Summary
Time-of-use tariffs are not new — Economy 7 and Economy 10 have existed for decades, switching a dedicated circuit (traditionally storage heaters and immersion heaters) onto a cheaper overnight rate via a physical time switch or a signal from the meter. What's changed is the sophistication and the stakes. Dynamic tariffs such as Octopus Agile change the unit price every half hour based on wholesale market conditions, sometimes swinging significantly within a single day, and modern time-of-use tariffs are increasingly paired with high-power domestic loads that didn't exist when Economy 7 was designed: EV chargers drawing up to 7kW or more, heat pumps running for extended periods, home battery storage systems charging and discharging on a schedule, and immersion heaters being digitally diverted rather than simply timed.
For an electrician, this matters at three points: first, whether the property's smart meter can actually support the tariff the customer wants (a genuine prerequisite, not a formality); second, whether the appliance being installed has the right control hardware to actually respond to the tariff's price signal, whether that's a manufacturer API/app schedule or a physical relay; and third, whether the cumulative effect of several load-shifted appliances switching on together at a rate changeover creates a loading condition the original circuit design and diversity assumptions didn't anticipate. None of this replaces the fundamentals of BS 7671 — a circuit is still sized, protected, and isolated the same way regardless of what triggers it to switch — but it does add a design conversation that wasn't previously part of a standard consumer unit or circuit installation.
The most common failure mode reported anecdotally by installers is not a wiring fault at all, but a mismatch between customer expectation and hardware capability: a customer signs up to a dynamic tariff expecting their immersion heater or older storage heaters to automatically shift to the cheapest half-hour, when the actual installed hardware is a simple mechanical timer with no ability to respond to a variable digital price signal. Managing this expectation — and specifying the right control hardware where load-shifting is genuinely wanted — is as much a part of the job as the wiring itself.
Key Facts
- SMETS2 smart meters — dynamic and genuinely time-varying tariffs depend on a smart meter capable of reporting half-hourly (or more granular) consumption data back to the supplier; older SMETS1 meters, or a property with no smart meter at all, generally cannot support a genuinely dynamic tariff, and the customer may need a meter exchange arranged through their supplier before any wiring work is worthwhile
- Smart Meters Act 2018 — the UK statutory basis for the national smart meter rollout programme; relevant background context for why meter capability varies by installation date and supplier, though it does not itself prescribe electrical installation detail
- Legacy Economy 7/10 switching — traditionally implemented via a dedicated "white meter" with an internal or radio teleswitch signal controlling a contactor that switches specific circuits (immersion heater, storage heaters) onto the off-peak period automatically, entirely independent of any app or internet connection
- Modern dynamic tariff load-shifting is usually appliance-side, not meter-side — unlike Economy 7's meter-controlled contactor, most current dynamic tariff integrations (e.g. EV charger scheduling via a manufacturer or tariff-provider app) control the appliance directly over its own internet/API connection, with the meter providing consumption data back to the supplier rather than switching anything itself
- "Dumb" loads still need a relay/contactor for load-shifting — an appliance with no native scheduling intelligence (a standard immersion heater is the clearest example) cannot respond to a dynamic price signal on its own; retrofitting genuine load-shifting to it requires either an app-controlled relay/contactor (e.g. a smart plug-in or hardwired relay rated for the load) or a PV/tariff diverter device, correctly specified for the circuit's current and switching duty
- EV charger native tariff integration — many current EV chargers and some tariff providers offer built-in scheduling that charges during the tariff's cheapest identified window automatically; this is a charger/software feature, not something the electrician configures at circuit level, but the circuit must still be installed to the same BS 7671 Section 722 standard regardless of whether smart scheduling is used
- Heat pump and battery storage scheduling — heat pump controllers and battery storage inverters increasingly offer tariff-aware scheduling as a manufacturer software feature; verify with the manufacturer's current documentation whether the specific model and firmware genuinely support the customer's chosen tariff/provider before promising this functionality
- Diversity assumptions and peak coincidence — BS 7671's guidance on diversity (assessing the likely maximum demand of a group of circuits, rather than assuming every circuit draws its full rated current simultaneously) is based on typical, largely random patterns of appliance use; deliberately time-shifting several high-power loads onto the same cheap-rate window (for example, several neighbouring or same-property loads all starting at a tariff's off-peak changeover time) increases the statistical likelihood of genuine coincident peak demand, which the traditional diversity assumption was never designed to represent
