Summary

An annexe is not a garden office. A garden office needs a laptop, lights and a 2kW heater; an annexe has someone living in it, which usually means an electric shower or a hot water cylinder, a hob and oven, space heating, a washing machine and perhaps a heat pump or EV charger. The diversified maximum demand can be 40–60A, and that is the number that drives everything: the cable size, the trench, the earthing, whether the house's existing 60A or 80A cut-out fuse can take it, and whether the job becomes a DNO application rather than a sub-main. Price the load before you price the cable.

The second thing that separates annexe pricing from garden-room pricing is the paperwork. A self-contained annexe that is let, or assessed separately for council tax, is often expected to have its own meter, which means a new DNO service and a supplier meter rather than a sub-main. The electrician's quote then has to say clearly which parts are yours (the meter tails, the consumer unit, the internal circuits, the notification) and which are the DNO's and the energy supplier's, and who pays whom. For the whole-annexe build cost, see granny annexe pricing guide; for the load and cable sizing method, see garden room electrical supply sizing.

This guide gives the price bands, a materials and labour breakdown, three worked quotes and the margin logic for a typical UK sole-trader electrician.

Key Facts

Quick Reference Table

Spending too long on quotes? squote turns a 2-minute voice recording into a professional quote.

Try squote free →
Scenario Cable Protection at house Annexe board Typical price (supply and fit)
Small annexe, electric panel heating, no shower, 15m run 6mm² 3-core SWA 40A RCBO/MCB 4–6-way RCBO + SPD £1,500–£2,200
Annexe with electric shower and kitchenette, 25m run 10mm² 3-core SWA 50–63A 6–8-way RCBO + SPD £2,200–£3,200
Annexe with shower, cooker, heat pump, 40m run, TT earth 16mm² 3-core SWA 63A switch-fuse 8–10-way RCBO + SPD £3,200–£4,800
As above with 30m of drive crossing and reinstatement 16mm² in duct 63A switch-fuse 8–10-way £4,500–£6,500
Annexe fed by new DNO supply (your side only: tails, board, circuits) 25mm² tails DNO cut-out 8–10-way RCBO + SPD £1,200–£2,500 plus DNO and meter
Add EV charger on the annexe board 6mm² final circuit per BS 7671 Section 722 PEN-fault device or TT +£900–£1,500
Add external lighting and sockets around annexe 2.5mm² SWA or 1.5mm² RCBO – +£300–£800

Detailed Guidance

Step 1: Price the load and check the house supply

Add up the annexe's connected load and apply diversity as you would for a small dwelling (IET On-Site Guide Appendix A). A worked example for an annexe with a 9.5kW shower, 6kW cooker, 3kW of panel heaters, 1kW of lights and sockets and a washing machine comes out at roughly 45–55A after diversity, which is why 6mm² is rarely enough for a true annexe.

Then look at the house. Read the cut-out fuse rating on the DNO label (commonly 60A, 80A or 100A), estimate the house's own maximum demand, and decide whether the sum is acceptable. If the house has a 60A fuse, gas heating and an electric shower already, adding a 50A annexe is not realistic on a sub-main; the customer needs a fuse upgrade from the DNO (often free or low cost if the service cable permits, but it can require a new service) or a separate supply. Put this check in your quote as a stated assumption so the customer knows a DNO cost may follow.

Step 2: Cable, route and burial

Measure the actual route, not the straight line: around the patio, under the fence line, up into the annexe. Add 10% for terminations and vertical drops. Size the cable for current-carrying capacity at the installation method used (buried direct, in duct, clipped to a fence is not acceptable long-term), then check voltage drop for the full run plus the longest final circuit in the annexe. On runs over 35–40m with a 40A+ load, 16mm² is often needed for volt drop even where 10mm² carries the current.

Burial: a trench at 450–600mm in the garden, deeper under vehicle areas, with the cable in duct or on a sand bed, covered with warning tape or cable covers. Keep the trench away from tree roots, the new annexe's drainage run and the water supply where possible, and record the route on the EIC with a sketch. Where the annexe builder is digging foundations and service trenches, get the duct in at the same time and price only the pull-through.

