Summary
A detached garage is a small building with every trade in it: groundworks, concrete, masonry, carpentry, roofing, a door installer, an electrician and usually a drainage connection, on a footprint small enough that the trades cannot all be on site at once. Customers price it from a sectional garage brochure and are surprised by a masonry quote three times higher; tradespeople price it from the brickwork and forget the muck-away, the soakaway, the scaffold for the roof and the sub-main from the house. The result is a job that either loses the quote or loses money on it.
The job has three distinct markets and the quote has to say which one it is in. A prefabricated concrete sectional or a timber garage on a slab is a base-and-erection job: the base is the builder's, the building arrives on a lorry. A single-skin masonry garage with piers and a flat or trussed roof is the traditional domestic garage and the bulk of the work. A cavity-wall garage with a pitched roof, matching the house, with room above or designed for conversion later, is a small extension by another name and is priced like one.
This guide prices all three, breaks the masonry garage into stages with days and material costs, sets out the planning and Building Regulations position, lists the extras that decide whether the job pays, and gives the margins.
Key Facts
- Typical prices (2026, ex VAT) — concrete sectional single on a new base £6,000–£12,000; timber-framed single £12,000–£22,000; single-skin brick single, flat roof £16,000–£24,000; single-skin brick single, pitched tiled roof £20,000–£32,000; cavity brick single, pitched roof to match house £26,000–£40,000; double garage in brick with pitched roof £30,000–£52,000
- Standard sizes — single garage internal 3.0 × 6.0 m (18 m²) minimum for a modern car, 3.5 × 6.5 m (23 m²) comfortable; double 5.5–6.0 × 6.0 m (33–36 m²); a 30 m² internal floor area is the Building Regulations exemption threshold
- Building Regulations exemption — Schedule 2 Class 6 of the Building Regulations 2010: a detached single-storey building with a floor area not exceeding 30 m², containing no sleeping accommodation, is exempt provided it is either at least 1 m from the boundary of its curtilage or constructed substantially of non-combustible material; above 30 m², or closer than 1 m in combustible construction, a full plans or building notice application is needed (see outbuildings regs)
- Part P still applies — a new circuit or sub-main to the garage is notifiable electrical work whatever the exemption status; use a registered electrician who self-certifies, or notify Building Control
- Drainage — surface water from the roof must go to a soakaway, a watercourse or a surface-water sewer in that order of preference (Approved Document H3); a soakaway at least 5 m from any building, sized to BRE Digest 365 (see soakaways)
- Planning — permitted development under Schedule 2 Part 1 Class E of the Town and Country Planning (General Permitted Development) (England) Order 2015: not forward of the principal elevation, maximum height 4 m with a dual-pitched roof or 3 m otherwise, 2.5 m if within 2 m of a boundary, eaves no higher than 2.5 m, total outbuildings not more than 50% of the curtilage, with restrictions on designated land and none for flats or listed buildings (see permitted development householder)
- Foundations — strip footings 600 mm wide, concrete 225–300 mm thick, to a depth set by the ground, typically 750–1,000 mm, deeper near trees or in shrinkable clay; a ground-bearing slab 100–150 mm of C25/30 concrete on 150 mm compacted MOT Type 1 and a 1200-gauge DPM, with A142 mesh where a vehicle is parked (see foundation depths and types)
- Walls — single-skin 102.5 mm brick or 100 mm block with 215 × 215 mm attached piers at not more than 3 m centres and at door jambs, to about 2.3–2.5 m eaves height, with a DPC at 150 mm above ground; or a 275–300 mm cavity wall where the garage is to match the house or be converted later
- Roof — fink trussed rafters at 600 mm centres on a timber wall plate strapped to the wall, 25 mm × 50 mm battens on a breathable membrane, concrete interlocking tiles at 30–35° pitch, ridge and verge dry-fixed; or a flat roof on 47 × 150 mm joists with firrings to a 1:40 fall, 18 mm OSB deck and a single-ply or GRP membrane
