Summary
Approved Document B is being amended in stages rather than reissued, and the 2026 stage is the one about tall residential buildings. The second-staircase policy was announced by the government in 2023 in the wake of the Grenfell Tower Inquiry, with the height threshold settled at 18 m after consultation (the original proposal was 30 m). It has been known about for three years and most developers of taller blocks have already been designing to it; what changed on 30 September 2026 is that it is now in the statutory guidance with a hard transitional cut-off, so a block of flats of seven storeys or more that does not have two stairs can no longer rely on the Approved Document to show compliance with Requirement B1 (means of warning and escape).
For the great majority of the trade the practical consequence is not the second stair itself — few builders of houses and extensions will ever work on an 18 m block — but three things that follow from it. First, the edition of Approved Document B in force on the date your application was deposited now matters, and you must be able to say which one applies to a job. Second, the evacuation-lift provisions and the interlocked-stair rule affect refurbishment, conversion and material-change-of-use work in existing mid-rise blocks, which is work that small and medium contractors do. Third, the 2029 stage removes the BS 476 fire-resistance classifications from the document altogether, and that will touch every fire door, every fire-stopping product and every structural fire-protection specification on every job, so the clock is now running on product re-certification.
This article explains the 2026 changes, the transitional rules, the 2025 and 2029 stages either side of them, and what each means on site for domestic, HMO, conversion and small commercial work. Where a secondary source quotes a paragraph number that could not be confirmed against the GOV.UK amendment booklet, it is marked. The primary source is the MHCLG amendment document on GOV.UK.
Key Facts
- Effective date: 30 September 2026, England only. Wales, Scotland and Northern Ireland have their own fire-safety guidance and timetables (see welsh building regulations differences guide and scottish building standards vs english building regs comparison)
- Second common stair: blocks of flats with a storey 18 m or more above ground level (measured by the Approved Document's method — from the lowest ground level adjoining the building to the finished floor level of the top storey, excluding roof-top plant) should have more than one common stair
- Interlocked / scissor stairs (two stairs stacked or interlocking within one enclosure) count as a single escape route, not an alternative means of escape
- Evacuation lifts: where a block includes an evacuation lift, it should be within an evacuation shaft comprising a protected stairway, the evacuation lift and an evacuation lift lobby that acts as a refuge for people waiting and has direct access to the protected stairway. The amendment governs design where a lift is provided; it does not itself require an evacuation lift in every building
- Transitional arrangements: the previous edition (2019 edition incorporating 2020, 2022 and 2025 amendments) may continue to apply where a building notice, initial notice or full-plans application was submitted before 30 September 2026, and the work had started and was sufficiently progressed before that date or becomes so within 18 months after it. For a new building, sufficiently progressed means permanent foundation concrete or permanent piling started; existing buildings and material changes of use have their own criteria
- 2025 stage (2 March 2025): BS 476 Parts 6 and 7 (reaction to fire) and BS 476-3 (roofs) removed as classification routes — BS EN 13501-1 and BS EN 13501-5 only; Regulation 38 fire-safety information requirements strengthened; sprinklers in all new care homes regardless of height
- 2029 stage (2 September 2029): BS 476 Parts 20–24 (fire resistance) removed from Approved Document B — BS EN 13501-2 classifications (e.g. EI 30, REI 60) only, with their own transitional provisions
- Approved Document B is guidance, not law: the legal requirements are Schedule 1 Part B of the Building Regulations 2010 (B1–B5). Following the Approved Document is one way to demonstrate compliance; a fire-engineered alternative remains possible but must be justified to the Building Control body
- Higher-risk buildings (seven storeys or 18 m, with two or more residential units) are also subject to the Building Safety Act 2022 gateway regime via the Building Safety Regulator, which sits on top of Approved Document B (see building safety act 2022)
- Volume 1 covers dwellings (houses and flats); Volume 2 covers buildings other than dwellings. The 2026 changes are to Volume 1
- Fire Safety (England) Regulations 2022 and the Regulatory Reform (Fire Safety) Order 2005 continue to govern occupied blocks; the Approved Document governs design and building work
- Domestic work unchanged: escape windows, protected stairways in three-storey houses, loft conversions, fire doors to integral garages, smoke alarms to BS 5839-6 — none of these changed in 2026
Quick Reference Table
Need to quote compliant work? squote includes relevant regulations in your quotes.
