Summary
Bathroom suite installation is the most variable kitchen-and-bathroom job in pricing. The "suite" itself (bath, basin, WC) has a wide retail range — £200 to £4,000+ — and the labour to fit that suite is broadly independent. A £200 budget suite and a £2,500 Roca/Duravit suite both take roughly the same fitting time. Pricing the labour and the suite separately on the quote is the only way to avoid the customer confusion of "I saw a cheaper bathroom from Wickes for £999 fitted."
The pricing tier depends on layout change. A like-for-like swap on existing services is one tier; a full refurb with new tiling, new sub-floor, new layout, and a shower upgrade is another. Customers often start asking for a "swap" and progressively realise they want a refurb — qualify scope in the first conversation and price both tiers in the quote.
This guide covers labour bands by scope, materials, the regulatory framework (Water Regs, Building Regs Parts G/P/F/L), the typical sequence, common upgrades, and worked pricing examples. For tiling work specifically see bathroom tiling pricing guide (already in the corpus); for shower-specific work see shower installation pricing guide.
Key Facts
- Like-for-like swap, basic 3-piece suite (bath, basin, WC) — £900–£1,800 labour, 1.5–2 days
- Suite swap + new shower over bath (mixer or electric) — £1,200–£2,400 labour, 2–3 days
- Suite swap + full re-tile (walls and floor) — £2,500–£4,500 labour, 4–6 days
- Full bathroom refit (services moved, sub-floor, tiling, electrics) — £4,500–£9,000 labour, 7–14 days
- En-suite refit (smaller scope, shower + WC + basin) — £3,200–£6,500 labour
- Cloakroom (WC + basin only) — £600–£1,500 labour for fit; £1,800–£3,500 full refit
- Plumber day rate — £280–£420 regional, £360–£500 London
- Tiler day rate — £200–£320 regional, £260–£380 London
- Electrician day rate (Part P) — £280–£480 regional, £360–£560 London
- Bath (standard 1700mm steel) — £80–£180 supplied
- Bath (standard 1700mm acrylic) — £120–£280 supplied
- Bath (premium freestanding / cast iron) — £400–£1,500 supplied
- Basin (pedestal / wall-hung, basic) — £60–£180 supplied
- Basin (premium / countertop) — £200–£600 supplied
- Close-coupled WC (basic) — £80–£180 supplied
- Wall-hung WC + concealed cistern + frame — £250–£600 supplied
- Bath taps + bath shower mixer — £80–£250 supplied
- Basin tap (mono / mixer) — £40–£180 supplied
- WC seat — £20–£80 (rarely supplied with budget WC, often supplied with mid-range+)
- Bath waste + trap — £20–£40 supplied
- Basin waste + bottle trap — £15–£35 supplied
- Shower screen (chrome over bath) — £80–£250 supplied
- Shower enclosure (1000mm × 1000mm) — £200–£500 supplied
- Tile backer board (Marmox/Wedi 12.5mm) — £18–£32 per m² supplied
- Bathroom extract fan (BS EN 60335 compliant, 15 l/s) — £40–£140 supplied
- WRAS-approved appliance valves — £4–£8 each
- Bath panel (acrylic, plain) — £25–£60 supplied
- Bath panel (matched-finish premium) — £80–£250
- VAT — 20% standard rate
Quick Reference Table
Spending too long on quotes? squote turns a 2-minute voice recording into a professional quote.