- Door — a standard single door opening of 2,134 × 2,134 mm (7 ft × 7 ft) or 2,438 mm wide for a modern car; up-and-over £500–£1,000 supplied, sectional £1,200–£2,500, roller £900–£2,000 (see garage door installation pricing guide)
- Labour benchmarks — groundworker £180–£260/day; bricklayer £220–£320/day plus labourer £140–£200/day; carpenter £200–£280/day; roofer £200–£300/day; electrician £250–£350/day (see bricklayer day rate guide)
- Programme, masonry single — 1 day set out and strip, 2–3 days excavate and pour footings, 2 days hardcore, DPM and slab (plus curing), 5–7 days brickwork and piers, 1 day wall plate and trusses, 3–4 days felt, batten and tile, 1 day door and personnel door, 1–2 days electrics, 1–2 days gutters, soakaway and making good: 15–22 working days
- Material allowances, masonry single — 7–9 m³ concrete for footings and slab £1,000–£1,500 delivered; 2,500–3,000 facing bricks £1,200–£2,200 or 450 blocks £600–£900; sand, cement and lime £250–£400; 8–10 trusses £700–£1,100; tiles, membrane, battens, ridge and verge £1,200–£2,000; wall plate, straps, fascia and soffit £300–£500; gutters and downpipes £150–£300; DPC and DPM £80–£150; lintels £150–£400; door and frame £500–£2,500; personnel door and window £300–£800; electrics materials £400–£800; skips and muck-away £500–£1,000
- Plant — mini-digger and dumper hire £250–£400/day; scaffold or tower for the roof £400–£900; whacker plate and mixer £60–£100/day
- Margin — 20–30% gross on the whole job; materials at 15–25% over trade price; the small size means overheads per square metre are high and a 15% margin is a loss once the snags are counted
Quick Reference Table
Spending too long on quotes? squote turns a 2-minute voice recording into a professional quote.
Try squote free →| Garage type | Size | Programme | Typical price to customer (ex VAT, 2026) |
|---|---|---|---|
| Base only for a sectional or timber garage (slab, DPM, hardcore) | 3.5 × 6.5 m | 3–4 days | £2,500–£4,500 |
| Concrete sectional single, supplied and erected on your base | 3 × 6 m | Base + 1 day erection | £6,000–£12,000 total |
| Timber-framed single, clad, felt or metal roof, on your base | 3 × 6 m | 5–8 days | £12,000–£22,000 |
| Single-skin brick with piers, flat roof (GRP or single-ply), up-and-over door | 3 × 6 m | 12–16 days | £16,000–£24,000 |
| Single-skin brick with piers, trussed pitched roof, concrete tiles | 3 × 6 m | 15–22 days | £20,000–£32,000 |
| Cavity brick to match house, pitched roof, sectional door, insulated | 3.5 × 6.5 m | 20–28 days | £26,000–£40,000 |
| Double, single-skin brick, pitched roof, two doors or one double door | 6 × 6 m | 22–30 days | £30,000–£45,000 |
| Double, cavity brick, pitched roof, room-in-roof ready | 6 × 6.5 m | 30–40 days | £40,000–£55,000 |
| Electrical supply from house, SWA sub-main, consumer unit, lights and sockets | — | 1–2 days | £1,200–£2,500 |
| Soakaway and rainwater connection | — | 1 day | £500–£1,100 |
| Building Regulations application (over 30 m² or within 1 m combustible) | — | — | £400–£900 fee plus drawings |
Detailed Guidance
Pin down the specification before the price
Three decisions set the price and the customer rarely makes them unprompted:
- Size. A 3 × 6 m internal garage fits a car and nothing else; many customers want storage, a bike or a workbench and need 3.5 × 6.5 m, which takes the floor area from 18 m² to 23 m², still under the 30 m² exemption line. A double at 6 × 6 m is over it and needs a Building Regulations application whatever the construction.
- Construction. Sectional, timber, single-skin masonry, or cavity. A customer who says "brick to match the house" means cavity construction with facing bricks on the outer leaf and a roof that matches, which is the top of the range. A customer who says "just a garage" is usually happy with single-skin blockwork rendered or single-skin brick with piers.
- Roof. Pitched trussed roofs cost £3,000–£6,000 more than flat on a single garage but last three times as long and are what most customers picture. If the garage must sit within 2 m of a boundary under permitted development, the 2.5 m height limit forces a flat roof or a planning application.
