Summary

Battery storage has moved from an early-adopter add-on to a mainstream retrofit product, and the technical requirements are well covered in battery storage — DNO notification thresholds, fire safety separation, and the new BS 7671 Chapter 57 rules. What that article doesn't cover, and what actually determines whether a battery job is profitable, is how to price the labour, materials and margin correctly, and where installers most commonly leave money on the table or absorb costs they should have quoted for.

This guide is written for the person doing the quoting, not the person doing the technical install. It breaks down realistic day rates, typical hardware costs by system size and chemistry, where DNO notification (G98 vs G99) affects programme and price, and the specific red flags — fire compartment relocation, undersized existing consumer units, cable run length to a compliant location — that turn a straightforward-looking battery job into a loss-making one if they're missed at the quoting stage.

Pricing this work well matters more than it used to. Since BS 7671:2018+A4:2026 introduced Chapter 57 and PAS 63100:2024 formally prohibited loft, bedroom, and unprotected escape route locations for battery systems, a meaningful share of "simple" battery retrofits now involve relocating cable routes or specifying a fire-rated enclosure that wasn't needed under the previous rules — and that additional scope needs to be priced, not absorbed.

Key Facts

Quick Reference Table

Spending too long on quotes? squote turns a 2-minute voice recording into a professional quote.

Try squote free →
System Type Typical Installed Price Labour Days Typical DNO Route
3.6-5kWh AC-coupled retrofit (existing solar PV) £4,500-£6,500 1 day G98
8-10kWh AC-coupled retrofit £6,500-£9,500 1-2 days G98
10-13.5kWh DC-coupled hybrid (new inverter) £9,000-£13,500 2-3 days G98 (usually)
13.5kWh+ or three-phase system £12,000-£18,000+ 2-3 days G99
Battery-only (no existing solar PV) £5,500-£10,000 1-2 days G98 (usually)
Combined new solar PV + battery £10,000-£18,000+ 2-4 days G98 or G99 by size

Figures are indicative 2026 UK market ranges for planning purposes — always price from current supplier cost sheets and site-specific labour assessment rather than these ranges alone.

Detailed Guidance

Labour Cost Breakdown

A realistic labour quote for a battery installation should itemise, even if the customer only sees a single line total:

Two-person crews are standard for battery installs given the weight of the units and the value of having a second person for testing/commissioning while the first completes physical fixing work.

Material Cost Breakdown

Beyond the headline battery unit price, a complete material cost breakdown includes:

Pricing by System Type

AC-coupled retrofit is the most common and most predictable job: adding a battery inverter to an existing solar PV system without touching the existing PV inverter. This is generally the lowest-labour, lowest-risk option to price, provided the existing consumer unit and cable routes are already compliant.

DC-coupled hybrid systems replace the existing PV inverter with a hybrid unit that manages both the panels and the battery on the DC side. This is more efficient long-term but adds inverter cost, additional commissioning complexity, and typically a half to full extra day of labour — price it as a materially different job, not a like-for-like swap of the AC-coupled quote.

Whole-house backup / EPS (emergency power supply) configurations, where the battery can island the property from the grid during an outage, require additional switching hardware and a more involved commissioning process, and should carry a distinct, higher price point reflecting that additional scope — don't quote this as a standard installation with "backup capability thrown in."

Margin and Markup Guidance

A 20-35% gross margin on hardware (battery, inverter, and associated electrical materials) is a reasonable starting point, with labour charged transparently at the day rate rather than disguised inside an inflated hardware price. This transparency matters for two practical reasons: customers increasingly compare quotes against publicly known hardware prices, and a clearly itemised quote is easier to defend if a customer queries the total or asks for a breakdown.

The most common margin killer on battery jobs isn't the hardware markup — it's underestimating commissioning time. Pairing a battery with an inverter, setting correct G98/G99 export parameters, and troubleshooting an app or monitoring platform connection routinely takes longer than a confident quote assumes, especially on the first few installs of a new product line. Build in a realistic commissioning time allowance rather than pricing based on the manufacturer's best-case install time.

Red Flags That Blow the Budget

Frequently Asked Questions

Why do quotes for what looks like the same battery vary so much between installers?

Largely because of what's included versus excluded. A quote that assumes the existing location is compliant, the consumer unit is already RCBO-ready, and no cable run extension is needed will look significantly cheaper than one that's priced a full PAS 63100:2024-compliant location from the outset — until the cheaper quote hits a site survey and the price changes. Itemising the quote clearly protects both the installer and the customer from this mismatch.

Should the DNO notification (G98/G99) be a separate line item?

Yes, particularly for G99 jobs where approval time and potential DNO reinforcement costs represent a genuine programme and cost risk that the customer should see and understand upfront, rather than discovering as a surprise delay partway through the job.

How much extra should I quote if the customer's preferred location isn't PAS 63100:2024 compliant?

This depends entirely on the site — a straightforward move from a cupboard to a nearby garage might add only a modest amount of extra cable and half a day's labour, while a location that requires a fire-rated enclosure or a long external cable run to reach a genuinely compliant space can add a significant proportion of the total job cost. Always assess this on-site before quoting a fixed price; a phone-based estimate on location compliance is one of the most common sources of a quote that doesn't survive the actual site visit.

Is retrofitting a battery to existing solar PV cheaper than a combined new solar + battery installation?

Per-project, yes — a retrofit avoids the cost of new PV panels, and often avoids a full inverter replacement if an AC-coupled battery inverter is used. However, a combined new-build solar + battery installation can be more cost-efficient per kWh of capacity delivered, since scaffold, DNO notification, and commissioning time are shared across both elements of the job rather than duplicated across two separate site visits months apart.

What warranty or callback provision should be built into the price?

A small allowance — commonly built into the margin rather than itemised separately to the customer — covering a return visit for commissioning-related issues (BMS warning codes, inverter/battery pairing faults, app or monitoring connectivity problems) in the weeks following handover is standard good practice, distinct from the manufacturer's product warranty which covers hardware failure over a longer term.

Regulations & Standards