Summary
Domestic EV charger pricing is a single-charger, single-circuit job — see ev charger installation pricing guide for that scope. Workplace and commercial multi-bay installations are a different job entirely: multiple charge points sharing one electrical supply, a DNO application process that can take weeks rather than being a same-day notification, and — critically — dynamic load management (DLM) hardware that continuously balances demand across all the bays so the site never exceeds its available supply capacity. Pricing this correctly means separating what scales per bay (the charger unit itself, its spur cabling) from what's shared infrastructure (the DLM controller, the main feeder, the DNO application, the sub-board), since shared infrastructure cost per bay drops sharply as the scheme gets bigger.
The commercial driver for load management is straightforward: without it, a site with (say) an 8-bay ambition but only headroom for 4 chargers running simultaneously at full power would either need a very expensive DNO supply upgrade, or accept that chargers randomly fail to deliver full power when several vehicles plug in at once. A DLM controller monitors real-time demand — usually via CT clamps on the incoming supply — and throttles individual charge points dynamically so the total site load never exceeds the available capacity, letting a business install more charge points than a "dumb" installation of the same supply could support.
The OZEV Workplace Charging Scheme materially changes the customer conversation on cost. It pays £350 per socket installed, up to a maximum of 40 sockets per applicant — a significant offset on a multi-bay scheme, and one that should be quoted as a net-cost reduction to the customer, not folded into your sell price. As with the domestic OZEV scheme, always check current eligibility and amounts before quoting, and note that the installer or the applicant business (not you as the electrician, typically) applies for the grant — confirm current process requirements before committing a customer to a job on the assumption the grant will land.
Key Facts
Charger and hardware costs
- Commercial 7kW AC charge point (untethered, workplace-grade) — £600-£1,000 per unit
- Commercial 22kW three-phase AC charge point — £1,200-£2,000 per unit
- Dynamic load management (DLM) controller — £800-£2,500 depending on the number of charge points it manages and whether it's a standalone unit or built into a master/slave charger network
- CT clamp set at the main incomer (for DLM monitoring) — £150-£300
- OCPP-networked master/slave charger sets — some manufacturers build load balancing into the chargers themselves via networking rather than a separate box; pricing is typically absorbed into a small per-unit premium rather than one large controller cost
Civils, cabling and containment
- SWA armoured cable, 3-phase feeder (per metre, material + labour) — £35-£55
- Per-bay spur cabling (per metre, material + labour) — £25-£40
- Cable containment (galvanised steel or heavy-duty trunking, external/car park rated, per metre) — £15-£35
- Trenching and reinstatement, paved/tarmac car park (per metre) — £40-£90
- Sub-distribution board for car park circuits (MCCBs/RCBOs, enclosure) — £900-£1,800
DNO and compliance
- DNO application/notification (G98, single-phase, low capacity) — usually free, notification only
- DNO application (G99, three-phase or higher capacity) — typically £250-£750 application fee; as fees and process vary by DNO and can change
- DNO supply reinforcement/upgrade (where required) — highly site-specific, from around £1,500 for a straightforward capacity increase to £10,000+ for significant network reinforcement — always treat as a provisional sum pending DNO quotation, not a fixed price
- Testing, certification and commissioning — £350-£700 depending on scheme size
Grants and scheme size
- OZEV Workplace Charging Scheme (WCS) — £350 per socket, up to 40 sockets per applicant; reduces the customer's net cost, not the installer's sell price
- BS 7671:2018+A4:2026, Section 722 — governs EV charging installation regardless of scale; the same core requirements apply, but PEN fault protection and diversity calculations become more significant across multiple bays sharing one supply
Quick Reference Table
Spending too long on quotes? squote turns a 2-minute voice recording into a professional quote.
Try squote free →| Scheme size | Typical hardware | DLM required? | Typical total (ex-VAT, before grant) | Approx. total after WCS grant |
|---|---|---|---|---|
| 4-bay, single-phase, near DB | 4 x 7kW AC | Optional at this scale | £8,000-£12,000 | £6,600-£10,600 |
| 4-bay, longer run / 3-phase | 4 x 7kW or 22kW AC | Recommended | £11,000-£16,000 | £9,600-£14,600 |
| 10-bay, 3-phase, DLM | 10 x 7kW AC + DLM | Yes | £15,000-£22,000 | £11,500-£18,500 |
| 10-bay with new DNO supply application | 10 x 7kW AC + DLM | Yes | £18,000-£28,000 | £14,500-£24,500 |
| 20-bay, 3-phase, DLM, significant civils | 20 x 7kW AC + DLM | Yes | £28,000-£42,000 | £21,000-£35,000 |
| 20-bay with DNO reinforcement | 20 x 7kW AC + DLM | Yes | £35,000-£55,000+ | £28,000-£48,000+ |
These are indicative ranges — always survey the specific site (existing supply capacity, cable run distances, parking surface type, and whether a DNO reinforcement is needed) before quoting a fixed price.