Walk the site with the customer. Where does the drive meet the door, where does the surface water go, where is the nearest point of the house electrical installation, where will the skip and the digger sit, and is there a tree within 10 m, which changes the foundation depth. Photograph the boundary positions.
Planning and Building Regulations
Planning. Most detached garages are permitted development under Class E provided they are behind the principal elevation, within the height limits, and the total area of outbuildings does not exceed 50% of the garden. On designated land (conservation areas, AONBs, National Parks) outbuildings at the side of the house are not permitted development and there are limits on size further from the house. Flats and listed buildings have no permitted development. A lawful development certificate (£150–£300 fee plus drawings) is worth having for the customer's file; see lawful development certificate.
Building Regulations. A detached garage up to 30 m² floor area, with no sleeping accommodation, either at least 1 m from the boundary or substantially non-combustible, is exempt. Masonry with a tiled roof is non-combustible for this purpose, so a brick single garage can sit on the boundary and remain exempt; a timber garage within 1 m of the boundary is not exempt and needs an application. Over 30 m², everything applies: Part A structure, Part C moisture, Part H drainage, Part B fire separation if within 1 m of a boundary, and Part L if the garage is heated.
Exempt does not mean unregulated. The electrical supply is notifiable under Part P. The surface water drainage still has to go somewhere lawful. And the exemption is from the Building Regulations, not from building properly: a garage with footings too shallow for the clay will crack in its first dry summer whether or not an inspector ever saw it.
Groundworks and slab
Set out with the customer present and get the position signed off; a garage 300 mm from where the customer imagined it is the commonest dispute. Strip the topsoil and dig the footings to firm ground or the depth Building Control would expect for the soil: 750 mm in good gravel, 1,000 mm in clay, more near trees. Pour the footings in one go. Build up to DPC in engineering brick or dense block, then compact 150 mm of Type 1, lay the DPM up the walls, and pour the slab with a float finish and a slight fall to the door. A142 mesh in the slab where a car will stand, and a construction joint if the slab is more than about 6 m long in either direction.
Muck-away is the forgotten line: a single garage's footings and strip produce 10–15 m³ of spoil, two or three 8-yard skips or a grab lorry at £250–£400 a load.
Walls and roof
Single-skin walls need piers: at every corner, at the door jambs, and at not more than 3 m centres along the sides, bonded into the wall with the pier the full height. The wall plate is bedded on the last course and strapped down with galvanised restraint straps at not more than 2 m centres; the trusses are fixed to it with truss clips, with diagonal bracing to the manufacturer's layout. A single garage takes eight to ten fink trusses at 600 mm centres with a gable ladder at each end, or a hipped end if the customer wants it.
Lintels over the main door opening carry the roof: a steel box lintel or a pair of concrete lintels for a 2.4 m opening in single-skin work, sized from the manufacturer's table for the span and the load. Over 3 m, or for a double door opening, get a calculation.
Flat roofs are faster and cheaper: joists at 400 mm centres with firrings to 1:40, 18 mm OSB3, and a GRP or single-ply membrane with a 150 mm upstand at the abutments and a drip to the gutter. Allow for the membrane installer's lead time.
Door, electrics and drainage
Fit the door frame to the opening and the door to the frame, with the manufacturer's fixings into the piers. Up-and-over doors need headroom of 50–100 mm above the opening for the track; sectional doors need 150–250 mm and a side clearance each side; check before the lintel height is fixed.
The electrical supply is a separate quoted line from a registered electrician: a 4–10 mm² SWA sub-main from the house consumer unit through a suitable protective device, run underground at 500 mm depth with marker tape or clipped along a wall, to a small consumer unit in the garage with RCD protection, a lighting circuit and a socket circuit; an EV charger if wanted at the same time (see garden room electrical supply sizing). A 1.5 mm² cable from a spare way is not a garage supply.
Rainwater goes to a soakaway dug at least 5 m from the garage and the house, sized from a percolation test, or to an existing surface-water drain if the customer has one and the connection is permitted. Never to the foul drain.
Pricing it and protecting the margin
Price from the stage table with the materials listed, and add the plant, the skips, the scaffold and the Building Control fee as their own lines. State what the price assumes: foundation depth, no services in the dig, no tree roots, a level site, access for a mini-digger and a lorry. Anything found at the dig is a variation.
