Summary

Hot tub installation looks like a delivery-day job — get the tub off the lorry, put it on the patio, fill it up — but the two things that actually need proper trade pricing are the base (structural loading, not just levelling) and the electrical supply (dedicated circuit, correct RCD protection, weatherproof isolation, and for larger tubs a hardwired connection rather than a plug). Both are frequently treated as an afterthought by customers who have bought the tub online and expect it to be "just put down and switched on," and both are where an under-priced job turns into a callback or a safety issue.

This guide covers pricing for the installation scope around a hot tub — base, delivery/positioning, electrical supply, and optional decking/screening — not the hot tub unit itself, which varies enormously in price by size, brand, and spec (entry-level plug-and-play spas start around £3,000-£5,000; premium hardwired spas with full hydrotherapy specification run £8,000-£18,000+) and is a supplier/materials decision, not a trade installation quote.

For the base construction detail this guide scales from, see shed base pricing guide (the "garden-room / hot-tub footing" line applies directly). For electrical supply sizing and outdoor cable/RCD requirements, see outdoor electrics and armoured cable. For swimming pools — a much larger-scale, different-cost-structure project — see swimming pool installation pricing guide.

Key Facts

Quick Reference Table

Spending too long on quotes? squote turns a 2-minute voice recording into a professional quote.

Try squote free →
Installation scope Typical cost Notes
Basic — existing sound patio, plug-and-play 13A socket install £500-£900 Suitable only if patio is confirmed structurally adequate
Standard — new reinforced concrete base, dedicated RCD socket circuit £2,250-£4,900 Most common mid-range installation; sum of base-only + electrics-only rows below
Standard + decking surround £3,650-£7,200 Base + electrics + surrounding deck for access/privacy
Premium — hardwired supply (32A+), consumer unit works, decking/screening £5,500-£9,500+ Larger premium tubs with higher electrical demand
Base only (if client arranging own electrics) £1,800-£3,500 See shed base pricing guide "garden-room / hot-tub footing"
Electrics only (if client has existing suitable base) £450-£1,400 Socket circuit vs full hardwired circuit, see below
Delivery/positioning with restricted access (crane/HIAB) £150-£450 add-on Confirm access at survey, not on delivery day

Figures exclude VAT and the hot tub unit purchase price itself.

Detailed Guidance

Base — the structural item most likely to be skipped

A hot tub is a genuinely heavy, static, concentrated load — unlike a shed or summer house where weight is distributed and modest, a filled hot tub places a sustained, significant load on a small footprint. Manufacturers specify a base capable of taking this load without settling, cracking, or shifting over time, which in practice means a reinforced concrete slab (not simply paving slabs on sand, which is adequate for a shed but not for this loading) at a thickness the manufacturer specifies for the tub's filled weight — commonly 100-150mm with mesh reinforcement for standard domestic tubs.

Assessing an existing patio for reuse: check the patio is genuinely concrete (not paving slabs on a sand/mortar bed, which will not spread the load adequately), confirm its thickness and condition (no visible cracking, hollow-sounding areas, or edge deterioration), and confirm it's been down long enough to have fully cured and settled. If any of these are in doubt, price a new base rather than risk a settling or cracking failure discovered after the tub is filled and in use — retrofitting a base under an installed, filled tub is a far more expensive and disruptive job than doing it right the first time.

For full base construction cost detail (excavation, sub-base, concrete specification, reinforcement), see shed base pricing guide, which lists a "garden-room / hot-tub footing" line at £1,800-£3,500 for the base construction itself — this guide's base pricing is drawn directly from that breakdown.

Electrical supply — size it to the tub, not a generic assumption

Hot tub electrical demand varies significantly by model — a small plug-and-play spa with a modest heater may run comfortably on a dedicated 13A RCD-protected outdoor socket circuit; a larger tub with a bigger heater element, multiple pump stages, and additional features (lighting, waterfall, blower) often needs a hardwired 32A or larger circuit. Always check the specific model's electrical datasheet before pricing or installing — do not assume based on tub size or price alone, as heater wattage (the main electrical load) varies between similarly-sized models.

Core requirements regardless of supply size:

If the existing consumer unit has no spare ways or capacity for a new circuit of the required size, factor a consumer unit upgrade or additional distribution board into the quote — this is a common surprise on hardwired installations and should be checked at the electrical survey stage.

Worked example 1 — basic install, existing sound patio, plug-and-play socket

Client has an existing solid concrete patio confirmed adequate for the load, and a small plug-and-play spa running on a 13A supply.