- Property-level main switch/tails rating — a property that has added an EV charger, an immersion diverter, and a heat pump over time, each individually assessed as acceptable against the main supply rating using standard diversity, may still be at risk of nuisance tripping or overload at the exact moment several of these deliberately fire together at a rate changeover; a full load assessment considering coincident time-shifted demand, not just each addition in isolation, is good practice when multiple load-shifting devices are present on one supply
- Network-level (DNO) coincidence risk — beyond the individual property, if many homes on the same local low-voltage network are on the same or similar tariffs and shift load to the same cheap-rate window, this creates a documented industry concern for local network loading; this is primarily a DNO/network planning consideration rather than something an individual circuit installation can mitigate, but it's useful context when advising customers or specifying load management/staggered scheduling where available
- Remote/automatic switching and BS 7671 isolation requirements — a circuit that can be switched on remotely or automatically (by a relay responding to a tariff signal, a smart meter signal, or an app command) must still provide a reliable means of isolation for maintenance and emergency purposes that does not depend on the remote system; safe isolation procedure must account for the possibility that a circuit believed to be switched off could be remotely re-energised, and appropriate warning labelling at the isolation point is good practice — the precise BS 7671 regulation number for warning notices on remotely/automatically switched circuits, as this should be confirmed against the current edition before citing on a certificate
- Contactor and relay rating for switching duty — a contactor or relay used to implement legacy-style or retrofit load-shifting switching must be rated not just for the connected load's current, but for the switching duty cycle involved — a device switching on and off potentially several times a day (following a dynamic half-hourly tariff, rather than a single overnight on/off cycle) sees materially more switching operations over its service life than a traditional Economy 7 contactor switching twice a day, and should be specified accordingly
Quick Reference Table
Quoting an electrical job? Describe the work and squote handles the pricing.
Try squote free →| Scenario | What the electrician needs to check | Typical control method |
|---|---|---|
| Customer wants EV charger scheduled to cheapest tariff window | Charger's native scheduling/tariff integration support; SMETS2 meter present | Charger app/API, no additional relay needed |
| Customer wants immersion heater load-shifted onto cheap-rate periods | No native intelligence in a standard immersion element; needs added control hardware | App-controlled relay/contactor or PV/tariff diverter device |
| Legacy Economy 7 storage heaters being retained on a new dynamic-style tariff | Confirm whether the tariff still supports simple time-block switching or requires appliance-side intelligence the storage heaters don't have | Existing meter-controlled contactor, if tariff structure is compatible |
| Battery storage system to charge/discharge on tariff schedule | Manufacturer/firmware support for the specific tariff provider's API or a generic time-of-use schedule | Inverter's own scheduling software |
| Heat pump to run preferentially in cheap-rate windows | Heat pump controller's tariff-aware scheduling support; may conflict with weather compensation/comfort settings if forced into rigid windows | Heat pump manufacturer controller software |
| Multiple load-shifted appliances on one property (EV + immersion + heat pump) | Coincident peak demand risk if all scheduled to the same changeover time; review main tails/supply rating against realistic coincident load | Staggered scheduling where possible, or load management hardware |
| Property has no smart meter, or an older SMETS1 meter | Dynamic/genuinely time-varying tariffs generally require SMETS2; advise customer to arrange a meter exchange with their supplier first | N/A — meter exchange, not an electrical installation task |
| Retrofitting a relay to an existing "dumb" appliance for load-shifting | Relay/contactor current rating and switching duty cycle suitability for frequent (multiple times daily) switching, not just occasional overnight switching | Hardwired relay/contactor rated for the duty |
Detailed Guidance
Establishing whether the property can actually support the tariff being discussed
Before any wiring conversation, confirm the property has a working SMETS2 smart meter reporting correctly to the supplier — genuinely dynamic, half-hourly tariffs are built around this data flow, and a property without it, or with an older SMETS1 meter that hasn't been migrated, generally cannot take a dynamic tariff regardless of what electrical work is carried out. This is a supplier/meter-operator matter, not something the installing electrician resolves, but flagging it early avoids specifying load-shifting control hardware for a tariff the property can't actually access yet.
