How to Price a Concrete Slab: Ground Slabs & Foundations

Quick Answer: Ready-mix concrete (C20 / GEN3 strength) delivered costs £130–£175 per m³; mass strip foundation costs £90–£160 per linear metre installed. A 5m × 5m × 150mm garage/shed slab (3.75m³) total installed £900–£1,500 including DPC, mesh, edge formwork, labour. All structural concrete must follow BS 8500-1:2023 mix spec, BS 8110 / Eurocode 2 design, and Building Regulations Part A for any load-bearing application.

Summary

Concrete slabs sit behind every UK building project — foundation strips, ground floor slabs, garage bases, shed pads, driveway sub-bases. Pricing is conceptually simple (volume of concrete × £/m³ + formwork + reinforcement + labour) but practically variable due to access, ground conditions, and reinforcement requirements.

This guide covers the main types of domestic slab (mass strip foundation, ground floor slab, shed/garage base, driveway sub-base), how to specify concrete mix correctly, when reinforcement is needed, and how to itemise the components for a defensible quote. It does not cover engineered foundations (raft, piled) which need structural engineer specification.

The most common pricing mistake: assuming concrete is the biggest cost. For most domestic slabs, concrete itself is 25–35% of total — excavation, hardcore, DPC, formwork, mesh and labour together make up the rest. Quote it line-by-line.

Key Facts

Quick Reference Table

Spending too long on quotes? squote turns a 2-minute voice recording into a professional quote.

Try squote free →
Slab Type Typical Spec Concrete £/m² Total £/m² Notes
Shed/summerhouse base 100mm C20 + mesh £14–£18 £40–£70 DIY-friendly
Garage base 150mm C25 + mesh + DPM £22–£28 £60–£100 Standard garage
Domestic ground floor slab 150mm C25 + mesh + DPM + insulation £22–£28 £85–£140 Includes 100mm insulation
Garden path 100mm C20, no mesh £14–£18 £45–£75 Decorative finishes extra
Driveway sub-base + 150mm slab C30 + mesh + edges £22–£32 £75–£140 Block paving over extra
Mass strip foundation 600mm × 250mm C20 mass concrete £30–£40/m³ £90–£160/m linear Standard depth
Strip foundation 800mm × 300mm C25 for clay/heavy load £35–£50/m³ £130–£200/m linear Clay soil typical
Raft foundation (engineered) Reinforced C30 + mesh £30–£45 £200–£400 Engineer's spec
Conservatory base C25 + insulation £22–£28 £100–£180 UPVC frame load

Detailed Guidance

Concrete mix specification

BS 8500-1:2023 standardises mix designations. Common UK ready-mix grades:

For most domestic work: GEN3 (or C20/25) is correct for ground floor slab; RC25/30 for reinforced foundations. Specify on delivery ticket.

Slump and aggregate

Specify when ordering. Don't request "as supplied" — the result varies by depot.

Volume calculation

Volume (m³) = length × width × thickness.

For ground floor 5m × 6m × 150mm thick:

Add 5–10% wastage and contingency. Order 5m³ to be safe; cost £680–£875 for ready-mix delivered.

For strip foundation 600mm wide × 250mm deep × 25m linear:

Add 10–15% for over-dig fill and surcharge. Order 4.5m³.

Excavation and prep

Standard sequence:

  1. Mark out — Spray paint, string line to engineered or planning drawing
  2. Strip topsoil — 200–300mm typical, removed from site or used elsewhere
  3. Excavate to formation level — Mini-digger £150–£250/day rate
  4. Lay hardcore (MOT Type 1) compacted — 100–150mm layer
  5. Compact — Whacker plate, multiple passes until firm
  6. Sand blinding (optional) — 25–50mm to protect DPM
  7. Lay DPM (1200 gauge polythene) — Continuous, taped at joints, turned up 150mm at edges
  8. Lay insulation (if ground floor of habitable building) — 100mm PIR taped at joints
  9. Lay reinforcement — A142 or A193 mesh on 25mm bar-chair spacers
  10. Formwork at edges — Timber shutters fixed to ground stakes
  11. Pour concrete — Distribute, tamp, float
  12. Curing — Cover with hessian or plastic 24–72 hours, water if hot weather

For a 5×6m garage slab, this is 2–3 days for 2-fitter team including delivery wait.

Reinforcement — when needed

No reinforcement: Garden paths under 100mm thick, paving sub-base, shed base under 5m².

A142 mesh: Standard ground floor slab, garage base, driveway, small slab (5–20m²).

A193 mesh: Heavier load (commercial driveway, large garage), reinforced foundation strip.

Rebar (B500B): Engineered slabs, beams, retaining walls. Specified by structural engineer.

Always lay reinforcement on bar chairs/spacers — not directly on DPM. Mesh laid on ground = useless (won't resist tension where it's needed).

DPM (damp-proof membrane) — non-negotiable

For habitable building slab:

DPM connects to wall DPC at perimeter. Failure here = rising damp through floor; whole house affected.

Insulation — for habitable building slab

Building Regs Part L 2021 requires ground floor U-value ≤0.18 W/m²K for new dwellings, ≤0.25 for extensions.

Typical achieve:

Insulation cost: £14–£22/m² for 100mm PIR. Lay between DPM and mesh.

Edge formwork and finish

Surface finishes:

Specify in quote.

Curing

Concrete strength develops over 28 days. First 7 days critical:

Premature loading or freezing = cracking and reduced final strength.

Ready-mix delivery considerations

Order from local ready-mix supplier (Hanson, Tarmac, Aggregate Industries, smaller local). Delivery considerations:

For tight access sites, consider concrete pump or volumetric (on-site mixing) supplier — costs more but solves access.

Worked example — 5m × 6m × 150mm garage slab

Frequently Asked Questions

Can I mix concrete on site instead of ready-mix?

For small slabs (<2m³) site mixing is viable but slow. Cost roughly £80–£120/m³ in materials plus significant labour (2 hours+ per m³ mixing). For anything bigger than a shed base, ready-mix is faster, more consistent, and cheaper overall. Site mix is for awkward access or emergency repair only.

How thick should my concrete slab be?

Standard guidance:

Below 100mm cracks easily. Above 200mm wastes material unless engineered for load.

Do I need to wait 28 days before walking on concrete?

Walking on concrete: 24–48 hours after pour. Driving light vehicle: 7+ days. Full structural loading: 28 days. The 28-day figure is when concrete reaches design strength. For most domestic applications, normal use OK after 7 days; avoid heavy point loads.

Will my driveway crack?

Some hairline cracking is normal in unreinforced concrete (shrinkage cracks during cure). Major cracking results from: poor sub-base preparation, insufficient thickness, no/wrong reinforcement, frost during cure, or excessive load. A properly specified and laid driveway has expansion joints every 4–6m to control crack location.

Do I need Building Regulations for a garden slab?

No for: paths, driveways, shed bases, garden walls under 1m, garage bases for non-habitable buildings. Yes for: foundations of habitable buildings, garage attached to house, conservatory base. Always confirm with Building Control before starting structural work.

Regulations & Standards