Item Cost
Patio suitability check and minor levelling £60
Dedicated outdoor RCD-protected socket, short cable run (6m) £340
Weatherproof local isolator £120
Part P certification £0 (included in electrician's cert fee)
Delivery assistance/positioning £90
Cost subtotal £610
Margin (30%) £183
Quoted price (ex VAT) £793
Quoted price (inc VAT) £952

Worked example 2 — standard install, new base, dedicated RCD socket circuit

Client wants a new base built (no suitable existing patio) and a dedicated socket circuit for a mid-range plug-and-play tub.

Item Cost
Site clearance and setout £70
Excavation, formwork, reinforced concrete base (150mm) £2,050
SWA cable run (14m), trenching, ducting £340
Dedicated RCD-protected outdoor socket + isolator £380
Part P certification £0 (included in electrician's cert fee)
Delivery assistance/positioning £110
Cost subtotal £2,950
Margin (28%) £826
Quoted price (ex VAT) £3,776
Quoted price (inc VAT) £4,531

Worked example 3 — premium install, hardwired supply, decking surround

Premium tub with a larger heater requiring a hardwired 32A circuit, new base, and a timber decking surround for access and privacy.

Item Cost
Site clearance and setout £90
Excavation, formwork, reinforced concrete base (150mm, larger footprint) £2,600
Consumer unit additional way/upgrade check and works £320
SWA cable run (20m), trenching, ducting, hardwired 32A circuit £780
Weatherproof local isolator, commissioning £180
Part P certification £0 (included in electrician's cert fee)
Timber decking surround, approx. 12m² £2,160
HIAB/crane assist for restricted-access delivery £280
Cost subtotal £6,410
Margin (25%) £1,603
Quoted price (ex VAT) £8,013
Quoted price (inc VAT) £9,616

Decking and screening — priced as a standard decking job

Where a client wants a decking surround for step-free access, privacy screening, or aesthetics, price this as a standard decking job scaled to the required area — see decking installation pricing guide for softwood, hardwood and composite pricing per m². The one hot-tub-specific consideration is designing the deck frame with adequate access for future tub maintenance and, if the deck sits over or adjacent to the electrical isolator or cable run, ensuring the isolator remains accessible and the buried cable route is recorded before decking covers it.

Delivery and access — check before install day, not on it

Hot tubs are typically delivered on a pallet and moved into position with a hand truck, tub dolly, or similar — manageable on most sites with reasonable side access. On restricted-access properties (narrow side gates, steps, no vehicle access to the rear garden), a small crane or HIAB lift over the property may be needed, adding £150-£450 depending on the lift complexity. Confirm access width and any level changes at the initial site survey — discovering an access problem on delivery day, with the tub on the lorry, is an expensive and avoidable failure.

Where builders lose money on hot tub installs

Frequently Asked Questions

Can I just plug a hot tub into an outdoor socket I already have?

Only if that socket is confirmed to be a dedicated, correctly-rated, RCD-protected outdoor circuit suitable for the specific tub's electrical demand, and the tub's manufacturer permits plug-and-play operation on a standard supply. Running a hot tub from an extension lead, a shared socket circuit, or an indoor socket via a lead through a door or window is unsafe, commonly invalidates the manufacturer's warranty, and is not compliant practice. Always check the specific tub's electrical requirements against the existing circuit before assuming it's suitable.

Does a hot tub need planning permission?

Usually not — a hot tub itself is typically treated similarly to other garden features under permitted development, though a hot tub combined with a substantial decking structure, screening, or roofed enclosure can bring boundary-height and outbuilding-coverage rules into play in the same way as any other garden structure. Check local constraints, particularly in conservation areas or where other permitted development rights have already been used up by existing garden buildings.

Why does a hot tub need a stronger base than a garden shed?

A filled hot tub concentrates a very significant static load (commonly 1,200-1,900kg for a 4-6 person tub) onto a relatively small footprint, and that load doesn't move or redistribute the way foot traffic or light storage does. A shed base needs to support distributed, comparatively light weight; a hot tub base needs to sustain a heavy, sustained, concentrated load without settling or cracking — which is why manufacturers specify a proper reinforced concrete slab rather than paving slabs on a sand bed.

How much does it cost to run a hot tub once installed?

Typically £30-£70 per month depending on tub size, insulation quality, target temperature, and how often it's covered when not in use. Well-insulated modern tubs with a good-fitting cover run toward the lower end; older or poorly-insulated tubs left uncovered or at a high constant temperature run higher. This is worth discussing with the customer at quote stage as part of the overall cost-of-ownership picture, not just the installation price.

What margin should I target on hot tub installation?

25-30% is typical, similar to other garden structure and electrical installation work. Push toward the higher end on straightforward jobs with an existing suitable base and a simple socket circuit; toward the lower end on premium jobs with new base construction, hardwired electrics, and decking, where cost variability across multiple trades (groundworks, electrical, carpentry) is higher.