Summary

A bathroom fitter is a multi-trade: plumber for the first and second fix, tiler for the walls and floor, carpenter for the boxing-in and the floor, decorator for the ceiling and the woodwork, and project manager for the electrician and the glazier. That is why the day rate sits above a single-trade rate and why the fixed price for a refit is the figure most customers actually compare. The trap is pricing a bathroom from a per-item list (£300 to fit a bath, £150 for a basin, £250 for the toilet) and discovering that the strip-out took a day because the old tiles were on sand and cement, the floor needed a layer of ply and a self-levelling compound before any tile went down, and the shower wall needed tanking that nobody allowed for.

The day rate is where the real costs live: the van, the tools, the public liability, the holidays, the days quoting and the days waiting for an electrician. Convert it to a fixed price only once you have surveyed the room and counted the days, with the preparation and the specialist items priced as their own lines. This guide builds the 2026 day rate, gives the regional figures, shows how it converts to a fixed price for the common bathroom sizes, lists the items that should always be separate lines, and works a standard family bathroom refit through to a quote. For the per-room cost detail see full bathroom installation pricing guide and bathroom tiling pricing guide; for the general method see pricing labour and day rate to hourly rate calculator.

Key Facts

Quick Reference Table

Spending too long on quotes? squote turns a 2-minute voice recording into a professional quote.

Try squote free →
Charge Regional (outside London/SE) South East London Notes
Day rate, bathroom fitter, own tools £220–£320 £270–£380 £320–£450 6.5–7 billable hours
Hourly equivalent £35–£50 £40–£58 £48–£65 Repairs only
Half-day minimum £150–£220 £180–£250 £200–£300 Tap, toilet, reseal
Full family bathroom refit, labour £3,500–£6,500 £4,200–£7,500 £5,000–£9,000 6–10 days
En-suite refit, labour £2,500–£4,500 £3,000–£5,200 £3,600–£6,500 4–7 days
Wet room, labour £4,500–£8,000 £5,200–£9,000 £6,500–£11,000 8–12 days
Strip-out, including disposal £300–£700 £350–£800 £450–£1,000 Skip or tip runs
Floor preparation (ply and levelling), per m² £15–£30 £18–£34 £22–£40 Plus primer
Tanking a shower enclosure £150–£300 £180–£340 £220–£400 Liquid or sheet system
Wall tiling, standard porcelain, per m² £35–£60 £40–£65 £50–£80 Labour only
Floor tiling, standard porcelain, per m² £40–£70 £45–£75 £55–£90 Labour only
Bath fitted, like-for-like, with panel £250–£400 £300–£450 £350–£550 Including waste and trap
Shower enclosure and tray fitted £350–£600 £400–£700 £500–£850 Tray bedded, screen sealed
Close-coupled WC fitted £150–£250 £170–£280 £200–£350 Like-for-like position
Electric shower on new circuit (electrician) £450–£750 £500–£850 £600–£1,000 Part P certificate included

Detailed Guidance

Building the day rate from your costs

Start with what the year costs before you earn anything. A typical self-employed bathroom fitter's overheads in 2026 look like this:

Annual cost Typical figure
Van finance or depreciation, insurance, tax, fuel, servicing £7,500–£10,500
Tools, tile cutter, consumables, replacements £1,500–£2,500
Public liability and tools insurance £600–£1,100
Phone, software, quoting app, accountancy £1,200–£2,000
Training, trade memberships, certification £300–£800
Workwear, PPE, first aid £250–£500
Total overheads £11,350–£17,400

Add the income you need to live on and to fund a pension and holidays, say £42,000–£55,000 for an experienced fitter, and divide by billable days. A fitter who works 46 weeks loses days to quoting, surveys, snagging visits and the morning the sanitaryware arrives damaged; 200–215 billable days is realistic. At £14,000 overheads and £48,000 income over 210 days the rate is £295 a day before profit, which is why the regional range starts above £220 and why anyone charging £180 is subsidising the customer out of their own pension.

Converting the day rate to a fixed price

Customers want a fixed price for a refit, and a fixed price is only safe when it is built from counted days plus separately priced risks. Survey the room and count:

Stage Like-for-like layout New layout
Strip-out and disposal 0.5–1 day 1–1.5 days
First fix plumbing, waste and supply 0.5 day 1–2 days
Floor preparation, boxing-in, studwork 0.5 day 0.5–1 day
Tanking and curing 0.5 day 0.5 day
Wall tiling (20–25 m²) 3–4 days 3–4 days
Floor tiling (4–6 m²) 0.5–1 day 0.5–1 day
Second fix: bath, WC, basin, shower, screen 1–1.5 days 1–1.5 days
Decorating, silicone, snagging 0.5–1 day 0.5–1 day
Total 7–9.5 days 8.5–12 days

Multiply by the day rate, add the electrician's price with a handling margin, add materials at trade cost plus 15–25%, and add 10–15% contingency on a pre-1980 house where the floor and the walls are unknown until the tiles come off. The common mistakes are counting the tiling at a per-metre rate that assumes a flat wall and a straight layout, and forgetting the day lost between grouting and fitting the screen, or between tanking and tiling, which the fixed price has to carry even if you fill it with another job.

