Summary

Garden steps are the most under-priced item in landscaping quotes because they look small. A flight of five steps on a drawing is a 1.2 m by 2 m rectangle; on site it is excavation on a slope, a concrete footing, a tapered concrete or block core, risers built true, treads laid to fall with consistent nosing, two cheek walls or side returns, and the junction with whatever is at the top and bottom. The materials are cheap; the labour is dense, and every step has to match the others or the customer trips. Landscapers who price steps per step at a flat rate without measuring the total rise are the ones who end up building a flight for free.

Pricing has to start with the levels. The total rise divided by a comfortable riser height gives the number of steps; the number of steps multiplied by the going gives the run; the run has to fit the slope. If it does not, there is a landing or a retaining wall in the job that nobody has drawn. Measuring the rise with a laser or a long level and a staff before quoting is the single most valuable fifteen minutes in landscape pricing.

This guide prices the common UK forms (concrete block core faced with brick and paving, cast in-situ concrete, natural stone slabs on a block core, timber sleeper steps on a slope, and precast concrete or steel-edged gravel steps), covers footings, drainage, handrails and lighting as extras, and sets out the rise and going rules that apply when the steps form part of the access to a dwelling. For construction method and dimensional rules see garden steps; for the related wall and paving work see retaining wall pricing guide and patio installation pricing guide.

Key Facts

Quick Reference Table

Spending too long on quotes? squote turns a 2-minute voice recording into a professional quote.

Try squote free →
Step type (flight of 5, 1.2 m wide, 800 mm total rise) Materials (your cost) Labour (2 people) Your cost Customer price (20–30% margin)
Concrete block core, brick risers, pressed concrete slab treads £350–£550 2–3 days £1,150–£1,750 £1,400–£2,300
Concrete block core, brick risers, riven sandstone treads £450–£700 2.5–3 days £1,350–£1,900 £1,650–£2,500
Block core, sawn sandstone risers, bull-nosed sandstone treads £650–£1,000 3–4 days £1,750–£2,600 £2,100–£3,400
Porcelain treads and risers on block core £750–£1,200 3–4.5 days £1,950–£3,000 £2,400–£3,900
Cast in-situ concrete steps, brushed finish (shuttered) £300–£450 2–2.5 days £1,050–£1,450 £1,250–£1,900
Treated softwood sleeper steps, gravel treads, on slope £300–£450 1.25–2 days £750–£1,250 £900–£1,650
Oak sleeper steps, gravel treads £450–£700 1.25–2 days £900–£1,500 £1,100–£1,950
Steel-edged gravel steps (Corten or galvanised edging) £500–£800 1.5–2.5 days £1,100–£1,800 £1,350–£2,350
Precast concrete step units on footing £400–£650 1–1.5 days £800–£1,250 £1,000–£1,600
Add cheek walls both sides, brick, 800 mm high £350–£600 +1.5–2 days +£950–£1,400 +£1,200–£1,800

Prices are 2024 regional England excluding VAT, assuming reasonable access, firm subsoil and spoil removed by skip. Add 25–40% for London. Flights wider than 1.2 m scale roughly in proportion to width for materials and 60–70% in proportion for labour.

Detailed Guidance

Measure the levels first

Set a datum at the top landing and measure down to the bottom landing with a laser level or a level and staff. Record the total rise and the horizontal run available. Then:

Worked example: total rise 830 mm, run available 1,900 mm. At 165 mm rise, 830 ÷ 165 = 5.03, so five risers at 166 mm. Four goings of 350 mm = 1,400 mm, within the 1,900 mm, leaving 500 mm for the top tread or landing. Five steps, each 166 mm rise, 350 mm going. Write those two figures on the quote; they are what you will build to and what the customer agreed.

The block-core method: time breakdown

The standard UK garden step is a tapered mass of concrete blocks on a footing, faced with brick risers and slab treads. For a five-step, 1.2 m wide flight:

Task Time (2 people) Notes
Set out, excavate footing and step profile, barrow spoil 0.5 day Slopes add time; clay adds more
Pour footing, allow to cure overnight 0.25 day Minimum 150 mm, 225 mm on clay or soft ground
Build block core, step by step, to profile 0.5–0.75 day Check each riser height with a gauge rod
Build brick risers, two courses each, pointed 0.5 day Riser height = block + bedding + slab; set out so courses work
Lay slab treads on full mortar bed, 25–40 mm nosing, 1:70 fall 0.5 day Cut slabs to width; one cut per tread minimum
Point treads, clean, haunch sides, backfill and make good 0.25–0.5 day Protect from rain for 24 hours
Total 2.5–3 days

The gauge rod is the discipline: a rod marked with the riser height, used on every step, is the difference between a flight that feels right and one that trips. Variation of more than 5 mm between risers is noticeable underfoot.

