Summary

Fitting uPVC windows is one of the highest-volume jobs in UK domestic work and one of the easiest to do badly. A window that is a few millimetres out of square sticks, leaks and drops its sash within a year. A window with no packers under the glazing bridges carries its own weight on the sealant. A window fitted without a lintel check can bring the outer leaf down on the installer. The product itself is forgiving; the survey, the packing and the sealing are where the job is won or lost.

This guide covers the full sequence for a replacement casement window in a cavity-wall house: survey and measurement, removing the old frame, preparing the reveal, fitting the sill, fixing and packing, glazing and toe-and-heeling, sealing, and the regulatory sign-off. It applies to tilt-and-turn and flush-sash uPVC with minor differences and to new-build openings with the obvious change that there is no old frame to remove. Box sash replacement and timber are covered elsewhere. For prices see window replacement pricing guide; this article is about doing the job.

The common misconception is that a window is "fitted" when it is foamed in. It is fitted when it is mechanically fixed, correctly packed so the frame cannot bow, square enough that the sash closes evenly on every side, and sealed so that water running down the face of the wall has a path out that does not go behind the frame. Foam is a draught seal and a thermal filler, never a fixing.

Key Facts

Quick Reference Table

Spending too long on quotes? squote turns a 2-minute voice recording into a professional quote.

Try squote free →
Stage What the standard or regulation says Practical figure
Survey width Smallest of three brick-to-brick measurements minus clearance Minus 10 mm
Survey height Smallest of three measurements, sill to lintel, minus clearance and sill Minus 10 mm plus sill height
Fixing from corner BS 8213-4:2016 150 mm
Fixing centres BS 8213-4:2016 600 mm maximum
Masonry embedment Fixing manufacturer 40 mm minimum
Frame clearance Installer practice 5 mm each side
Whole-window U-value Approved Document L Vol 1 (2021) 1.4 W/m²K or WER band B
Trickle vent, habitable room Approved Document F Vol 1 (2021) 8,000 mm² equivalent area
Trickle vent, wet room Approved Document F Vol 1 (2021) 4,000 mm² equivalent area
Safety glass in windows Approved Document K Below 800 mm from floor
Escape window opening Approved Document B Vol 1 0.33 m², 450 × 450 mm minimum
Escape window sill height Approved Document B Vol 1 800–1,100 mm above floor
Foam type Installer practice Low-expansion window foam
External sealant BS EN ISO 11600 Neutral-cure silicone, F-25-LM
Labour per opening Market (2026) £200–£350

Detailed Guidance

Survey: measuring the opening

Measure from the outside, brick-to-brick, with the old frame still in. Take the width at the top, middle and bottom of the opening and the height at the left, centre and right. Record all six; the smallest in each direction is the working size. Deduct 10 mm from the width and 10 mm from the height for clearance, then deduct the sill height from the height if a stub sill is being used, because the sill sits on the masonry and the frame sits on the sill.

Check the opening for square by measuring the two diagonals. If they differ by more than 10 mm on a standard window, note it and decide whether to order a slightly smaller frame and make up the difference with packers and trims, or whether the reveal needs making good first. A frame forced into an out-of-square opening will never close properly.

Measure the depth of the reveal from the outer face of the brick to the internal plaster line, and note where the old frame sits. The new frame should sit behind the outer leaf by around 30–50 mm so the brick reveal covers the cavity and the frame edge. If the existing frame is set further back or further forward, decide where the new frame will sit before ordering sill projection and add-ons.

Look up. Is there a lintel? A concrete or steel lintel over the outer leaf will be visible once the render or soldier course is examined, or can be detected with a stud detector or a careful tap. On houses built before about 1930, a brick arch or a soldier course over the window usually has no lintel behind it and the timber frame has been carrying the outer leaf for a century. If there is no lintel, the job needs one fitted before the old frame comes out (a catnic-type lintel or a helical bar system, priced separately), or at minimum the arch needs propping while the frame is swapped. Do not discover this on fitting day.

Note the sill detail: existing stone sub-sill, tile sill or nothing. Check the height from the top of the sub-sill to the DPC and whether the sub-sill projects enough to throw water clear. Note trickle vent sizes on the existing frame, the glass type in each pane, whether the room is a first-floor bedroom (escape window) and whether any pane falls in a critical location under Approved Document K.

Ordering

Order the frame at the working size. Specify the sill (stub sill 85 mm or 150 mm, or none where a sub-sill will take the frame directly), the sill end caps, the add-ons for reveal depth, trickle vents sized to Approved Document F, the glass specification pane by pane (toughened where required, obscure in bathrooms, laminated where asked), the opening configuration with escape hinges where needed, and the colour or foil on each face. Confirm the sealed units are to BS EN 1279 and that the U-value or WER certificate for the whole window meets the 1.4 W/m²K limit; most manufacturers supply a certificate per order for FENSA or CERTASS purposes.

Removing the old frame

Take the opening sashes off first, then the fixed glass. For a timber frame, cut through the sill and the head with a reciprocating saw, then cut each jamb in the middle and lever the pieces in towards the room. For an old uPVC or aluminium frame, find and remove the fixings, cut the frame in the same way and prise it out. Work from inside so debris falls into the house onto dust sheets rather than onto the pavement.

Clean the reveal back to sound masonry. Remove old foam, mastic, loose render and the nails from a timber sub-frame. Check the reveal again for square and for the sub-sill level. Repair any damaged brick reveal before fitting; a frame cannot be sealed to crumbling brick.

