Summary
An annexe is not a garden office. A garden office needs a laptop, lights and a 2kW heater; an annexe has someone living in it, which usually means an electric shower or a hot water cylinder, a hob and oven, space heating, a washing machine and perhaps a heat pump or EV charger. The diversified maximum demand can be 40–60A, and that is the number that drives everything: the cable size, the trench, the earthing, whether the house's existing 60A or 80A cut-out fuse can take it, and whether the job becomes a DNO application rather than a sub-main. Price the load before you price the cable.
The second thing that separates annexe pricing from garden-room pricing is the paperwork. A self-contained annexe that is let, or assessed separately for council tax, is often expected to have its own meter, which means a new DNO service and a supplier meter rather than a sub-main. The electrician's quote then has to say clearly which parts are yours (the meter tails, the consumer unit, the internal circuits, the notification) and which are the DNO's and the energy supplier's, and who pays whom. For the whole-annexe build cost, see granny annexe pricing guide; for the load and cable sizing method, see garden room electrical supply sizing.
This guide gives the price bands, a materials and labour breakdown, three worked quotes and the margin logic for a typical UK sole-trader electrician.
Key Facts
- Typical sub-main price — £1,500–£3,500 for a 6mm² or 10mm² SWA run of 10–40m to a 4–8-way RCBO consumer unit, including trench where you dig it, glands, testing and notification.
- Annexe maximum demand — commonly 40–60A after diversity (shower 8.5–10.5kW alone is 37–46A; cooker 6–7kW diversified to about 15–20A; heating 2–4kW; sockets and lights). The house cut-out fuse (60A, 80A or 100A) must carry the house plus the annexe. See garden room electrical supply sizing.
- SWA sizing (3-core, 70°C thermoplastic, BS 7671 Appendix 4 Table 4D4A) — 6mm² ≈ 53A clipped direct; 10mm² ≈ 73A; 16mm² ≈ 97A. Buried in duct (Method D) ratings are lower: check the table for the installation method actually used.
- Voltage drop limit — 5% (11.5V at 230V) for the whole run from origin to the furthest final circuit (BS 7671 Appendix 12). Rough mV/A/m: 6mm² 7.3, 10mm² 4.4, 16mm² 2.8, 25mm² 1.75. A 40A load over 45m on 10mm² drops about 7.9V, leaving under 3.6V for the annexe's own circuits.
- Burial — BS 7671 regulation 522.8.10 requires buried cables to be protected against damage with warning tape or covers; no statutory depth, but 450–600mm in gardens and 600mm+ under drives is standard practice. Twin-wall ducting (black for electrical) is good practice and makes a future upgrade cheap.
- Earthing — exporting the house's PME (TN-C-S) earth to a detached building is restricted under BS 7671 regulation 411.4.5 where there are touchable extraneous-conductive-parts; many annexes with external metalwork, hot tubs or EV charging are made TT with a local earth rod. A rod and TT arrangement adds £150–£400. See tncs earthing pme.
- Protection in the annexe — a dedicated consumer unit with a main switch, RCBOs on every final circuit, Type 2 SPD (regulation 443.4) and, where circuits serve socket-outlets up to 32A in the kinds of premises listed in regulation 421.1.7, AFDDs. For a single private dwelling AFDDs are recommended rather than required. See spd installation.
- Supply device at the house — a dedicated MCB or RCBO for the sub-main in the house board (or a switch-fuse if the board is full or an older type), sized to the cable, typically 40A, 50A or 63A.
- Part P — a new circuit, outdoor work and a new consumer unit are all notifiable in England and Wales. Self-certify through a competent person scheme (£3–£10 per notification on top of annual membership) or notify Building Control (£250–£500 per job). See part p notifiable work.
- Certification — Electrical Installation Certificate with full schedule of test results. Not a Minor Works Certificate.
- DNO alternative — a new single-phase service to the annexe from the street or from the existing service head costs £1,500–£5,000+ for the DNO's work, plus meter installation by the chosen supplier, plus your tails, cut-out-to-board and internal work. Quotes take 2–6 weeks; some operators charge a design fee.
