Summary
Floor screeds are one of the least-forgiving construction elements. Get the mix wrong, cure it wrong, or tile onto it too early and the result is a bond failure that's only visible weeks or months later when tiles lift, cracks appear, or wood floors cup. Rectification is almost always a full lift and re-lay — there is no partial fix.
For a plasterer, floor-layer or tiler, screed knowledge sits at the boundary between two trades and is the point where blame lands when a floor fails. The tiler blames the screeder, the screeder blames the drying schedule, the customer blames whoever they can find. Documented pre-tile moisture testing protects everyone.
The rise of anhydrite (calcium sulphate) liquid screeds in the last 15 years has changed the game — they are faster to lay, self-levelling and better for UFH — but they demand rigorous drying discipline before covering. Cement screeds are more forgiving but slow. Choose the right system for the programme.
Key Facts
- Cement:sand ratio — 1:3 by volume is the modern standard for domestic sand-and-cement floor screeds; 1:4 acceptable for lightly-loaded areas. Never go weaker than 1:4.
- Sand type — sharp (concreting) sand only. Building/plastering sand contains fine particles that weaken the mix and encourage cracking.
- Minimum depth (BS 8204-1) — 25mm bonded to concrete; 65mm unbonded (with DPM); 75mm floating (with insulation); 75mm minimum over UFH pipes measured above pipe crown.
- Foot traffic — cement screed at 24 hours; anhydrite at 24–48 hours; both keep loading light until 7 days.
- Full cure — cement screed reaches ~95% strength at 28 days. Do not tile before then unless using a rapid-set primer/adhesive system.
- Curing method — polythene sheet over cement screed for first 7 days minimum; keep from drying too fast in warm/windy conditions.
- Anhydrite/calcium sulphate screed — self-levelling, poured to depths of 40–75mm typical, sets to walkable in 24–48 hours. Cannot be laid over reactive substrates (see below).
- Anhydrite laitance — a chalky calcium-sulphate hydrate film forms on the surface. Must be removed by mechanical sanding before ANY covering; adhesives will not bond through it.
- Moisture — cement screed — must be below 75% relative humidity (BS 8203) or 2% CM (calcium carbide) before covering. As a rule of thumb: 1 day per mm of thickness under good drying conditions.
- Moisture — anhydrite screed — must be below 75% RH or 0.5% CM before covering. Anhydrite is more moisture-sensitive: residual moisture reacts with cement-based adhesives, forming ettringite and destroying the bond.
- Underfloor heating drying — commissioning heat cycle is a way to accelerate drying but must be programmed properly. Cement: turn on at day 21, ramp 5°C/day to 45°C max, hold 3 days, ramp back down. Anhydrite: commission from day 7 per manufacturer schedule.
- Reinforcement — polypropylene fibres at 0.6–1kg/m³ in the mix reduce plastic shrinkage cracking. A197 mesh is unnecessary in domestic floors <100mm.
- Movement joints — required at doorways, at changes in bay width, and in bays >40m² for cement (>1000m² for anhydrite).
- Contamination — do not mix salt-contaminated sand, seawater or admixtures without checking compatibility. Chloride content limits are set by BS 8204.
Quick Reference Table
Spending too long on quotes? squote turns a 2-minute voice recording into a professional quote.
Try squote free →| Screed Type | Depth | Foot Traffic | Foot-Load OK | Tile-Ready |
|---|---|---|---|---|
| Cement (bonded, 25mm) | 25 min | 24 hr | 3 days | 21–28 days |
| Cement (unbonded, 65mm) | 65 min | 24 hr | 7 days | 28+ days |
| Cement (floating, 75mm over insulation) | 75 min | 24 hr | 7 days | 28–35 days |
| Cement (over UFH, 65–75mm) | 65 above pipe | 24 hr | 7 days | 28 days min + heating cycle |
| Anhydrite (40–50mm) | 40 min | 24–48 hr | 7 days | 40+ days with sanding |
| Anhydrite (75mm over UFH) | 75 above pipe | 48 hr | 7 days | 60+ days with heating |
| Mix Reference (cement:sand by volume) | Application |
|---|---|
| 1:3 sharp sand (with polypropylene fibres) | Domestic, standard load |
| 1:4 sharp sand | Domestic light-load only |
| 1:3.5 with rapid cement | Fast-track domestic |
| 1:4:1 (cement:sand:crushed 6mm) | Industrial / heavy-load |
Detailed Guidance
Preparation before screeding
- Substrate check — concrete slab must be sound, clean and free of laitance, dust, oil or debris. Sweep, vac, prime.