Try squote free →| Scope | Time | Labour | Suite Materials | Other Materials | Total Fitted |
|---|---|---|---|---|---|
| Like-for-like budget swap | 1.5 days | £400–£700 | £250–£550 | £100–£200 | £750–£1,450 |
| Like-for-like mid-range swap | 2 days | £550–£900 | £600–£1,500 | £150–£300 | £1,300–£2,700 |
| Like-for-like + shower over bath | 2.5–3 days | £700–£1,200 | £700–£1,800 | £200–£400 | £1,600–£3,400 |
| Suite + full re-tile (mid-range) | 5–6 days | £1,500–£2,500 | £700–£1,800 | £900–£1,800 | £3,100–£6,100 |
| Suite + full re-tile + new shower enclosure | 6–8 days | £2,000–£3,200 | £1,000–£2,500 | £1,100–£2,200 | £4,100–£7,900 |
| Full refurb: layout change, sub-floor, tiling, electrics | 10–14 days | £3,500–£6,000 | £1,200–£3,000 | £1,800–£3,500 | £6,500–£12,500 |
| Wet room conversion (no bath, sealed floor) | 8–12 days | £3,200–£5,500 | £800–£2,000 | £1,500–£3,000 | £5,500–£10,500 |
| Cloakroom retrofit | 1.5–2 days | £450–£800 | £300–£700 | £150–£300 | £900–£1,800 |
| En-suite full refit | 6–9 days | £2,500–£4,500 | £1,000–£2,500 | £1,200–£2,500 | £4,700–£9,500 |
Detailed Guidance
Like-for-Like Swap — What's Actually In Scope
A genuine like-for-like swap:
- Isolate water supplies and drain pipework
- Remove old bath, basin, WC
- Inspect and refresh waste connections (new traps, new flexi-hoses)
- Fit new bath; level, seal to wall
- Fit new basin; connect supplies and waste
- Fit new WC; connect supply (15mm cold) and 110mm waste
- Pressure-test all connections
- Run hot/cold and flush WC; check no leaks
- Seal perimeter with sanitary silicone
- Tidy up, dispose of old suite
Realistic time: 1.5–2 days for one plumber working competently. The "1 day swap" quote is over-promised — once you account for old fitting removal, new connections, levelling, sealing and testing, it's a 1.5-day job for sure.
When Layout Changes Become Scope
The customer often starts with "just swap the bath" and progressively realises they want changes. The cost-jumping points:
- WC pan moves >300mm — soil pipe relocation; significant time + material
- Bath becomes shower enclosure — drain change, screen/door, full tile retile, floor possible falls
- Basin moves wall — new supply runs in wall, waste in or under floor
- Bath orientation change — new feed, waste, taps positioned differently
- Floor level change — new tile vs lino, may need sub-floor work
Each of these is a tier upgrade in pricing. Spell them out: "Layout change adds 2–4 days to the schedule and increases the labour quote by £600–£1,200."
Wet Room Scope
A wet room replaces a shower enclosure with a sealed, tile-or-floor-finished area with integrated falls to a linear or central drain. Scope:
- Sub-floor: existing T&G or chipboard removed; new structural deck if needed
- Tanking: full-wall and floor liquid or sheet tanking
- Falls: integral 1:50 fall to drain (BS 5385-4:2015 wet-room tiling)
- Drain: linear drain or central gully connected to soil/waste
- Tile: porcelain or stone, slip-resistant for floor
- Splashback: continuous tiling to height (typically 2.0m at shower position)
Wet rooms are significantly more expensive than shower enclosures because of the tanking and fall work. A standard 1m × 1m enclosure can be £500–£1,200; a 1.5m × 1.5m wet room is £3,500–£6,500 + suite cost.
Bathroom Electrical Scope
Bathrooms are "special locations" per BS 7671 Section 701. Electrical work is notifiable under Part P:
- Zone 0 (inside the bath/shower): no electrical equipment except SELV
- Zone 1 (above bath/shower up to 2.25m): IPX4 minimum, low-voltage where required
- Zone 2 (within 0.6m of zone 1): IPX4 minimum
- Beyond zone 2 (rest of bathroom): standard accessories permitted
Typical bathroom electrical work:
- 15 l/s minimum extract fan (mechanical extract per Part F)
- Shaver socket (special low-voltage isolating type)
- IP-rated downlight or pendant
- Heated towel rail (if electric)
- Underfloor heating (if installed)
- All RCD protected (typically 30mA)
- Notifiable to Building Control or self-certified by registered installer
Customer Sanity-Check Items
Items that often surprise customers when read on the quote:
- "Extract fan required by Part F" — many older bathrooms have no fan and customers think it's optional
- "Trickle vents in any replacement window" — Part F 2022 update affects bathroom windows too
- "Existing WC stops, valves and earth bonding will need updating" — older bathrooms often don't have equipotential bonding to current spec
- "Sub-floor replacement may be needed if rotted" — discovered when bath is lifted
- "Tile choice affects timetable" — large-format tiles, complex patterns add 30–80% to tile labour
Always include a "scope clarifications" section in the quote covering these.