- Labour — a qualified electrician £280–£400 per day; two-person team for cable pulling and trenching days. A typical sub-main job is 2–3 days with one and a half to two people.
- Trenching — if the electrician digs: £30–£60 per linear metre for a 600mm trench in soft ground by hand, less by mini-digger on a clear run; crossing a drive or patio adds cutting and reinstatement at £80–£150 per metre.
Quick Reference Table
Spending too long on quotes? squote turns a 2-minute voice recording into a professional quote.
Try squote free →| Scenario | Cable | Protection at house | Annexe board | Typical price (supply and fit) |
|---|---|---|---|---|
| Small annexe, electric panel heating, no shower, 15m run | 6mm² 3-core SWA | 40A RCBO/MCB | 4–6-way RCBO + SPD | £1,500–£2,200 |
| Annexe with electric shower and kitchenette, 25m run | 10mm² 3-core SWA | 50–63A | 6–8-way RCBO + SPD | £2,200–£3,200 |
| Annexe with shower, cooker, heat pump, 40m run, TT earth | 16mm² 3-core SWA | 63A switch-fuse | 8–10-way RCBO + SPD | £3,200–£4,800 |
| As above with 30m of drive crossing and reinstatement | 16mm² in duct | 63A switch-fuse | 8–10-way | £4,500–£6,500 |
| Annexe fed by new DNO supply (your side only: tails, board, circuits) | 25mm² tails | DNO cut-out | 8–10-way RCBO + SPD | £1,200–£2,500 plus DNO and meter |
| Add EV charger on the annexe board | 6mm² final circuit | per BS 7671 Section 722 | PEN-fault device or TT | +£900–£1,500 |
| Add external lighting and sockets around annexe | 2.5mm² SWA or 1.5mm² | RCBO | – | +£300–£800 |
Detailed Guidance
Step 1: Price the load and check the house supply
Add up the annexe's connected load and apply diversity as you would for a small dwelling (IET On-Site Guide Appendix A). A worked example for an annexe with a 9.5kW shower, 6kW cooker, 3kW of panel heaters, 1kW of lights and sockets and a washing machine comes out at roughly 45–55A after diversity, which is why 6mm² is rarely enough for a true annexe.
Then look at the house. Read the cut-out fuse rating on the DNO label (commonly 60A, 80A or 100A), estimate the house's own maximum demand, and decide whether the sum is acceptable. If the house has a 60A fuse, gas heating and an electric shower already, adding a 50A annexe is not realistic on a sub-main; the customer needs a fuse upgrade from the DNO (often free or low cost if the service cable permits, but it can require a new service) or a separate supply. Put this check in your quote as a stated assumption so the customer knows a DNO cost may follow.
Step 2: Cable, route and burial
Measure the actual route, not the straight line: around the patio, under the fence line, up into the annexe. Add 10% for terminations and vertical drops. Size the cable for current-carrying capacity at the installation method used (buried direct, in duct, clipped to a fence is not acceptable long-term), then check voltage drop for the full run plus the longest final circuit in the annexe. On runs over 35–40m with a 40A+ load, 16mm² is often needed for volt drop even where 10mm² carries the current.
Burial: a trench at 450–600mm in the garden, deeper under vehicle areas, with the cable in duct or on a sand bed, covered with warning tape or cable covers. Keep the trench away from tree roots, the new annexe's drainage run and the water supply where possible, and record the route on the EIC with a sketch. Where the annexe builder is digging foundations and service trenches, get the duct in at the same time and price only the pull-through.
Step 3: Earthing decision
Three options, priced differently:
| Arrangement | When | Cost impact |
|---|---|---|
| Export PME earth from house | Annexe is a building with no touchable extraneous-conductive-parts beyond those bonded, no hot tub or EV charging outside | Cheapest: earth via SWA armour and separate CPC; main bonding in annexe if any extraneous metal services |
| TT island at the annexe | External metalwork, hot tub, EV charger, or DNO advises against PME export | Add earth rod (1.2m or 2.4m), rod pit, 16mm² earthing conductor, Ra measured under 200Ω (ideally under 100Ω), 100mA S-type incomer or all-RCBO board: +£150–£400 |
| TT for the whole installation | House is already TT (rural overhead supply) | Rod at the annexe or confirm the house rod serves; same cost band |
Do not price an annexe EV charger on an exported PME earth without a PEN-fault protection device or a TT arrangement that complies with BS 7671 Section 722. See ev charger.