Natural stone and porcelain treads

Bull-nosed sandstone treads (a sawn slab with a rounded front edge, typically 600 × 350–400 mm × 35–40 mm) and matching riser strips give the premium look. Material rises to £650–£1,000 for five steps, and labour rises because every piece is heavier, every cut is a wet-saw cut, and the joints have to be tight and even. Porcelain is harder still: it needs a priming slurry on the back of every piece, a full solid bed with no voids, and specialist blades; allow 25–40% more labour than sandstone. Porcelain risers are often fixed with a flexible adhesive rather than mortar. Price a 10% wastage on sandstone and 15% on porcelain.

Sleeper steps on a slope

The quickest and cheapest form for informal gardens. Each step is a sleeper (or two stacked for a 200 mm rise) set into the slope, pinned with 300–450 mm steel road pins or screwed to posts driven behind, with the tread filled with compacted MOT Type 1 and topped with 20 mm gravel or bark. The going is whatever the slope allows, typically 400–600 mm, which makes for a relaxed, ramped feel. Weaknesses: the gravel migrates, the sleepers rot in 10–15 years (treated softwood) or 25+ years (oak), and the steps are not suitable as the dwelling's approach route. Price at £900–£1,650 for five, and tell the customer about the lifespan.

Footings, drainage and frost

Dig to firm ground, which on most UK gardens means through 300–450 mm of topsoil. On shrinkable clay, go to 450 mm minimum and widen the footing; a step flight that heaves in a wet winter opens every joint. Lay treads to a 1:60–1:80 fall to the front so water runs off the nosing, never back into the riser joint where it freezes and spalls the brick. Where the bottom step meets a lawn or planted area, leave the lowest riser 50–75 mm clear of the soil line or build a brick-on-edge step-off, or the mortar joint sits permanently wet. Where the flight is against a house wall, keep the top tread at least 150 mm below the damp-proof course.

Handrails, lighting and the approach-route rules

If the steps are the route from the pavement or parking space to the dwelling's principal entrance on a new dwelling, Approved Document M Volume 1 applies and the flight needs the M4(1) proportions, a minimum 900 mm clear width and a handrail on at least one side where there are three or more risers, with a landing at top and bottom. Existing dwellings being altered are not automatically caught, but a reasonable landscaper builds the approach route to those proportions anyway, and planning conditions on new-build plots often require it. Price a galvanised steel handrail at £120–£250 per linear metre installed, core-drilled and resin-fixed into the cheek wall or tread.

Riser lights (SELV LED, 12 V, IP65, £25–£60 each) are the most-requested extra. Run the cable in a duct through the block core before facing, or you will be chasing stone. The transformer needs a weatherproof enclosure and a 230 V supply; a mains SWA run to a garden is electrical work that needs a competent electrician and may need Part P notification if it is a new circuit. See garden lighting installation pricing guide and garden lighting installation.

Presenting the quote

State the number of steps, the rise and going, the width, the facing materials by type and colour, the footing specification, who removes spoil, and what is excluded (handrail, lighting, retaining walls, lawn reinstatement, planting). Fix the price for the specified flight, and give a per-step rate for any variation the levels force on site, plus a clay or rock excavation rate. Photograph the levels survey and keep it with the quote; when a customer says "I thought there would be four steps", the survey is your answer.

Frequently Asked Questions

Do garden steps need Building Regulations approval?

Not on their own. Steps in a private garden that are not part of the access to the dwelling are outside the Building Regulations. If they form the approach route to the principal entrance of a new dwelling, or are built as part of work that is itself notifiable (an extension with a new entrance, for example), Approved Document M Volume 1 and Approved Document K apply to that route. A flight attached to the house with a retaining wall over 1 m, or a wall adjoining a highway, may also need planning permission under the Town and Country Planning (General Permitted Development) (England) Order 2015, Schedule 2 Part 2 Class A limits (1 m adjacent to a highway, 2 m elsewhere); see planning permission fences walls.

What is the ideal rise and going for garden steps?

150–170 mm rise with 300–350 mm going. Outdoors, people move more slowly and carry things, and the longer going feels generous and safe. The traditional check is 2R + G = 600–650 mm; 165 + 165 + 320 = 650 works well. Never vary the rise within a flight, and never make a single step in a path (a "trip step"); make it two, or a ramp.

How deep should the footing be?

For a flight of up to about 1 m total rise on firm ground, a 150 mm minimum thickness of GEN3 concrete on compacted subsoil, 100 mm wider than the step on each side. On shrinkable clay, soft or made-up ground, or for taller flights with cheek walls, 225–300 mm thick and taken down to at least 450 mm below finished ground level. The footing is a few bags of ballast; a heaved flight is a rebuild.

Can I build steps against the house wall?

Yes, with two precautions. Keep the top tread at least 150 mm below the damp-proof course so you do not bridge it, and do not bond the step core into the house wall, because the steps and the house will move differently; leave a compressible joint and seal it. If the wall is a cavity wall with vents or weep holes, do not cover them.

How long before the customer can use the steps?

Mortar-bedded treads need 24 hours before light foot traffic and 48–72 hours before heavy use or furniture dragged across them; protect from rain and frost during that period. Cast in-situ concrete needs 48 hours for foot traffic and 7 days before any point loads. Sleeper steps can be used immediately.

Regulations & Standards