Lines that should always be separate on the quote

Some items vary so much between bathrooms that bundling them into the fixed price loses money on half the jobs and overcharges the other half. Price these as their own lines, with a stated assumption and a stated rate for variation:

Tiling: where the fixed price goes wrong

The tiling is half the days on most refits and the part most likely to blow out. Output depends on tile size, layout and the number of cuts, and a bathroom is nearly all cuts: around the bath, the window reveal, the boxed soil pipe, the niche, the door frame. Standard 300 × 600 mm porcelain on a plain wall runs at 8–10 m² a day; the same tile in a bathroom with a niche and a window is 6–7 m². Herringbone or a 45° layout adds 30–50% to the labour and 15–20% to the wastage. Large-format tiles over 600 mm on one side need a flat substrate (3 mm in 2 m) and two people for anything over 1200 × 600 mm.

Substrate rules decide the preparation: BS 5385-1 limits tiling onto plaster skim to around 20 kg/m² including adhesive, direct onto plasterboard to 32 kg/m², and allows 50–60 kg/m² on cement backer board. A 10 mm porcelain is 22–25 kg/m² with adhesive, which rules out skim and makes backer board the safe choice in a shower area. Wet areas must follow BS 5385-4:2015, with tanking over plasterboard and movement joints at the internal corners and the perimeter. Put the backer board and tanking on the quote as lines; see tile backer board guide and wall tiling pricing guide.

Electrics in a bathroom: who does what

Unless you are a registered electrician, every new circuit, every shower circuit and most alterations in a bathroom are Part P notifiable and need a certificate from someone who is. The practical arrangement is to subcontract a registered electrician for the first fix (shower cable, fan, lighting, shaver socket) and the second fix and certification, and to carry their price in the quote with a 10–15% handling margin for the coordination and the risk. Section 701 of BS 7671 sets the zones: no switches or sockets other than shaver units within 3 m of the bath or shower edge, IPX4 fittings in zone 1 and 2, and 30 mA RCD protection on every circuit in the room. Downlights in zone 1 must be IPX4 and rated for the zone; a 12 V SELV fitting is the safest choice above a shower. See bathroom zones and ip ratings for the zone diagram.

Worked example: family bathroom, like-for-like layout, Midlands

A 2.1 × 2.4 m bathroom in a 1970s semi: strip out a bath, basin, WC and tiles on plasterboard, fit a new bath with a shower over, a glass bath screen, a basin and a close-coupled WC in the same positions, tile 22 m² of walls in 300 × 600 mm porcelain and 5 m² of floor, replace the extractor fan, and decorate the ceiling and the door. The customer supplies the sanitaryware and tiles.

Item Days Cost
Strip-out and two tip runs 1 £300
First fix: new waste for bath, supply extensions, check 22 mm feed 0.5 £150
6 mm ply and levelling compound to 5 m² floor 0.5 £150 + £110 materials
Tank shower end of bath, two walls to 1.8 m, 100 mm upstand 0.5 £150 + £85 materials
Wall tiling 22 m² with bath, window and niche cuts 3.5 £1,050
Floor tiling 5 m² 0.5 £150
Second fix: bath, screen, basin, WC, shower valve, wastes, traps 1.5 £450
Decorating ceiling and door, silicone, snagging 0.5 £150
Adhesive, grout, trims, backer, silicone, fixings, pipe and fittings at trade + 20% £520
Electrician: new fan on timer, two downlights, certificate (subcontract £420 + 12%) £470
Subtotal (8.5 days at £300 plus materials and subcontract) £3,735
Contingency 10% (wall condition behind old tiles) £374
Fixed price, labour and materials, excluding sanitaryware and tiles £4,109

Round it to £4,100, state the assumptions (walls sound, floor within 10 mm, customer-supplied sanitaryware on site by day one), and stage the payment: 25% on booking, 50% at the end of tiling, the balance on completion. The same job in London would be £5,600–£6,200.

Frequently Asked Questions

Should I charge a day rate or a fixed price for a bathroom refit?

A fixed price, built from counted days and separately priced risks, for any full refit. Customers will not commit to an open-ended day rate for a job that empties the only bathroom in the house, and a day rate rewards the fitter for being slow. Keep the day rate for what it is good at: small repairs, works of unknown extent (a leak under a floor), and the variation rate on the fixed-price quote. State both on the quote so the customer can see how an extra is calculated.

Can I fit the electric shower myself?

Only the plumbing. The shower circuit, the pull-cord switch and the connection are notifiable electrical work in a special location, and unless you are registered with a competent person scheme you cannot certify it. Fit the unit and the pipework, and have the electrician connect and certify. A customer whose insurer asks for the Part P certificate after a fault will not be helped by "the bathroom fitter did it".

How many days should a bathroom refit take?

Six to ten days for a family bathroom with a like-for-like layout and one fitter, with the tiling at three to four of those days; eight to twelve with a layout change or a wet room. Anything quoted at three days either has a second person on site, no tiling, or a corner cut. Tell the customer the realistic number and the two days the room is unusable while the tanking and the grout cure, and offer a temporary WC connection if it is the only one in the house.

What do I do if I find rot or a leak after the strip-out?

Stop, photograph it, and price it as a variation before touching it. The contingency in the quote covers blown plaster and a floor slightly out of level, not a rotten joist end or a soil pipe that needs replacing. A written variation with a photograph, a price and the day it adds to the programme is the difference between a paid extra and a dispute. See variation orders explained.

What should I charge for a half-day job like a tap change?

The half-day minimum: £150–£220 regionally. By the time you have travelled, isolated the supply, found the isolation valve does not close, replaced it, fitted the tap and tested it, the morning has gone, and a quoted "£60 to change a tap" is a loss. Tell the customer the minimum covers up to four hours on site and any small extra parts, and that the next hour is at the hourly rate.