Step 4: The annexe consumer unit and circuits
A living annexe usually needs:
- Lighting (1–2 circuits), sockets (1–2 ring finals or radials), shower (40–50A radial on 10mm² for a 9.5–10.5kW shower), cooker (32A on 6mm²), heating (panel heaters or wet UFH controls), immersion or cylinder, and an extractor fan circuit if not on lighting.
- RCBOs throughout (Type A minimum), Type 2 SPD, main switch sized to the sub-main. A 10-way metal enclosure to BS EN 61439-3 with RCBOs and SPD costs £180–£320 trade.
- Bathroom zones and IP ratings for the shower room (BS 7671 Section 701) and supplementary bonding unless the omission conditions are met.
- Smoke and heat alarms to BS 5839-6 Grade D1 or D2 interlinked, which Building Control will expect for sleeping accommodation.
Price the annexe fit-out separately from the sub-main; customers often have the annexe supplier's electrician doing the internal work and only need the supply.
Worked quote 1: Modest annexe, 15m sub-main, PME earth
| Item | Qty | Unit | Materials | Labour |
|---|---|---|---|---|
| 6mm² 3-core SWA | 18m | £6.50 | £117 | – |
| Twin-wall duct 50mm and warning tape | 18m | £3.00 | £54 | – |
| SWA glands, shrouds, earth tags, adaptable boxes | 2 sets | £18 | £36 | – |
| 40A RCBO in house board | 1 | £45 | £45 | – |
| 6-way RCBO consumer unit with SPD, 5 RCBOs | 1 | £240 | £240 | – |
| Sundries (cable, clips, back boxes, tape) | – | – | £60 | – |
| Trench hand-dug 15m and backfill | 15m | £40 | – | £600 |
| Electrician: install, terminate, test, certify | 1.5 days | £340 | – | £510 |
| Part P notification (CPS) | 1 | £8 | £8 | – |
| Subtotals | £560 | £1,110 | ||
| Materials markup 20% | £112 | |||
| Quote total (ex VAT) | £1,782 |
Worked quote 2: Annexe with shower and cooker, 30m run, TT earth
| Item | Materials | Labour |
|---|---|---|
| 10mm² 3-core SWA, 34m at £10.50 | £357 | – |
| Duct, tape, sand | £110 | – |
| Glands, tags, boxes | £40 | – |
| 63A switch-fuse at house (board full) and tails | £95 | – |
| 8-way RCBO board with SPD, 7 RCBOs | £310 | – |
| Earth rod 1.2m, pit, clamp, 16mm² earthing conductor | £55 | – |
| Sundries | £80 | – |
| Trench 30m by mini-digger (hire £180 plus operator day) | £180 | £320 |
| Electrician 2.5 days at £340 plus mate 1 day at £180 | – | £1,030 |
| Part P notification | £8 | – |
| Subtotals | £1,235 | £1,350 |
| Materials markup 20% | £247 | |
| Quote total (ex VAT) | £2,832 |
Worked quote 3: Separate DNO supply (your side only)
The customer has had a DNO quote of £3,200 for a new single-phase service to the annexe and the supplier will fit a smart meter at no charge. Your quote covers: meter box or cabinet position agreed with the DNO, 25mm² tails and 16mm² earthing conductor from the cut-out to the annexe board, a 10-way RCBO board with SPD, the annexe final circuits, test and EIC. Typical £1,400–£2,400 for the board and tails plus £1,200–£2,500 for the final circuits depending on the fit-out. Make clear in writing that the DNO's £3,200, any wayleave or road-opening costs, and the meter appointment are outside your price and that your start date depends on the DNO's connection date.
Margin and risk items to include
- Materials markup — 15–25% is normal on SWA and boards; copper price swings make SWA volatile, so date your quote and give 30 days' validity.
- Trench unknowns — rock, roots, old foundations and unmarked services. Quote hand-dig per metre with a stated allowance and a rate for extras, or exclude excavation entirely.
