House Extension Build Process: Planning Timeline, Building Notice vs Full Plans, CDM Duties and Construction Sequence

Quick Answer: A typical single-storey rear extension takes 3–6 months from planning application to completion. Most extensions ≤4m (detached) or ≤3m (semi/terraced) are permitted development. The build sequence is: strip out → foundations → drainage → slab → blockwork/frame → roof → first fix → plaster → second fix → decoration. Building Control must inspect at foundations, damp proof course, floor slab, and completion.

Summary

For most tradespeople, a house extension is either the entire job (if you're a main contractor or builder) or one phase of it. Understanding the full process helps you sequence your own trade correctly, anticipate delays, and give clients realistic timelines.

The biggest timeline killers are: waiting for planning (8–10 weeks), party wall disputes (if semi-detached or terraced), structural calculations delays, and material procurement (steel beams, windows). Extensions that start without confirming structural beam sizes are particularly prone to delay — the steelwork cannot be ordered until the structural engineer issues their calculations.

CDM 2015 applies to all construction work in domestic settings. For single-site, single-client domestic projects, the domestic client duty holder responsibilities are simpler than commercial, but the Principal Designer and Principal Contractor duties still exist where there is more than one contractor.

Key Facts

Quick Reference Table

Spending too long on quotes? squote turns a 2-minute voice recording into a professional quote.

Try squote free →
Route When to Use Timeline
Permitted Development Single/rear extension within PD limits Start after Building Regs (no planning wait)
Prior Approval Larger extensions (4–8m/3–6m) 42-day decision period
Full Planning Application Large, sensitive, restricted areas 8–10 weeks decision; 6 weeks for householder
Conservation Area/Listed Building Any extension in restricted area Full planning + Listed Building Consent if listed
Build Stage Timing Inspection Required?
Strip out Day 1–3 No
Excavate foundations Week 1 LABC: inspect before concrete
Pour concrete foundations Week 1–2 After inspection
Drainage first fix Week 2 LABC: drainage test
Oversite/slab Week 2–3 LABC: before slab pour
DPC Week 3 LABC: before backfilling
Blockwork/brick walls Week 3–6 No (unless cavity issues)
Roof structure Week 5–8 No
Roof covering Week 6–9 No
Window/door installation Week 7–10 No
First fix (M&E) Week 8–11
Plaster Week 10–14 No
Second fix Week 12–16
Decoration Week 14–18
LABC final inspection Week 16–20 Yes

Detailed Guidance

Planning Stage

Step 1: Determine PD eligibility

Step 2: Submit if required

Step 3: Party Wall Act

Design and Structural Engineering

Before building starts, ensure:

Avoid the common delay: Order steel beams before work starts. Lead time for structural steelwork: typically 4–6 weeks. Many extensions have stood as completed blockwork waiting for a beam.

Building Control Route: Full Plans vs Building Notice

Full Plans:

Building Notice:

CDM 2015 for Domestic Extensions

Most single domestic extensions are CDM notifiable only if they exceed 500 person-days or have >20 workers for >30 days. For smaller projects:

Construction Sequence

Week 1–2: Groundworks

  1. Mark out extension footprint with pegs and lines
  2. Excavate topsoil; store separately for reinstatement
  3. Excavate foundation trenches (depth per structural engineer — minimum 450mm in clay soil, typically 600–900mm)
  4. Lay drainage runs (set falls before backfilling)
  5. LABC inspection of foundation excavations
  6. Pour strip foundations or trench-fill concrete to within 150mm of DPC level
  7. Complete drainage connection to existing system; LABC drainage inspection

Week 2–4: Masonry

  1. Build up cavity walls or solid walls to DPC level
  2. LABC DPC inspection
  3. Install floor insulation and DPM
  4. LABC slab inspection; pour concrete slab
  5. Build walls to window/door head height
  6. Install lintels; insert window/door frames (or boxes if windows ordered separately)
  7. Build walls to full height; install cavity wall ties at 900mm horizontal, 450mm vertical

Week 4–8: Roof

  1. Install structural roof members (rafters, ceiling joists, or engineered trusses)
  2. Fix sheathing/sarking boards or batten as per roof system
  3. Install breathable underlay; batten and counter-batten
  4. Fix tile/slate covering; fix ridge tiles (or dry-fix system)
  5. Install flashings at abutment walls and any valley

Week 6–10: Windows, Doors, External Finish

  1. Install windows and external doors in prepared openings
  2. Internal: install steel beam where existing house opens to extension (LABC may inspect padstones and beam bearing)
  3. External: render, point, or clad as per design
  4. Make good cavity walls and ties at opening to existing house

Week 8–14: First Fix and Finishes

  1. Electrician: first fix (cable routes, back boxes)
  2. Plumber: first fix (water, heating pipework)
  3. Screeding or floor preparation
  4. Plasterboard and skim

Week 12–18: Second Fix and Completion

  1. Electrician: second fix (sockets, switches, consumer unit)
  2. Plumber: second fix (sanitary ware, rad valves, boiler changes if needed)
  3. Decorator: painting and decorating
  4. Kitchen/joinery: fit skirting, architrave, kitchen if applicable
  5. LABC final inspection (all trades complete)
  6. EIC, Gas Safe certificate, FENSA certificate as applicable

Frequently Asked Questions

How long does a single-storey extension take to build?

A straightforward single-storey rear kitchen extension (20–25m²) typically takes 10–14 weeks on site from groundworks to completion. Add 8–10 weeks for full planning, plus time for engineering and material procurement. Total project timeline from instruction to key in door: 6–9 months.

Do I need an architect for a simple extension?

Not legally. Building Regulations require drawings showing structural design, insulation, drainage and fire safety, but these can be produced by a building technician, structural engineer, or competent builder. An architect adds design value on complex or visually prominent projects; a technician is more cost-effective for straightforward rear extensions.

What inspections does LABC carry out?

LABC typically inspects at: foundation excavations (before concrete); DPC (before backfilling); ground floor (before slab pour); drainage (water test before backfilling); structural beam installation (if required); and final inspection (when complete). Some LABC offices also inspect at roof-level on larger projects.

Regulations & Standards