Fitting the sill

Cut the stub sill to the opening width less 5 mm, fit the end caps with a bead of silicone, and bed the sill on two continuous beads of neutral-cure silicone along the sub-sill. Level it along its length and check it falls slightly outwards, never inwards. Pack under the sill where the sub-sill is uneven so the frame weight does not bear on the silicone alone. Where the sill is fixed with screws, keep them out of the drainage channel. Some installers fix the sill through its upstand into the frame after assembly; either way the frame sits in the sill upstand with a bead of silicone between them.

Offering up, packing and fixing

Lift the frame into the opening with the glass out. Stand it on the sill, centre it so the clearance is equal each side, and plumb the jambs with a long level. Pack at the bottom corners first so the frame is sitting level, then at the head corners so it is held, and check the diagonals; the frame diagonals must match to within 2 mm.

Drill through the frame at the fixing positions: 150 mm from each corner, 150 mm each side of every mullion and transom, then at 600 mm centres or closer in between. Put a packer behind the frame at every fixing position before driving the screw, so the screw pulls the frame against the packer and not into a bow. Drive the fixing until it is snug, never tight enough to distort the profile; a bowed jamb is the single most common cause of a sash that will not lock.

Check the frame for square and plumb after each pair of fixings. On larger frames fix the sill jambs first, then the head, then the mid-height fixings. Fit the opening sashes before the final tightening so that the clearance around each sash can be checked and adjusted while the frame can still move.

Glazing and toe-and-heeling

Set the glazing bridges in the rebate on the sill and the hinge jamb. For a fixed pane, place packers on the bridges at the bottom corners and at the top corners so the unit is held square and cannot touch the frame. For an opening sash, toe-and-heel: pack at the bottom corner on the hinge side and at the top corner on the lock side, so the sealed unit braces the sash diagonally and the weight runs through the hinge. A sash that has not been toe-and-heeled drops at the lock side within months and the handle starts catching on the keep.

Push the unit home, fit the glazing beads short sides first then long sides, and tap home with a nylon mallet. Never lever a bead with a steel tool against the glass edge.

Sealing

Internally, fill the clearance gap with low-expansion window foam from a gun, in a continuous bead, filling the depth of the frame but not the full reveal; trim flush once cured. Externally, where the frame meets masonry, apply a neutral-cure silicone to BS EN ISO 11600 in a bead large enough to bridge the gap with adhesion to both faces, then tool it to a concave finish. On rough brick or where the gap exceeds about 8 mm, use a uPVC trim bedded in silicone and seal the trim edges. Seal the sill end caps to the brick and the sill-to-frame joint. Internally, finish the reveal with plaster or trim and seal the frame-to-plaster joint with a decorator's caulk or silicone depending on the finish.

The external seal must leave the sill drainage channel and any frame weep slots clear. Foam or silicone blocking the drain holes puts the condensation drain inside the frame and the water ends up on the inside sill.

Hardware, vents and handover

Adjust the hinges and keeps so the sash closes evenly with the same compression on all four sides. Fit the trickle vent covers, the handle and any restrictors ordered. Test every opener and every lock. Check the escape window opens to its full extent where one was specified.

Register the installation with FENSA or CERTASS within the scheme's time limit so the customer receives the Building Regulations compliance certificate, or arrange the Building Control inspection where a building notice was used. Give the customer the glass certificates, the manufacturer's guarantee and the care instructions. An insurance-backed guarantee is a condition of both competent-person schemes for the installer's own guarantee.

Frequently Asked Questions

Can a replacement window be fitted without trickle vents?

Only when the window being replaced had none and the room has another compliant means of background ventilation, or when Building Control accepts the ventilation strategy. Approved Document F Volume 1 (2021) says a replacement window must have background ventilators no smaller than the ones it replaces, and that where the old window had none the new one should have them, at 8,000 mm² equivalent area for a habitable room and 4,000 mm² for a kitchen, bathroom or utility room. Fitting without vents to keep a frame looking clean is the usual route to condensation complaints and a failed FENSA audit.

How much smaller than the opening should the frame be?

10 mm in each direction is the standard deduction: 5 mm clearance on each side and at the top and bottom, with the sill height deducted separately where a stub sill is used. Less than 5 mm per side leaves no room to pack and plumb; more than about 7 mm per side means the foam bead is too wide to hold the frame and the external trim becomes obtrusive. If the opening is badly out of square, order to the smallest clear dimension and make up the difference with trims rather than ordering oversize and attacking the reveal.

Does fitting a window need Building Control approval?

Yes. Replacement windows and external doors have been controlled fittings under the Building Regulations since April 2002. The work must either be self-certified by an installer registered with a competent-person scheme (FENSA, CERTASS or another approved scheme for windows and doors) or notified to the local authority with a building notice before work starts. The customer needs the certificate when the house is sold; a missing certificate is a standard enquiry on the TA6 property information form.

What glass is needed in a window next to a door?

Approved Document K treats glazing within 300 mm of either side of a door and below 1,500 mm from floor level as a critical location, the same as the door itself. The pane must be toughened or laminated to BS EN 12600 class 1 or 2 (or the older BS 6206 class A or B), or be small enough to fall under the small-pane exemption. The same applies to any window pane whose bottom edge is below 800 mm from the finished floor.

Do I need PAS 24 windows on a replacement job?

Not under the Building Regulations. Approved Document Q (security) applies to new dwellings and to buildings converted to dwellings, so a straight replacement does not have to meet PAS 24:2022. Most mainstream uPVC systems are PAS 24 tested as standard, and specifying it costs little, so there is no reason to fit untested frames on an accessible ground-floor window.

Regulations & Standards