Show the three construction options with prices if the customer is undecided; most choose the middle one, and a customer who has seen the £6,000 sectional price next to the £24,000 brick price understands what they are paying for.
Payment in stages: a deposit on order (materials), a stage payment at slab, one at roof on, and the balance on completion. A garage is a three-to-four-week job with £8,000–£12,000 of materials in it before the roof goes on.
Frequently Asked Questions
Can the garage go right on the boundary?
Under permitted development yes, provided the height is limited to 2.5 m within 2 m of the boundary, which means a flat roof. Under the Building Regulations exemption yes, provided it is substantially non-combustible, which masonry with a tiled or concrete roof is. Practically, the customer needs access to maintain the far side, the roof must drain onto their own land, and if the garage is built off a neighbour's wall or foundation the Party Wall etc. Act 1996 applies; see party wall act.
Does a detached garage need insulation?
Not if it is unheated and under the Building Regulations exemption, and Part L does not apply to an unheated garage in any case. If the customer intends to heat it or convert it later, build a cavity wall with partial-fill insulation and an insulated slab now; the cost difference on a single garage is £3,000–£5,000 and converting a single-skin garage later costs more than that.
What foundation does a sectional garage need?
A level concrete base to the manufacturer's dimensions, usually 100–150 mm of concrete on compacted hardcore with a DPM, flat to within a few millimetres and extending the manufacturer's margin beyond the building line. The erection crew will refuse a base that is out of level or short. Price the base at £2,500–£4,500 and confirm the dimensions from the manufacturer's drawing, not the brochure.
Can I build a garage with room above under permitted development?
Only within the 4 m height limit for a dual-pitched roof, which allows a modest storage loft but not a habitable room, and the building must remain incidental to the enjoyment of the house, not a separate dwelling. A room above for an office or a guest bed is a planning application and a full Building Regulations job with a protected stair, fire resistance and insulation; price it as an annexe (see granny annexe pricing guide).
Regulations & Standards
Building Regulations 2010, Schedule 2 Class 6 — exemption for detached single-storey buildings up to 30 m² without sleeping accommodation
Building Regulations 2010, Approved Document A (structure) — masonry wall thicknesses, piers and lateral restraint for small buildings
Building Regulations 2010, Approved Document C (resistance to moisture) — damp-proof courses and membranes, ground-bearing floors
Building Regulations 2010, Approved Document H (H3 rainwater drainage) — disposal of roof water, soakaways
Building Regulations 2010, Approved Document P (electrical safety) — the garage supply as notifiable work
Town and Country Planning (General Permitted Development) (England) Order 2015, Schedule 2 Part 1 Class E — outbuildings
Party Wall etc. Act 1996 — building on or near a boundary
BS 8000-3 — workmanship on building sites: masonry
BS EN 1996-1-1 — Eurocode 6: design of masonry structures (the basis for wall and pier design where calculations are needed)
BS 5268-3 — structural use of timber: trussed rafter roofs (bracing and fixing)
BS EN 771-1 — specification for masonry units: clay masonry units
BRE Digest 365 — soakaway design
Construction (Design and Management) Regulations 2015 — domestic client duties pass to the contractor on a garage build
GOV.UK — Building regulations approval: exemptions — the Schedule 2 exemptions for small detached buildings
Planning Portal — Outbuildings — permitted development rules for garages and outbuildings
GOV.UK — Approved Document A: structure — small building masonry guidance
GOV.UK — Approved Document H: drainage and waste disposal — rainwater disposal and soakaways
LABC — Garages and outbuildings guidance — Building Control guidance on exempt buildings
Trussed Rafter Association — Technical guidance — truss fixing and bracing
garage conversion pricing guide — the reverse job: turning a garage into a room
garage door installation pricing guide — the door as a priced line
garage roof replacement pricing guide — roofing an existing garage
outbuildings regs — the exemption rules in full
permitted development householder — Class E and the other permitted development classes
foundation depths and types — footing depths by ground condition
concrete volume — working out the footings and slab
brick quantities — bricks and blocks for the walls
soakaways — sizing and siting the soakaway
bricklayer day rate guide — the labour rates behind the figures