Summary

Dry lining is the foundation trade of modern UK building. Replacing wet plaster on bricks with plasterboard fixed by adhesive (dot-and-dab) or metal/timber stud framing saves drying time, reduces moisture in the structure, allows insulation and services to run within the wall depth, and gives a flatter substrate for finishing.

Pricing dry lining is mostly about the labour rate, the substrate condition, and the spec of board chosen. A 12.5mm wallboard is the cheapest; 15mm boards (better acoustic, fire resistance) cost 20–40% more in material and 10–20% more in labour because they're heavier. Moisture-resistant (green) and fire-rated (pink) boards are spec-driven by room use and Building Regulations Part B / Part F.

This guide covers labour rates by board type and fixing method, materials, substrate preparation, the BS 8212 framework, productivity expectations, and worked examples for common UK dry lining scopes. For broader plasterboard and finishing work see plasterboard types, dot and dab and scrim tape and jointing.

Key Facts

Quick Reference Table

Spending too long on quotes? squote turns a 2-minute voice recording into a professional quote.

Try squote free →
Scenario Spec Time Labour Materials Full Price
4×3×2.4m room walls, dot-and-dab + skim 12.5mm standard 1.5 days £270–£420 £100–£180 £370–£600
4×3×2.4m room walls, dot-and-dab + T&J 12.5mm standard 1 day £180–£280 £80–£140 £260–£420
4×3×2.4m room walls, metal stud + skim 12.5mm 2.5 days £450–£700 £180–£300 £630–£1,000
4×3 ceiling on timber joists + skim 12.5mm 1 day £180–£280 £60–£100 £240–£380
Bathroom walls (waterproof board) + tile substrate MR / cement board 1.5 days £270–£420 £140–£240 £410–£660
Loft conversion — 30m² wall, fire-rated to corridor 12.5mm Type F 1.5 days £270–£420 £140–£240 £410–£660
Garage conversion — 25m² wall + ceiling, acoustic 15mm acoustic 2 days £400–£600 £180–£300 £580–£900
Whole 2-bed flat (200m² total walls + ceilings) mixed spec 8–12 days £1,800–£3,200 £900–£1,600 £2,700–£4,800
Office partition wall (40m² metal stud) 12.5mm 2 days £400–£600 £240–£400 £640–£1,000

Detailed Guidance

Board Type Selection

Standard wallboard (12.5mm): most common. Fire reaction Euroclass A2-s1,d0. For general walls and ceilings in domestic use.

Heavy-duty / contract board (15mm): better acoustic and impact resistance. Required in some hotel, school and commercial corridor specifications. Adds 20–40% to material cost.

Moisture-resistant (MR / "green"): paper face is moisture-resistant. For bathrooms, kitchens, utility rooms. NOT waterproof — still needs tanking behind tiled wet-area showers.

Fire-rated (Type F / "pink"): glass-fibre reinforced. For protected corridors, escape routes, garages with habitable rooms above. 12.5mm Type F gives 30 minutes resistance on stud; 15mm Type F gives 60 minutes.

Acoustic board (e.g. Gypframe, Knauf Soundshield): denser, better sound reduction. For party walls in flats, hotel rooms, music rooms.

Cement board (Hardiebacker, Aquapanel): not strictly plasterboard, but a tile substrate. For wet rooms and shower walls.

The customer rarely asks for board spec — the installer or designer specifies. Quote with the spec named: "12.5mm standard wallboard for habitable rooms; 12.5mm MR for kitchen and bathroom; 15mm Type F for garage ceiling adjacent to bedroom."

Dot-and-Dab vs Stud Frame

Dot-and-dab (adhesive fix to masonry):

Metal stud framing (Gypframe, Knauf, Siniat systems):

Timber stud framing:

Substrate Preparation

Before dot-and-dab:

Before stud framing:

Acoustic and Fire Detail

Acoustic walls (e.g. between flats):

Fire walls (e.g. between garage and habitable room):

Tape-and-Joint vs Skim Finish

T&J finish (joints only filled and feathered):

Skim finish (full board covered with 2–3mm plaster):

The skim finish is the UK domestic default. T&J is common in commercial new build, office partitions and budget refits.

Productivity and Estimating

A typical 4×3m bedroom has:

Plus ceiling: 12m².

Total: 42.4m².

At 40 m²/day for dot-and-dab walls and 35 m²/day for ceiling: 1.5 days. Add 1 day for skim. Total: 2.5 days for the room.

Use this productivity rule when quoting larger projects.

Common Site Overruns

Frequently Asked Questions

Should I dot-and-dab onto bare brick or plaster first?

Either works. The product standard (BS 8212 and manufacturer instructions) permits direct dot-and-dab to brick, block, concrete. The brick must be sound, dust-free, and not subject to rising damp. Skim of bonding-coat plaster before boards adds cost but ISN'T needed for compliance.

Can I dot-and-dab over old plasterboard?

Not recommended. The old board may have failed adhesive, damp, or paint that prevents new bond. Remove old board first.

How do I fix into a dot-and-dab wall after the work is done?

Use plasterboard cavity fixings (e.g. Spring Toggles, Plasplugs, Fischer DUOPower). Heavy items (TVs >25kg, shelving) should fix through to the brick beyond the dab — use chemical anchors or expansion bolts of suitable length.

Is there a difference between British Gypsum, Knauf, and Siniat boards?

The products are equivalent for most domestic specifications. System warranties differ — if you use British Gypsum board with Knauf adhesive and Knauf metal track, neither manufacturer's system warranty applies. For commercial / spec-driven work, stick to one manufacturer's system.

What does BS 8212 actually say?

BS 8212:1995 "Code of practice for dry lining and partitioning using gypsum plasterboard" is the UK standard for dry lining. Key requirements:

The standard is the reference for compliance disputes.

Regulations & Standards