- House board condition — if the existing board has no spare way or is a plastic unit that cannot take a switch-fuse, price a switch-fuse enclosure next to it, or a board change (£500–£900 extra). See consumer unit upgrade.
- DNO fuse upgrade — state that you have assumed the existing cut-out can carry the combined load and that a DNO upgrade, if needed, is extra.
- Testing time — a sub-main plus an 8-circuit annexe is a full half-day of testing and certification. Do not absorb it.
- Waiting on other trades — annexe not watertight, no route into the building, foundations not in. Put a return-visit charge in the terms.
Frequently Asked Questions
Can I just run the annexe off a spare 32A way in the house board?
Only if the annexe's diversified demand is under 32A and the house supply has the headroom, which rules out any annexe with an electric shower. Price the load first. A 32A sub-main to a bedsit-style annexe with gas-free heating and a shower will trip and the customer will be back.
Does the annexe need its own meter?
Not for electrical safety. It is a question for the planning status, council tax and whether the annexe is let. A sub-main with a private sub-meter (£60–£150 fitted) lets the owner recharge usage without a DNO supply. A genuinely separate dwelling is usually better served by its own DNO supply and supplier meter.
Is the trench the electrician's job?
Whoever is cheapest and available. Many electricians price the trench as a separate line so the customer or groundworker can do it to a written specification (depth, width, duct, sand, tape, left open for inspection). Always inspect before backfill and photograph the route for the certificate.
Do I need Building Control for the annexe's electrics if the annexe itself is under Building Regulations?
If the annexe is being built under a Building Regulations application, the electrical work can be inspected as part of that application, but most Building Control bodies still want an EIC from a competent person scheme member or will charge for third-party inspection. Agree this with the main contractor at quote stage so the notification is not paid for twice.
What size cable for an annexe with an EV charger and a heat pump?
Add the charger (32A for 7kW) and the heat pump (typically 10–20A for 5–8kW domestic units) to the annexe's other loads. Many such annexes end up at 63–80A, which exceeds what most house supplies can spare and points firmly to a separate DNO supply or load management. Specify load-curtailment on the charger and price the supply accordingly.
Regulations & Standards
BS 7671:2018+A4:2026 — Requirements for Electrical Installations (IET Wiring Regulations, Amendment 4 published 15 April 2026), including regulation 411.4.5 (PME export to outbuildings), regulation 411.5.3 (TT earth electrode resistance), regulation 443.4 (SPDs), regulation 522.8.10 (buried cables), Section 701 (bathrooms), Section 722 (EV charging), Appendix 4 (cable ratings and volt drop) and Appendix 12 (voltage drop limits)
Building Regulations Approved Document P (England) and the Welsh equivalent — notification of new circuits, outdoor work and consumer units
Building Regulations Approved Document B Volume 1 and BS 5839-6:2019+A1:2020 — fire detection in dwellings, including annexes used for sleeping
BS EN 61439-3 — distribution boards intended to be operated by ordinary persons (domestic consumer units)
BS EN 61008 / BS EN 61009 — RCCBs and RCBOs
BS 5467 and BS 6724 — steel wire armoured cables (PVC and LSZH)
Electricity Safety, Quality and Continuity Regulations 2002 — DNO duties, PME earthing conditions and new connections
IET On-Site Guide (BS 7671:2018+A4:2026 edition) — diversity and simplified cable selection
BS 7671:2018+A4:2026 (IET Wiring Regulations) — Institution of Engineering and Technology
Energy Networks Association: getting a new electricity connection — ENA
Electricity Safety, Quality and Continuity Regulations 2002 — legislation.gov.uk
BS 5839-6:2019+A1:2020 — BSI Knowledge
garden room electrical supply sizing — the load and cable sizing method this pricing is built on
granny annexe pricing guide — whole-annexe build pricing including utilities
workshop supply — the full outbuilding sub-main design process and PME vs TT decision
swa cable glanding and termination — gland selection and armour-as-CPC checks
tncs earthing pme — when the PME earth can and cannot be exported
part p notifiable work — what to notify and how much it costs
garden room pricing guide — the lighter-load garden room comparison