Detailed Guidance
The survey: what determines whether this is a straightforward or expensive job
- Existing supply capacity and headroom. A site with a modern three-phase supply and spare capacity is a materially cheaper job than one needing a DNO-led reinforcement. Get an up-to-date maximum demand figure from the site's existing supply and compare it against the proposed charging load before quoting.
- Number of bays and whether they're phased. A business installing 4 bays now with ducting/capacity left for 6 more later changes the civils and containment spec significantly — always ask about phased expansion plans, since over-sizing ducting and the DLM controller's monitored capacity at the outset is far cheaper than a second mobilisation later.
- Car park surface and cable route. Tarmac or block-paved surfaces requiring trenching and reinstatement cost meaningfully more than a site with existing ducting, an adjacent plant room, or a route that can run on surface-clipped containment along a boundary wall.
- Whether load management is essential or precautionary. At small scale (4 bays on a supply with genuine spare capacity for all 4 to run simultaneously at full power) DLM may be a value-add rather than a strict requirement. At 10+ bays sharing anything less than a very large supply, DLM is close to mandatory to avoid either nuisance tripping or a very expensive supply upgrade.
- Single-phase vs three-phase. Workplace schemes above a handful of bays are almost always three-phase, both for the supply itself and often for the chargers (22kW three-phase units charge faster, useful for fleet/turnaround use cases, but cost more per unit and need a three-phase supply at each bay).
DNO applications for commercial multi-bay supply
A single domestic 7kW charger is typically installed under a G98 connect-and-notify process — the installer proceeds and notifies afterward. A commercial multi-bay scheme, particularly one adding meaningful new demand or requiring three-phase capacity increase, is more likely to need a G99 application requiring the DNO's prior approval before work proceeds. This can take several weeks and, in some cases, requires network reinforcement paid for by the customer at the DNO's quoted cost. Build the DNO timeline into the customer's expectations early — it is the most common cause of a workplace EV scheme's actual completion date slipping well past the site survey date, and should never be quoted as a fixed-fee line until the DNO has actually responded with a capacity assessment. See ev charger installation pricing guide for the G98/G99 distinction in more detail at domestic scale.
Dynamic load management hardware and how it changes the electrical design
A DLM system monitors the site's real-time total demand — typically via CT clamps clipped around the incoming supply's live conductors — and communicates with the charge points (either through a dedicated controller box, or through master/slave networking built into the chargers themselves) to throttle individual charging currents dynamically, keeping total demand within the supply's rated capacity. This changes both the design and the pricing conversation:
- Design: diversity can no longer be assumed in the traditional sense (not every EV charges at full power simultaneously) unless the DLM system is actively enforcing that limit — treat DLM as the mechanism that makes a shared-supply multi-bay scheme compliant and safe, not an optional convenience feature, once bay count rises much above 4-6 on a standard commercial supply.
- Pricing: the DLM controller and CT clamp set is a one-off shared cost regardless of bay count within its rated management capacity, meaning cost-per-bay for this line item falls sharply as the scheme scales — this is the main reason a 20-bay scheme's total cost per bay is meaningfully lower than a 4-bay scheme's.
Per-bay vs shared-infrastructure pricing structure
Build the quote in two clearly separated blocks so the customer understands where the money goes and so the price scales correctly if bay count changes during the sales conversation:
Shared infrastructure (largely fixed regardless of bay count within a reasonable range):
- DNO application and any supply reinforcement
- Main feeder cable and containment from the distribution board to the car park
- Sub-distribution board and main protective devices
- DLM controller and CT clamp set
- Design, project management, and commissioning/certification
Per-bay costs (scale roughly linearly with the number of charge points):
- Charge point unit itself
- Spur cabling and containment from the sub-board to each bay
- Bollard/post mounting or wall-mounting hardware per bay
- Individual protective device (RCBO) per circuit
Worked example: 10-bay workplace installation with dynamic load management
Site: a business car park, existing three-phase supply with some spare capacity but requiring a G99 application, tarmac surface requiring some trenching, chargers positioned around the car park perimeter roughly 8m apart on average from a central feed point.
| Line item | Cost (ex-VAT) |
|---|---|
| 10 x 7kW AC untethered smart charge points | £7,500 |
| Dynamic load management controller (10-bay capacity) | £1,800 |
| CT clamp set at main incomer | £220 |
| Main 3-phase feeder cable + containment, DB to car park (30m) | £1,350 |
| Per-bay spur cabling + containment (10 bays, ~8m average run) | £2,400 |
| Trenching/reinstatement, tarmac car park (40m) | £2,200 |
| Sub-distribution board (MCCBs/RCBOs, enclosure) | £1,200 |
| DNO application (G99) | £750 |
| Testing, certification, commissioning | £450 |
| Total (ex-VAT, before grant) | £17,870 |
| OZEV Workplace Charging Scheme grant (10 x £350) | -£3,500 |
| Net cost to customer | £14,370 |
This total reflects material and installation cost with a working margin already applied to each line at typical commercial electrical contracting rates — present the grant as a separate deduction on the quote so the customer sees both the full job value and their actual net cost clearly, rather than pre-netting it into a single lower headline figure.