Common Site Overruns
- Rotten sub-floor under bath — water has leaked for years; replace floor before fitting bath
- Old soil-stack lead bend — old lead pipework on WC waste; replace before connecting new pan
- Existing tile substrate failing — old tiles on plaster directly; new tile won't bond without tile backer board
- Customer changes specification mid-job — taps, suite item, tile colour; agree variation in writing
- Bath taps require new flexi-hoses — old hoses sometimes the wrong fitting for new taps
- Decommissioning not in scope — old toilet and bath dispose; £40–£100 disposal cost separately
Frequently Asked Questions
Should I include the suite in my quote or let the customer buy it?
Both approaches work. "Supply and fit" gives the customer one number and one accountability point — better for high-value or premium suites where coordination matters. "Labour only, customer to supply suite" puts the customer in control of brand and price — better for budget jobs.
Quote one way, with the alternative as an option: "Labour to install your supplied suite £X, OR supply-and-fit with our recommended suite £Y."
How long should a bathroom be out of service?
A like-for-like swap: 1.5–2 days out of service. A full refit: 7–14 days out of service. Customers planning around it (especially with one bathroom) need this estimate clear in writing. Some customers can use a downstairs cloakroom temporarily; others can't.
Do I need to upgrade the cold supply for a power shower?
Possibly. Standard 15mm rising main to a thermostatic mixer shower works at typical pressures (1.5–3 bar dynamic). For a power-shower pump or premium spa-jet shower, 22mm supply may be needed. Check manufacturer requirements before quoting.
What about the asbestos question?
Pre-2000 bathrooms occasionally contain asbestos in:
- Vinyl floor tiles or sheet flooring
- Old textured ceilings (artex)
- Old bath panels
- Old WC cisterns (rare but possible)
If the property is pre-2000 and a refit is planned, mention asbestos in the quote and offer a screening survey (£150–£400) before extensive demolition.
Can I work on the suite without notifying Building Control?
Like-for-like swap with no electrical alteration and no structural change: no notification needed. New circuit, new structural opening, change of use, or change of layout altering services: notification applies. Self-certification via competent person scheme (NICEIC, NAPIT, Gas Safe) covers most.
Regulations & Standards
Water Supply (Water Fittings) Regulations 1999 (SI 1999/1148) — backflow and material compliance
Building Regulations Part G — sanitation, hot water safety and water efficiency
Building Regulations Part P — electrical safety in dwellings
Building Regulations Part F — ventilation (Part F 2022 update)
Building Regulations Part L — energy efficiency (windows)
Building Regulations Part M — accessibility (relevant if accessible bathroom)
BS 7671:2018+A2:2022 — Section 701 (locations containing a bath or shower)
BS EN 60335-2-30 — particular requirements for room heaters
BS EN 14688:2018 — Sanitary appliances. Washbasins. Functional requirements and test methods
BS 5385-4:2015 — Wall and floor tiling. Code of practice for ceramic tiling in wet rooms
Approved Document G — Sanitation, hot water safety and water efficiency
bathroom tiling pricing guide — tiling scope and rates
shower installation pricing guide — shower-specific work
back flow prevention — Type AB air gap requirements
bathroom zones and ip ratings — Section 701 detail
part f extract rates — bathroom extract spec