fire in one bedroom does not cut off everyone else's escape. Pricing it means surveying every door opening on that route.
Most existing internal door frames are too thin for a fire door. An FD30S door is 44 mm thick and needs a frame with at least 30 mm of stop depth and solid fixings into the wall; many 1960s–1990s frames are 25 mm stock with a planted stop. Where the frame can be kept, allow for intumescent strips and cold smoke seals in the door or frame, three hinges to BS EN 1935, an overhead closer to BS EN 1154 and the fire-rated glazing of any vision panel. Where it cannot, allow a new fire-rated frame set, which is the £550–£900 figure. Kitchen doors nearly always need replacing because of the existing glazed panel.
Walls on the route are usually fine if they are masonry or plasterboard on timber studs with two layers of 12.5 mm board each side; a single layer of 9.5 mm board on an older partition is not 30 minutes and needs an extra layer. Check the ceiling under the stairs, the under-stairs cupboard (line it or remove the door and the contents from the route), and any glazed panel above a door. See fire doors and hmo fire safety for the construction detail.
Alarm grades and what the council will ask for
BS 5839-6 sets the grade (the hardware) and the category (the coverage). For a two-storey HMO with up to six occupants the usual requirement is Grade D1, category LD2: mains-powered interlinked detectors with tamper-proof backup power, smoke detection in the hall and landing and in every bedroom and living room, and a heat detector in the kitchen. That is 8–10 detectors for a six-bedroom house, at £60–£120 each installed on an existing lighting circuit with a dedicated supply where the council insists. Radio-interlinked detectors save chasing and are acceptable under the standard.
For three or more storeys, for larger occupancies, or where the escape route is compromised (an inner room, a stair that passes through a living room), most councils require a Grade A system: a control panel to BS 5839-1, sounders, call points and detection, with a commissioning certificate and a maintenance contract. Budget £2,500–£5,000 and tell the landlord about the annual servicing, which is a licence condition. If the council's standard calls for LD1 (detection in every room including the bathrooms and cupboards) the detector count rises by half.
Electrics, gas and water: the hidden capacity problem
Six adults in a house designed for a family of four draw more of everything. The consumer unit usually needs replacing to a metal-clad unit with RCBO or RCD protection to BS 7671:2018+A2:2022, with new circuits for each electric shower (8.5–9.5 kW on 10 mm² cable) and a dedicated cooker circuit for a second cooker. Many councils want a satisfactory EICR before the licence is granted, so a borderline installation is a rewire. Price the EICR at £150–£300 and the likely remedial work from its findings, with the rewire as a priced option.
Hot water is the second problem. A 24 kW combi cannot run two showers at once; a six-bed HMO with en-suites needs a 35–42 kW combi for sequential use or, better, an unvented cylinder of 210–300 litres with a system boiler, which brings Part G3 of the Building Regulations and a G3-qualified installer into the job. Cold mains flow of 20 litres a minute or more at the stopcock is the minimum for an unvented system; test it before you promise one. The annual Landlord Gas Safety Record is the landlord's job, but a new boiler should be left with its commissioning checklist and a first CP12.
Water supply to the extra bathrooms should be in 22 mm to the last branch, and the drainage from en-suites on upper floors usually means a second soil stack or a macerator; see macerator toilet installation pricing guide if a gravity connection is not possible.
Sound, layout and the extra rooms
Part E applies to the walls and floors between rooms for residential purposes on a material change of use, so a partition between two bedrooms should achieve the 43 dB DnT,w+Ctr airborne figure in Approved Document E, and the floor between an upstairs bedroom and a downstairs one should be upgraded with sound-absorbent quilt and a second board layer if it is a bare joisted floor. Pre-completion testing can be required, or the council may accept a robust detail built to a recognised specification. Price the acoustic partition at £120–£180 per m² and allow £800–£1,500 per floor for upgrading a ceiling; a cheap single-board stud wall will fail the test and have to be rebuilt.
A lounge turned into a bedroom needs a window with suitable means of escape under Approved Document B (an opening of at least 0.33 m² and 450 mm minimum in both dimensions, sill no more than 1,100 mm above the floor), a radiator, a data point and two double sockets at a minimum. A new bedroom from a garage brings Part L insulation, damp-proofing and a floor upgrade, at £12,000–£20,000 for the room, which only works where the licence income justifies it.
Building the quote and the margin
Price the job in three sections the landlord can read: compliance (fire doors, alarm, emergency lighting, protected route, EICR, consumer unit), capacity (boiler, cylinder, water, drainage, extra circuits), and layout (partitions, en-suites, kitchen, decorating). Give the compliance section as fixed items with quantities, because the council will ask the landlord for exactly that list. Carry a 10–15% contingency on a pre-1990 house and say what it covers (opening up finds, extra frame replacements, remedial electrics). Add 15–25% overhead and profit on top of your labour and materials, not inside the contingency.
Stage payments by section work well: deposit on order, a stage at first fix, a stage at second fix, and the balance on the building control completion certificate and the alarm commissioning certificate. Keep the certificates together, because the landlord needs them for the licence application: the alarm commissioning certificate, the fire door schedule, the EICR, the building control completion certificate, the Part P certificate and the gas safety record.