Try squote free →| Stage | Effective | What changed | Who it affects |
|---|---|---|---|
| 2020 amendments | 26 November 2020 | Combustible materials ban extended; sprinklers and wayfinding signage in blocks of flats over 11 m | Developers and contractors on blocks of flats over 11 m |
| 2022 amendments | 1 December 2022 | Secure information boxes and evacuation alert systems in blocks over 18 m; sprinkler and signage clarifications | Taller residential |
| 2025 amendments | 2 March 2025 | BS 476-6/-7 and BS 476-3 withdrawn as classification routes (Euroclass BS EN 13501-1/-5 only); Regulation 38 fire-safety information strengthened; sprinklers in all new care homes | Everyone specifying linings, cladding, roof coverings, insulation; care home builders |
| 2026 amendments | 30 September 2026 | Second common stair for blocks of flats with a storey 18 m or more; interlocked stairs = one route; evacuation shaft/lobby design for evacuation lifts | Developers, designers and contractors on new or substantially altered blocks of flats 18 m+ |
| 2029 amendments | 2 September 2029 | BS 476-20 to -24 fire-resistance classifications withdrawn; BS EN 13501-2 only | Everyone specifying fire doors, fire-stopping, structural fire protection, ductwork, glazing |
Detailed Guidance
What the 2026 amendments actually say
The amendment booklet published on GOV.UK amends the 2019 edition of Approved Document B Volume 1 (Dwellings), and consolidated versions of both volumes incorporating the 2020, 2022, 2025, 2026 and 2029 amendments have been issued so that designers can see the whole timeline in one document.
Second common stair. The guidance for means of escape in blocks of flats (Section 3 of Volume 1) now recommends that a block with a storey 18 m or more above ground has more than one common stair. Previously the Approved Document accepted a single stair for blocks of any height, relying on the "stay put" strategy and a high standard of compartmentation. Two stairs give an alternative route if one is compromised by smoke and give firefighters a stair that is not full of evacuating residents. The 18 m line is the same threshold used for higher-risk buildings under the Building Safety Act 2022 and for the combustible-materials ban.
Interlocked stairs. Two stairs interlocking or stacked within a single enclosure — a scissor stair — share walls, often share a lobby and can be compromised by the same fire. The amendment makes clear they count as one escape route for the purposes of the second-stair recommendation. A designer cannot satisfy the second-stair guidance with a scissor stair.
Evacuation lifts. Where a block includes an evacuation lift (a lift designed and powered to be used for evacuating people, particularly those who cannot use the stairs), the lift should sit within an evacuation shaft. The shaft contains the protected stairway, the lift and an evacuation lift lobby. The lobby acts as a refuge where people can wait for the lift and has direct access to the protected stairway so that, if the lift fails, those waiting are already in the protected route. The lobby and shaft must be designed in conjunction with the protected-route, smoke-control and fire-doorset guidance elsewhere in the document. Whether an evacuation lift is required at all, as opposed to how one is designed when provided, is a matter for Requirement B1 read with Approved Document M and the fire strategy. Many designers of 18 m+ blocks are now providing them as the practical means of meeting the Equality Act duty towards disabled residents.
Transitional arrangements — which edition applies to your job
The transitional arrangements follow the standard pattern for Building Regulations changes and are set out in the amending regulations and the booklet:
- Application deposited on or after 30 September 2026 — the 2026 amendments apply. No choice.
- Building notice, initial notice or full-plans application deposited before 30 September 2026, and the building work started and sufficiently progressed before 30 September 2026 — the previous edition applies to that work.
- Deposited before 30 September 2026 but not yet sufficiently progressed — the previous edition still applies provided the work is started and sufficiently progressed within 18 months of 30 September 2026, i.e. by 30 March 2028. Miss that and the 2026 amendments apply.
"Sufficiently progressed" for a new building means the pouring of permanent concrete for foundations or the permanent placing of piling. For work to an existing building or a material change of use the test is different (e.g. commencement of the relevant work). Note that the 18-month rule applies to the building on the application — a developer cannot start one block on a multi-block site and claim the whole site is sufficiently progressed; each building is assessed separately under the Building Regulations commencement rules introduced in 2023.
For a small contractor the practical rule is: ask the client or the Building Control body which edition the application falls under before you price fire-related work, and record it in the quotation. See building control and completion certificates.