- Bond coat (bonded screed) — SBR/water/cement slurry brush-scrubbed into wet substrate immediately before screed placement. For anhydrite, use manufacturer's primer.
- DPM (unbonded screed) — 1200g polythene sheet, joints lapped 100mm and taped. Turn up walls 100mm; trim after screed set.
- Insulation (floating screed) — 100mm PIR or EPS to Part L. Turn up around perimeter with edge foam expansion strip (10mm min).
- UFH pipe fixing — clip to insulation or staple to insulation with 15mm cover minimum around pipe (60mm cover above crown recommended for cement, 65mm above crown for anhydrite).
- Perimeter isolation — always fit 10mm compressible edge strip at all walls and vertical fixings. Screeds move as they cure; unrestrained movement means no cracking.
Mixing a sand-and-cement screed
Never batch by weight of sand — sand batches by volume with allowance for bulking (moisture content adds ~25% to loose volume). A good rule:
- 1 part OPC (Ordnance Portland Cement)
- 3 parts sharp sand (BS 882 medium grade)
- Water: START at 0.4:1 water:cement ratio. Add sparingly. The mix should be "damp earth" — squeeze a handful and it just holds shape without free water.
- Polypropylene fibres 0.9kg per m³ of screed volume — mix dry, then add water.
Over-wet mix is the number-one cause of cracked/soft screeds. If your screeder is pouring wet-looking mixes to make finishing easier, expect cracks and dust when it cures.
Laying and finishing
- Datum levels — screed to laser or dot-and-dab levels, set to finished floor level minus tile + adhesive (usually 15–20mm).
- Bay layout — for cement, screed in bays or continuously. Free movement joints at doorways.
- Compaction — screed must be compacted with a straight-edge rocked side-to-side and forward. Air pockets = weak zones.
- Finish — wood float initially, then closed with a steel trowel or power float. Do not over-trowel — this brings fines/laitance to the surface.
- Curing — cover with 1000g polythene as soon as the surface will not mark. Overlap joints, tape or weigh down edges. Leave for 7 days minimum for cement.
Anhydrite / liquid screed process
Anhydrite is different in three critical ways:
- Self-levelling — poured through a pump, spread with dappling bars only. No trowelling. Levels to within 2mm across 2m.
- Fast strength gain — 24-hour walkable, 48-hour light load, 7-day full load. Reduces programme by weeks.
- Laitance formation — a 2–5mm thick chalky calcium-sulphate skin. This layer is porous, weak, and blocks adhesive bonding.
Laitance removal is non-negotiable:
- Sand at 7–10 days — mechanical floor sander with 40–60 grit paper. Vacuum thoroughly.
- Prime — manufacturer-approved primer (usually a two-part epoxy or specific latex primer for anhydrite).
- Adhesive compatibility — must use a calcium-sulphate compatible adhesive (F ball F46 or similar). Standard C2 cement adhesive on anhydrite = bond failure within weeks.
Skipping laitance removal or using the wrong adhesive is the #1 reason tiled anhydrite floors fail. Document the sanding step with photos before laying.
Moisture testing — critical, always
Both screeds MUST be tested before covering. Never rely on time alone — a "42-day-old" screed in a damp new build can still be 4% moisture, well above spec.
Methods (BS 8203):
- Hygrometer (75% RH limit) — insulated box sealed to floor for minimum 4 hours (24 hours preferred). Reads relative humidity at the floor surface.
- Calcium carbide (CM) meter — sample extracted, reacted with carbide, reads pressure of acetylene gas. 2% max for cement, 0.5% max for anhydrite.
- Handheld capacitance meter — indicative only. Cannot be used for compliance. Useful for spot checks during drying.
- Sleeve test (BS 8203) — 500mm × 500mm rubber mat weighted to floor, left 24 hours. Condensation underneath = still wet. Rough qualitative check only.
Document every reading with location, date and reading. If a floor covering later fails, the moisture record proves you did your part.
Drying conditions
Screed dries at approximately 1mm per day under ideal conditions:
- 20°C ambient temperature
- 50–65% relative humidity
- Gentle ventilation (not draughts)
- No standing water, no covering
Under UK winter conditions in a new build with wet trades still working, drying rate can drop to 0.3mm/day. A 65mm screed can take 6 months to dry naturally in poor conditions.
Force-drying methods:
- Portable dehumidifiers — remove ~10L/day from a 30m² room. Effective for cement AND anhydrite.
- UFH commissioning cycle — ramp heating up 5°C/day from 20°C to 45°C, hold 3 days, ramp down. Reduces drying time by 40–60%.