Hidden costs and margin risks specific to workplace schemes
The lines most commonly missed at quoting stage, in rough order of how often they get missed: (1) DNO reinforcement cost — never confirmed until the DNO actually assesses the application, so any quote issued before that response should carry the DNO cost as a clearly stated provisional sum; (2) surface reinstatement standard — car park owners/landlords may specify a particular reinstatement finish (matching existing tarmac, line-marking replacement) that costs more than a basic patch; (3) out-of-hours working — many workplace car parks can only have cabling/trenching done outside business hours or at weekends, which should be priced as a labour premium, not absorbed; (4) future-proofing ducting — quoting only for the immediate bay count when the customer has stated expansion plans creates an expensive redo later; always price spare ducting/capacity as an option; (5) DLM controller compatibility — mixing charger brands on one site can limit which DLM systems will work; confirm compatibility before specifying, since a mismatched system can mean re-purchasing hardware mid-project.
Frequently Asked Questions
Do all workplace EV schemes need dynamic load management?
Not strictly at very small scale if the existing supply has genuine spare capacity for every bay to run at full power simultaneously without breaching the site's agreed maximum demand — but this is uncommon much above 4-6 bays on a typical commercial supply. Above that, DLM is the standard, cost-effective way to install more charge points than the raw supply capacity would otherwise support, and is increasingly treated as expected practice rather than an optional extra by DNOs and specifiers.
How long does the DNO application process typically take for a multi-bay scheme?
It varies significantly by DNO and by whether reinforcement is required — a straightforward G99 application with spare capacity can sometimes clear in a few weeks, while one requiring network reinforcement can take considerably longer and involve a separate DNO-quoted cost. current typical timescales with the specific DNO covering the site before committing a customer to a completion date, as this is the most variable part of the whole project timeline.
Can the OZEV Workplace Charging Scheme grant be claimed for all 20 or 40 bays on a large scheme?
The scheme caps at £350 per socket up to a maximum of 40 sockets per applicant — check current OZEV eligibility criteria and confirm who is applying (the business, sometimes via the installer) before quoting the grant as a guaranteed reduction, since eligibility and process details are periodically updated. Treat the grant figure on any quote as indicative pending the customer's own successful application, not as a certainty you can guarantee.
Is a 22kW three-phase charger worth the extra cost over 7kW for a workplace scheme?
It depends on turnaround requirements. For an all-day workplace parking scenario where vehicles are plugged in for 7-8 hours, 7kW is usually more than sufficient to fully charge most vehicles and is materially cheaper per unit and per metre of associated three-phase-per-bay cabling. 22kW becomes worthwhile where vehicles turn over during the day (fleet use, visitor parking, shorter dwell times) and need a faster charge in a shorter window — discuss the actual usage pattern with the customer rather than defaulting to the higher-power option.
Regulations & Standards
BS 7671:2018+A4:2026, Section 722 — Electric vehicle charging installations; applies equally to single and multi-bay schemes, with diversity and PEN fault protection considerations more significant at scale
The Building Regulations 2010, Part S — Infrastructure for charging electric vehicles; applies to new-build and major-renovation non-residential buildings with associated parking above the regulation's specified threshold
The Building Regulations 2010, Part P — Electrical safety (notifiable work)
The Electric Vehicles (Smart Charge Points) Regulations 2021 — smart functionality requirements for charge points sold/installed in Great Britain
ENA EREC G98 / G99 — connection of generation/EV charging equipment to the distribution network; G99 is the relevant process for most multi-bay commercial applications
IET Code of Practice for Electric Vehicle Charging Equipment Installation (5th ed.) — covers multi-charge-point and load management design guidance
GOV.UK — Workplace Charging Scheme guidance — eligibility, grant amount and application process
Energy Networks Association — EREC G98/G99 — DNO connection application process
IET — Code of Practice for EV Charging Installation — technical installation and load management guidance
GOV.UK — Approved Document Part S — EV infrastructure requirements for non-residential buildings
ev charger installation pricing guide — domestic single-charger pricing, PEN fault protection and G98 notification detail
ev charger installation types — charger types and Section 722 technical detail underlying both domestic and workplace pricing
pme earthing ev charging — PEN fault protection technical detail relevant to multi-bay schemes on PME supplies
dno g98 g99 applications — DNO notification and application process detail