What it means for domestic work
Nothing in the 2026 stage changes the guidance for:
- houses, including three-storey houses and loft conversions (protected stairway, escape windows, fire doors) — see loft conversion fire escape and part b fire
- extensions and garage conversions
- HMOs in houses (the HMO fire guidance is LACORS/local authority, read with Approved Document B) — see hmo fire safety
- smoke and heat alarm provision (BS 5839-6:2019+A1:2020) — see smoke alarms
- fire doors in domestic settings — see fire door installation
What has changed for domestic-scale work is the 2025 stage: since 2 March 2025, wall and ceiling linings, cladding, insulation and roof coverings must be classified to BS EN 13501-1 (reaction to fire) or BS EN 13501-5 (roofs); a product with only a BS 476-7 Class 1 or Class 0 certificate can no longer be used to demonstrate compliance on a new specification. If you are still specifying "Class 0" plasterboard or "Class 1" roofing, update to the Euroclass equivalent (typically A2-s1,d0 or B-s3,d2 for linings, B_ROOF(t4) for roofs) and ask suppliers for the BS EN 13501 classification report. See part b fire for the Euroclass table.
What it means for conversions and refurbishment of existing blocks
Mid-rise conversions — office to residential (see change of use office to residential), adding a storey under permitted development, or a material change of use creating flats — are where small and medium contractors meet these amendments:
- A material change of use to a block of flats triggers Requirement B1 for the whole building. If the top storey is 18 m or more and the application is deposited after 30 September 2026, the Approved Document route expects a second stair. Where that is not physically possible, a fire-engineered solution (BS 9991:2024 is the relevant code of practice) must be agreed with Building Control and, for a higher-risk building, with the Building Safety Regulator at Gateway 2.
- Adding storeys to an existing block can push the top storey over 18 m and bring the building into both the second-stair guidance and the higher-risk-building regime. Check the measured height before pricing.
- Lift replacement or installation in an existing block: if the new lift is to be an evacuation lift, the shaft and lobby design provisions apply.
- Work to a scissor-stair block does not require a second stair to be added retrospectively, but the single-route status should be recorded in the fire strategy and the Regulation 38 information.
Regulation 38 information and the golden thread
The 2025 stage strengthened the fire-safety information that must be handed to the Responsible Person at completion under Regulation 38 of the Building Regulations 2010. For any block of flats or non-domestic building, the contractor must provide information on the fire strategy, compartmentation, fire-stopping, active systems and — now — the stair and evacuation-lift arrangements. For higher-risk buildings this feeds the golden thread under the Building Safety Act (see building safety act golden thread requirements). Keep as-built records of every fire door, every penetration seal and every fire-stopping product with its BS EN 13501-2 classification; from 2029 the BS 476 numbers on older certificates will not be accepted on new specifications.
Preparing for the 2029 stage now
The 2029 removal of BS 476-20 to -24 is the stage that will affect every fire door hanger, dry liner, M&E contractor and fire-stopping installer. Fire-resistance performance will be expressed only as BS EN 13501-2 classifications — E (integrity), I (insulation), R (load-bearing), W (radiation) with minutes, e.g. EI 30 for a 30-minute fire door, REI 60 for a 60-minute load-bearing wall. "FD30" door leaf marketing names will persist, but the certificate behind them must be to BS EN 1634-1 test and BS EN 13501-2 classification. Start asking for BS EN 13501-2 classification reports on fire doors, fire-stopping, fire-rated ductwork and dampers, fire-rated glazing and structural fire protection now, because manufacturers are re-certifying and some legacy products will not be re-tested. See fire stopping and penetration seals, compartmentation and fire rated glazing.
Height measurement — getting 18 m right
The Approved Document measures height from the lowest ground level adjoining the building to the top of the finished floor of the top storey (excluding a storey consisting only of plant rooms). This is not the same as height to the roof or parapet, and on a sloping site the lowest adjoining ground level governs. A six-storey block with a 3 m storey height and a raised ground floor can be under 18 m; a seven-storey block almost never is. The same measurement method is used for the 11 m sprinkler threshold (2020 amendments) and the 18 m higher-risk-building threshold under the Building Safety Act, so one measured figure answers several questions. Record how you measured it.
Frequently Asked Questions
Does every existing block over 18 m now need a second staircase?
No. Approved Document B is guidance on how to comply with the Building Regulations when carrying out building work. It is not retrospective. An existing single-stair block that is not undergoing building work is governed by the Regulatory Reform (Fire Safety) Order 2005 and, if it is a higher-risk building, the Building Safety Act 2022 in-occupation regime — both of which require a fire risk assessment and a safety case, not a second stair. Building work to that block, particularly a material change of use or adding storeys, can bring Requirement B1 into play for the whole building, and that is where the second-stair guidance bites.