- Space heating + ventilation — extract vents, warm supply air. Faster than heat alone.
Never force-dry cement screed before day 21 — sudden drying causes plastic shrinkage cracks. Anhydrite can be commissioned earlier per manufacturer.
Cracks and defects
- Plastic shrinkage cracks (0–24 hrs) — surface cracking during curing. Cause: too dry a mix / drying too fast / no polythene. Cosmetic only if minor; structural if wide.
- Drying shrinkage cracks (weeks 1–4) — random cracking, usually at re-entrant corners or over pipe runs. Movement joints prevent most.
- Curling — edges lift due to differential drying (top dries first, contracts, curls up). Common on unbonded screeds without adequate curing. Bond breaker helps.
- Delamination — bonded screed lifts from substrate. Cause: dirty substrate, laitance on slab, poor slurry bond. Sound-test with a hammer at 500mm centres — hollow patches = delaminated.
- Powdering / dusting — surface too weak. Cause: over-wet mix, over-trowelling bringing fines up, walking on green screed. Prime and seal, or lift and re-lay.
When to insist on lift-and-relay
If any of these:
- Screed fails BS 8204 in-service crushing strength (cored sample <30 N/mm² Group A)
- Delamination >25% of area
- Moisture stubbornly above spec after 60 days force-drying (usually indicates buried moisture source)
Do not tile onto a suspect screed. The re-lay cost is £30–£60/m²; a bond failure claim on a large tiled area can be 10× that.
Frequently Asked Questions
Can I tile onto a screed at 21 days?
Only if you've measured the moisture and it's below spec, AND you're using a fast-set adhesive system. Standard practice is 28 days minimum for cement screed at 65mm. Rushing this is the #1 cause of tile bond failure in domestic work.
What if the UFH pipes have <60mm cover above them?
Below the recommended cover, thermal cycling stress on the screed can crack it above the pipes. If cover is 40–50mm, use a reinforced anhydrite mix or add a fibre-reinforced cement mix. Below 40mm, redesign the buildup.
Do I always need to prime before tiling?
Yes, on anhydrite absolutely (compatibility). On cement screeds, primer improves adhesion and reduces adhesive water-loss into the substrate. Skip it and adhesive can dry too fast, causing hollow spots.
Can I use ready-bagged floor levelling compound as a screed?
Only as a topping over an existing sound screed, typically 3–20mm depth. Levelling compounds are not screeds — they are thin bond-coats or top-outs. Not structural, not for depths beyond product spec.
The customer wants to lay tiles tomorrow — what do I say?
If the screed was poured today, no. If yesterday, no. If a week ago, still no. The customer's programme urgency does not change the physical curing timeline. Explain in writing what happens if they force it, and put your name to a proper timeline. That's your protection.
Why does anhydrite fail with cement adhesive?
Anhydrite is calcium sulphate. Cement-based adhesive contains portland cement which reacts with residual calcium sulphate + moisture to form ettringite, an expansive crystal that destroys the bond over weeks or months. Use calcium-sulphate compatible adhesives (F ball F46, Mapei Ultralite Flex, etc.) on anhydrite substrates.
Regulations & Standards
BS 8204-1:2003+A2:2011 — Screeds, bases and in situ floorings — Concrete bases and cementitious levelling screeds to receive floorings. Sets thickness, strength, mix requirements.
BS 8204-7:2003 — Screeds, bases and in situ floorings — Pumpable self-smoothing screeds — Code of practice. Covers anhydrite systems.
BS 8203:2017 — Code of practice for installation of resilient floor coverings. Sets moisture test methods and limits.
BS EN 13813:2002 — Screed material and floor screeds — Specification for screed materials.
BS EN 1264-4:2009 — Water-based surface embedded heating and cooling systems — Installation. Governs UFH-screed detailing.
Approved Document Part L — thermal requirements affecting floor buildup and insulation.
BS 8204-1 — Screeds and cementitious levelling — British Standards Institution
Cemex screed technical guide — commercial guidance
Gyvlon (anhydrite) technical library — manufacturer's data on liquid screeds
Tile Association pre-installation guidance — sector body on moisture and adhesive
F ball adhesives — anhydrite compatibility — technical bulletins
screed types — screed material comparison, when to choose each type
screed depth — minimum thickness calculator by system type
underfloor heating — wet UFH pipe spacing and screed integration
underfloor heating tiles — tiling over UFH, flexible adhesive selection
adhesive selection — adhesive class C2/S1/S2 by substrate
cement sand ratios — mix ratios cross-reference