Step 3: Earthing decision

Three options, priced differently:

Arrangement When Cost impact
Export PME earth from house Annexe is a building with no touchable extraneous-conductive-parts beyond those bonded, no hot tub or EV charging outside Cheapest: earth via SWA armour and separate CPC; main bonding in annexe if any extraneous metal services
TT island at the annexe External metalwork, hot tub, EV charger, or DNO advises against PME export Add earth rod (1.2m or 2.4m), rod pit, 16mm² earthing conductor, Ra measured under 200Ω (ideally under 100Ω), 100mA S-type incomer or all-RCBO board: +£150–£400
TT for the whole installation House is already TT (rural overhead supply) Rod at the annexe or confirm the house rod serves; same cost band

Do not price an annexe EV charger on an exported PME earth without a PEN-fault protection device or a TT arrangement that complies with BS 7671 Section 722. See ev charger.

Step 4: The annexe consumer unit and circuits

A living annexe usually needs:

Price the annexe fit-out separately from the sub-main; customers often have the annexe supplier's electrician doing the internal work and only need the supply.

Worked quote 1: Modest annexe, 15m sub-main, PME earth

Item Qty Unit Materials Labour
6mm² 3-core SWA 18m £6.50 £117 –
Twin-wall duct 50mm and warning tape 18m £3.00 £54 –
SWA glands, shrouds, earth tags, adaptable boxes 2 sets £18 £36 –
40A RCBO in house board 1 £45 £45 –
6-way RCBO consumer unit with SPD, 5 RCBOs 1 £240 £240 –
Sundries (cable, clips, back boxes, tape) – – £60 –
Trench hand-dug 15m and backfill 15m £40 – £600
Electrician: install, terminate, test, certify 1.5 days £340 – £510
Part P notification (CPS) 1 £8 £8 –
Subtotals £560 £1,110
Materials markup 20% £112
Quote total (ex VAT) £1,782

Worked quote 2: Annexe with shower and cooker, 30m run, TT earth

Item Materials Labour
10mm² 3-core SWA, 34m at £10.50 £357 –
Duct, tape, sand £110 –
Glands, tags, boxes £40 –
63A switch-fuse at house (board full) and tails £95 –
8-way RCBO board with SPD, 7 RCBOs £310 –
Earth rod 1.2m, pit, clamp, 16mm² earthing conductor £55 –
Sundries £80 –
Trench 30m by mini-digger (hire £180 plus operator day) £180 £320
Electrician 2.5 days at £340 plus mate 1 day at £180 – £1,030
Part P notification £8 –
Subtotals £1,235 £1,350
Materials markup 20% £247
Quote total (ex VAT) £2,832

Worked quote 3: Separate DNO supply (your side only)

The customer has had a DNO quote of £3,200 for a new single-phase service to the annexe and the supplier will fit a smart meter at no charge. Your quote covers: meter box or cabinet position agreed with the DNO, 25mm² tails and 16mm² earthing conductor from the cut-out to the annexe board, a 10-way RCBO board with SPD, the annexe final circuits, test and EIC. Typical £1,400–£2,400 for the board and tails plus £1,200–£2,500 for the final circuits depending on the fit-out. Make clear in writing that the DNO's £3,200, any wayleave or road-opening costs, and the meter appointment are outside your price and that your start date depends on the DNO's connection date.

Margin and risk items to include

Frequently Asked Questions

Can I just run the annexe off a spare 32A way in the house board?

Only if the annexe's diversified demand is under 32A and the house supply has the headroom, which rules out any annexe with an electric shower. Price the load first. A 32A sub-main to a bedsit-style annexe with gas-free heating and a shower will trip and the customer will be back.

Does the annexe need its own meter?

Not for electrical safety. It is a question for the planning status, council tax and whether the annexe is let. A sub-main with a private sub-meter (£60–£150 fitted) lets the owner recharge usage without a DNO supply. A genuinely separate dwelling is usually better served by its own DNO supply and supplier meter.

Is the trench the electrician's job?

Whoever is cheapest and available. Many electricians price the trench as a separate line so the customer or groundworker can do it to a written specification (depth, width, duct, sand, tape, left open for inspection). Always inspect before backfill and photograph the route for the certificate.

Do I need Building Control for the annexe's electrics if the annexe itself is under Building Regulations?

If the annexe is being built under a Building Regulations application, the electrical work can be inspected as part of that application, but most Building Control bodies still want an EIC from a competent person scheme member or will charge for third-party inspection. Agree this with the main contractor at quote stage so the notification is not paid for twice.

What size cable for an annexe with an EV charger and a heat pump?

Add the charger (32A for 7kW) and the heat pump (typically 10–20A for 5–8kW domestic units) to the annexe's other loads. Many such annexes end up at 63–80A, which exceeds what most house supplies can spare and points firmly to a separate DNO supply or load management. Specify load-curtailment on the charger and price the supply accordingly.

Regulations & Standards