Worked example: three-bed semi to six-bed HMO, Midlands
A 1960s three-bedroom semi with a through lounge, kitchen and single bathroom, two storeys, no loft conversion. The landlord wants six lettable rooms with two en-suites and a shared bathroom, and the council's standard requires Grade D1 LD2, FD30S doors, a protected route and a second cooking point for six.
| Item | Cost |
|---|---|
| Partition the through lounge into two bedrooms, acoustic, decorated (14 m²) | £2,300 |
| Partition the large front bedroom into two, acoustic (10 m²) | £1,650 |
| Seven FD30S doors (five into existing frames, two with new frames), closers, seals | £3,850 |
| Protected route: second board layer under stairs, kitchen door glazing, landing wall | £1,900 |
| Grade D1 LD2 alarm, 9 detectors, radio interlinked, dedicated circuit | £1,150 |
| Fire blanket and two extinguishers | £180 |
| Consumer unit upgrade, four new circuits, EICR, Part P | £1,650 |
| 38 kW combi replacing 24 kW, flue, controls, commissioning | £3,200 |
| Two en-suite shower rooms, tanked and tiled, electric showers | £9,800 |
| Shared bathroom refit with separate WC | £5,200 |
| Kitchen extended with second oven and hob, extra worktop and storage | £8,400 |
| Decorating throughout, six rooms and common parts | £3,600 |
| Skips, protection, making good | £1,100 |
| Subtotal labour and materials | £43,980 |
| Contingency 12% | £5,278 |
| Overhead and profit 20% on subtotal | £8,796 |
| Quote (excluding VAT, furniture and licence fee) | £58,054 |
At £9,676 per lettable room this sits in the middle of the national range. The same job in outer London would price at £70,000–£80,000 on labour alone.
Frequently Asked Questions
Does a small HMO with four tenants need the same fire precautions as a licensed one?
The licensing threshold and the fire duties are separate. A house let to four unrelated people is an HMO under the Housing Act 2004 even though it does not need a mandatory licence, and the Management of Houses in Multiple Occupation (England) Regulations 2006 and the Housing Health and Safety Rating System still apply to it, as does the Regulatory Reform (Fire Safety) Order 2005 for the common parts. Most councils expect at least a Grade D1 LD2 alarm and fire doors on the escape route for any HMO. Price the same compliance package, and check whether the council runs an additional licensing scheme that catches it anyway.
Can I use 30-minute fire doors without closers?
Not on the escape route of an HMO. The guidance and nearly every council standard require self-closing devices on FD30S doors, because a fire door propped open is a plain door. Fit overhead closers to BS EN 1154, or the concealed type where the landlord objects to the look, and make sure the door closes and latches from any opening angle before you sign it off. Free-swing closers that hold open and release on the alarm are acceptable on a Grade A system but cost £150–£250 each.
Who applies for building control, the landlord or me?
Either can, but the application is the landlord's legal responsibility as the person carrying out the work, and the certificate is in their name. In practice the builder usually submits a building notice or full plans application on their behalf, because the inspector wants to talk to whoever is on site. Agree in the contract who pays the fee (£600–£1,200 for a conversion of this size) and build the inspections into the programme: foundations are not an issue, but the inspector will want to see the fire doors, the escape route lining and the sound insulation before they are covered.
Does the conversion need planning permission?
For three to six occupants in a C4 small HMO the change from a family house is permitted development unless the council has an Article 4 direction for the area, in which case a full application is needed and may be refused on concentration grounds. Seven or more occupants is a sui generis use and always needs permission. Check the Article 4 position on the council's website before quoting and tell the landlord in writing; a conversion built without the permission it needed cannot be licensed and may have to be reversed.
Should I quote furniture and white goods?
Usually not within the building contract. Furnishing a six-bed HMO costs £6,000–£12,000 and is better bought by the landlord with their own supplier accounts, and it keeps your quote comparable with other builders'. Do quote the fixed items the licence standard requires, such as the fire blanket, the extinguishers and the second cooker, because those belong with the compliance package.
Regulations & Standards
Housing Act 2004, Part 2 — mandatory HMO licensing; the HHSRS assessment framework
Licensing of Houses in Multiple Occupation (Prescribed Description) (England) Order 2018 — removed the three-storey test; five or more persons in two or more households
Licensing of Houses in Multiple Occupation (Mandatory Conditions of Licences) (England) Regulations 2018 — minimum bedroom sizes of 6.51 m², 10.22 m² and 4.64 m²
Management of Houses in Multiple Occupation (England) Regulations 2006 — manager's duties for fire precautions, escape routes and services
Regulatory Reform (Fire Safety) Order 2005 — fire risk assessment of the common parts
Building Regulations 2010, Regulation 5 and 6 — material change of use; Approved Document B (Volume 1) fire safety, Approved Document E sound, Approved Document G3 unvented hot water, Approved Document P electrical safety
Town and Country Planning (Use Classes) Order 1987, Class C4 — small HMOs; Article 4 directions
BS 5839-6:2019+A1:2020 — fire detection and alarm systems in domestic premises; grades and categories
BS 5839-1:2025 — fire detection and alarm systems in non-domestic premises; Grade A systems
BS 5266-1:2016 — emergency lighting code of practice
BS 7671:2018+A2:2022 — IET Wiring Regulations
BS EN 1154 and BS EN 1935 — door closers and single-axis hinges for fire doors
LACORS Housing Fire Safety guidance (2008) — the basis of most councils' HMO fire standards
House in multiple occupation licence — GOV.UK — mandatory licensing threshold and application
HMO licensing: minimum room sizes guidance — GOV.UK — the 2018 room size conditions
Approved Document B: Volume 1 dwellings — GOV.UK — means of escape and fire doors
Approved Document E — GOV.UK — sound insulation on a material change of use
Housing fire safety guidance (LACORS) — the fire safety framework councils adopt
Use classes — Planning Portal — C3, C4 and sui generis HMOs
hmo licensing — licence types, thresholds and conditions
hmo fire safety — alarm grades, fire doors and escape routes in detail
fire door installation — fitting FD30S doors into existing openings