Legacy Economy 7/10 contactor switching vs modern app/API load-shifting
Traditional Economy 7 and Economy 10 circuits are switched by a contactor responding to a signal generated by the meter itself (historically via an internal time switch, or a radio teleswitch signal from the network operator) — entirely independent of the internet, the customer's phone, or any third-party app. This is simple, robust, and asks nothing of the electrician beyond correctly specifying and wiring the contactor and the switched circuits.
Modern dynamic tariff load-shifting generally works differently: the appliance itself (an EV charger, a smart plug, a heat pump controller, a battery inverter) connects to the internet and either polls the tariff provider's published price data or receives a schedule from an app, then switches or throttles itself accordingly. The meter's role in this model is largely limited to reporting consumption back to the supplier for billing, not controlling anything on site. This is an important distinction to explain to customers who assume a new dynamic tariff will automatically make their existing "dumb" appliances load-shift — it won't, unless that appliance (or an added relay/diverter) has its own means of responding to the tariff.
Specifying control hardware for "dumb" loads that need to load-shift
A standard immersion heater element has no intelligence of its own — it's either powered or not, controlled by whatever switch or timer feeds it. To genuinely load-shift an immersion heater onto a dynamic tariff's cheapest windows (as opposed to a fixed Economy 7-style overnight block), the circuit needs either an app/API-controlled relay or smart contactor capable of receiving a schedule from the tariff provider or a third-party scheduling service, or a solar/tariff diverter device designed for this purpose. Specify the relay or contactor for both the connected load's current rating and, importantly, the increased switching duty cycle implied by a half-hourly-variable tariff — a component designed for two switching operations a day (traditional Economy 7) will see meaningfully more wear if used to chase a genuinely dynamic half-hourly price signal with frequent on/off cycling.
Diversity and peak coincidence with deliberately time-shifted loads
Standard diversity calculations in domestic electrical design assume loads switch on and off according to largely independent, everyday patterns of use — the statistical likelihood of every circuit in a property drawing its full rated current at the same moment is treated as low, which is why consumer units and supply tails are not sized for the sum of every circuit's maximum rating. Deliberate load-shifting onto a shared cheap-rate window undermines part of that assumption: if an EV charger, an immersion diverter, and a heat pump are all scheduled (independently, by their own manufacturer software, with no coordination between them) to start at the same tariff changeover time, the property can see a genuine coincident peak that a traditional diversity assessment wouldn't have anticipated for that combination of loads. This is worth an explicit conversation with the customer and, where multiple significant loads are being added over time, a fresh look at the property's main supply rating and tails sizing rather than assessing each addition purely in isolation. Where available, staggering schedules (even by 15-30 minutes between appliances) or using a load management/monitoring device that can throttle or sequence multiple loads is a practical mitigation that doesn't require a supply upgrade.
Remote and automatic switching — isolation and labelling
Any circuit that can be switched on by something other than a person standing at the switch — a relay responding to a tariff signal, a smart meter, or a remote app command — introduces a safe isolation consideration that a purely manually-switched circuit doesn't have: a circuit found switched off at the point of work could, in principle, be remotely re-energised during that work if the isolation point relied only on the remote control mechanism rather than a genuine point of isolation. Standard safe isolation procedure (isolate at a point that removes all possibility of re-energisation, lock off, prove dead) still applies in full, and should not be substituted by simply disabling the remote schedule via an app. Clear labelling at the isolation point noting that the circuit is subject to remote/automatic switching is good practice so that anyone working on the installation in future — not just the original installer — is aware. the specific current BS 7671 regulation reference for warning notices applicable to remotely or automatically switched circuits before citing a clause number on a certificate, as wording and numbering should be checked against the edition in force at the time of the work.
