Summary

Getting the depth right for a screed — minimum thickness, cover over underfloor heating pipes, drying time before flooring — is a different question from getting the quantity right for the order. Depth and specification are covered fully in screed depth, which answers "how thick does this screed need to be, and how long will it take to dry." This article picks up once depth and screed type are decided and answers what follows: how much cement, sand, ready-mix, or pumped liquid screed to actually order, avoiding both an under-order (a stalled pour) and an over-order (unusable surplus, since screed cannot be stored once mixed or delivered).

The ordering method differs sharply by screed type. Bagged sand/cement mixed on site is priced by the bag/tonne and forgiving of small quantity errors — a spare bag of cement is not wasted money the way a part-load of ready-mix or pumped screed is. Ready-mix and pumped liquid anhydrite screed are both ordered by the cubic metre from a supplier with a minimum load charge, meaning a small domestic room can trigger a minimum-load cost regardless of how little screed it actually needs — the single most commonly missed cost driver in screed quoting, and it changes which screed type is genuinely cheapest for a small job.

This article works through bagged sand/cement ordering, ready-mix and the minimum-load problem, pumped liquid screed thresholds, and self-levelling compound coverage rates, with three worked examples: a small bathroom, a kitchen extension, and a whole-ground-floor new build.

Key Facts

Quick Reference Table

Got your quantities? squote builds the full quote with labour, materials and markup.

Try squote free →
Screed Type Order Unit Typical Minimum Load/Charge Waste Allowance Best Suited To
Bagged sand/cement (hand or mixer mixed) Bags of cement + tonnes of sand None (buy exact quantity + spares) 10% Small jobs, awkward access, part-room repairs
Ready-mix sand/cement (wet, lorry-delivered) m³ 4–6m³ (mini-mix trucks from ~1–2m³ at higher rate) 10% Mid-size single-pour rooms with lorry access
Pumped liquid anhydrite/calcium sulphate m³ ~3–5m³ domestic minimum (commercial minimum 20–30m³) 5% Whole-floor pours, UFH installations, larger areas
Self-levelling compound (SLC) 20kg bags None (buy to calculated bag count) 5–10% (round up per bag) Thin toppings (3–15mm) over an existing screed/slab
Fibre reinforcement additive Pre-measured bags per m³ Matches screed order quantity None (dose per m³ exactly) Any screed where the spec calls for fibre reinforcement

Detailed Guidance

Step 1: Confirm area and depth before ordering anything

Volume (m³) = floor area (m²) × depth (m). This is the same starting calculation as the basic volume example in screed depth — the depth itself (65mm standard sand/cement, 30–40mm anhydrite, etc.) is confirmed using that article's method before this article's quantity takeoff begins. Measure the actual room area net of any built-in features that won't be screeded (kitchen island plinths, permanently fixed cabinetry footprints), since screeding over an area that won't actually need covering wastes material.

Step 2: Decide bagged, ready-mix, or pumped — and check the minimum load

This decision is where quantity and cost interact most directly:

Step 3: Worked example — small bathroom, bagged sand/cement

Scenario: A 2.4m × 1.8m bathroom (4.3m²), 65mm sand/cement floating screed over insulation, no underfloor heating, awkward first-floor access ruling out any pumped or wet ready-mix delivery.

This is a textbook case for bagged materials carried up by hand — the total order is small enough that a ready-mix or pump minimum load would cost several times more than the screed the room actually needs.

Step 4: Worked example — kitchen extension, ready-mix sand/cement

Scenario: A 6m × 4.5m single-storey kitchen extension (27m²), 75mm sand/cement screed over insulation with underfloor heating (30mm minimum cover over pipe crown, confirmed via screed depth), good vehicle access for a ready-mix lorry to pump or chute directly into the room.

This example shows why the minimum-load question has to be checked before committing to ready-mix — a job needing only 2.23m³ can end up paying for a full 4m³ minimum load, which changes the real cost-per-m² materially versus a bagged or mini-mix alternative.

Step 5: Worked example — whole ground floor, new-build, pumped liquid anhydrite screed

Scenario: A new-build detached house, 95m² ground floor (open-plan living/kitchen/hall combined for a single continuous pour), 40mm anhydrite screed over underfloor heating pipes (confirmed cover per screed depth), good site access for a screed pump rig.

This example is the clean case for pumped liquid screed — a large enough continuous area that the minimum load isn't a constraint, good access for the pump rig, and a single-pour job that benefits from liquid screed's self-levelling and faster laying time over a large open-plan area.

Step 6: Self-levelling compound — ordering by bag, not by volume

Where the job is a thin self-levelling compound topping over an existing sound screed or slab (rather than a full new screed), order by bag count rather than volume:

Common quantity-ordering mistakes

Frequently Asked Questions

Is it cheaper to hand-mix bagged screed or order ready-mix for a mid-size room?

It depends entirely on whether the calculated volume clears the ready-mix supplier's minimum load. Below the minimum, bagged materials are almost always cheaper per m² since there's no minimum-load penalty — above it, ready-mix is usually cheaper on labour and gives a more consistent mix. Calculate the volume first, check the local supplier's minimum load, and compare both routes before committing.

Can I order slightly less than the calculated volume to save money, and top up if needed?

No — this is one of the more expensive mistakes in screed ordering. Wet ready-mix or pumped screed cannot realistically be "topped up" mid-pour without a visible cold joint and workability mismatch, and running out mid-pour is a much costlier problem than the waste allowance. Always order the full calculated volume plus the standard waste allowance, never below it.

How much does the waste allowance actually cost me if I over-order?

For bagged materials, very little — unused bags of cement (kept dry) or part-bulk-bags of sand are usable on the next job. For ready-mix or pumped screed, the waste allowance is genuinely consumed (poured and used as slightly thicker screed, or discarded if genuinely surplus) — but 5–10% is a modest cost relative to the risk and cost of running short mid-pour, which is why the allowance is standard practice rather than an optional buffer.

Does a fibre-reinforced screed need more or less material than a standard mix?

The base cement and sand quantities are unchanged — fibre reinforcement is an additive dosed into the same mix, typically at 0.9kg of polypropylene fibres per m³, not a substitute for any of the base materials. Order the fibre dose to match the confirmed screed volume exactly, since under-dosing loses the reinforcement benefit and over-dosing can affect workability.

Regulations & Standards