Frequently Asked Questions
Does a dynamic tariff require any different consumer unit specification?
Not inherently — the consumer unit and individual circuits are still specified, protected, and isolated to the same BS 7671 requirements regardless of the tariff. What changes is the design conversation around diversity where multiple significant loads are being deliberately scheduled to run together, and the presence of any relay/contactor hardware needed to give a "dumb" appliance the ability to load-shift, which should be specified and protected like any other switched load.
Can I just tell a customer their new dynamic tariff will automatically make their immersion heater or storage heaters cheaper to run?
Only if there's control hardware in place that can actually respond to the tariff's price signal. A standard immersion heater with a basic timer, or older storage heaters on a simple charge/no-charge input, will not automatically shift to the cheapest half-hour of a genuinely dynamic tariff without added intelligence — either a compatible relay/diverter device or, for storage heaters, confirmation that the tariff still supports the simple time-block structure those heaters were designed around. Set this expectation clearly before the customer signs up to a tariff expecting automatic savings that the installed hardware can't actually deliver.
Is there a risk of nuisance tripping from load-shifted appliances all firing at once?
Yes, this is a genuine and growing consideration as more properties add EV chargers, heat pumps, and battery storage alongside existing loads, each independently scheduled by its own manufacturer software to target the same cheap-rate changeover time. Where a property has, or is adding, more than one significant time-shiftable load, it's worth reviewing the main supply/tails rating against a realistic coincident demand scenario rather than assessing each device in isolation against standard diversity assumptions designed for largely random, non-coordinated appliance use.
Do I need to notify anyone before installing a relay to enable tariff-based load-shifting on an existing circuit?
Any new circuit work or significant alteration to an existing circuit remains notifiable under Building Regulations Part P in the same way as any other domestic electrical work, regardless of the reason for the alteration. Adding a relay/contactor to an existing correctly-installed circuit for load-shifting purposes should be assessed on the same basis as any other circuit alteration — if in doubt, treat it as notifiable and certify accordingly.
Regulations & Standards
BS 7671:2018+A4:2026 (IET Wiring Regulations) — governs circuit design, protection, isolation and labelling for any circuit involved in load-shifting, regardless of how it is triggered to switch
BS 7671:2018+A4:2026, Section 722 — Electric vehicle charging installations; applies to EV chargers being scheduled under a dynamic tariff exactly as it does to any other EV charging installation
The Building Regulations 2010, Part P — Electrical safety (notifiable work); applies to new circuits or significant alterations, including added relay/contactor hardware for tariff-based load-shifting
The Smart Meters Act 2018 — statutory basis for the GB smart meter rollout; background context for SMETS2 meter availability and capability
The Electricity Safety, Quality and Continuity Regulations 2002 (ESQCR) — relevant background on supply quality and DNO obligations where network-level coincidence of time-shifted loads is a consideration
The Electric Vehicles (Smart Charge Points) Regulations 2021 — requires most new EV chargers sold/installed in Great Britain to have smart functionality including default off-peak charging behaviour, directly relevant to tariff-based EV scheduling
Ofgem — smart meters and half-hourly settlement — background on smart meter data requirements underpinning dynamic tariffs
Energy Networks Association — network impact of electrification and flexible demand — DNO-level context on coincident demand from time-shifted loads
IET — Code of Practice for Electric Vehicle Charging Equipment Installation (5th ed.) — Section 722 and load management design guidance
GOV.UK — Smart Meters Act 2018 — statutory background to the smart meter rollout
ev charger installation pricing guide — domestic EV charger installation pricing, including circuit and earthing detail relevant to tariff-scheduled charging
ev charger workplace load management pricing guide — commercial load management pricing, using the same diversity/coincidence principles at a larger scale
ev charger installation types — Section 722 technical detail for EV charging circuits
pme earthing ev charging — PEN fault protection detail relevant to any EV charger regardless of tariff or scheduling