We deposited full plans in August 2026 but will not start foundations until spring 2027 — which edition applies?
The previous edition (2019 edition incorporating 2020, 2022 and 2025 amendments), provided permanent foundation concrete or piling is placed within 18 months of 30 September 2026. If the start slips past that window, the 2026 amendments apply and the design will need to be revisited. Put the deadline in the programme and tell the client in writing.
Is the second stair a legal requirement or just guidance?
Guidance. The legal requirement is Schedule 1 Requirement B1 of the Building Regulations 2010: adequate means of escape in case of fire. The Approved Document describes one way of meeting it, and a single-stair 18 m+ design deposited after 30 September 2026 would need a fire-engineered justification (BS 9991:2024 and a qualified fire engineer) to be accepted. For a higher-risk building the Building Safety Regulator is the Building Control body and has, in practice, expected two stairs since the policy was announced in 2023.
Do the 2026 changes affect Wales, Scotland or Northern Ireland?
Not directly. Approved Document B is English guidance. Wales has its own Approved Document B and has had sprinklers in all new dwellings since 2016; Scotland's Technical Handbooks already required two stairs in taller domestic buildings before England moved; Northern Ireland uses Technical Booklet E. Check the relevant national guidance for work outside England.
What should I change in my fire door and fire-stopping quotes now?
Specify and obtain BS EN 13501-2 classifications (EI 30, EI 60) and BS EN 1634-1 test evidence rather than BS 476-22 "FD30" certificates, record installed products against the Regulation 38 information, and photograph every penetration seal before it is closed in. None of that is mandatory for domestic work today, but it is the direction of travel and it costs nothing to start.
Regulations & Standards
Building Regulations 2010 (SI 2010/2214), Schedule 1 Part B — Requirements B1 (means of warning and escape), B2 (internal fire spread — linings), B3 (internal fire spread — structure), B4 (external fire spread), B5 (access and facilities for the fire service); Regulation 38 (fire safety information)
Approved Document B (Fire safety), Volume 1: Dwellings, 2019 edition incorporating 2020, 2022, 2025 and 2026 amendments — statutory guidance; the 2026 amendments took effect 30 September 2026
Approved Document B, Volume 2: Buildings other than dwellings — same amendment timeline
The Building (Amendment) Regulations giving effect to the 2026 changes and transitional provisions
Building Safety Act 2022 and the Building (Higher-Risk Buildings Procedures) (England) Regulations 2023 — gateway regime for buildings 18 m or seven storeys with two or more residential units
Regulatory Reform (Fire Safety) Order 2005 — fire safety in occupied buildings; Responsible Person duties
Fire Safety (England) Regulations 2022 — duties in multi-occupied residential buildings (wayfinding signage, lift checks, evacuation plans)
BS 9991:2024 — fire safety in the design, management and use of residential buildings; code of practice (the fire-engineering alternative to the Approved Document)
BS 9999:2017 — fire safety in the design, management and use of buildings (non-residential)
BS EN 13501-1 — reaction-to-fire classification (sole route since 2 March 2025)
BS EN 13501-2 — fire-resistance classification (sole route from 2 September 2029)
BS EN 13501-5 — roof external fire performance classification
BS EN 1634-1 — fire resistance tests for doorsets
BS EN 81-76:2025 — safety rules for lifts: evacuation of persons with disabilities using lifts (published July 2025, superseding CEN/TS 81-76:2011); the product standard behind the evacuation-lift provisions
BS 5839-1:2017 and BS 5839-6:2019+A1:2020 — fire detection and alarm systems, non-domestic and domestic
BS 9251:2021 — domestic and residential sprinkler systems
GOV.UK — Approved Document B: 2026 amendments (MHCLG amendment booklet) — primary source for the 2026 changes
GOV.UK — Fire safety: Approved Document B — consolidated volumes and all amendment documents
Fire Protection Association — Update to Approved Document B released — trade body summary
Building Safety Hub — Fire safety Approved Document B update — staged amendment timeline
Firex — Approved Document B: September 2026 changes explained — transitional arrangements and 2029 stage
HSE — Building Safety Regulator — higher-risk building gateway regime
part b fire — Approved Document B as it applies to domestic work, including the Euroclass table
building safety act 2022 — higher-risk buildings and the gateway regime
building safety act golden thread requirements — information duties for higher-risk buildings
building control — applications, notices and which edition applies
change of use office to residential — conversions that bring B1 into play for the whole building
hmo fire safety — fire safety in houses in multiple occupation
escape routes — means of escape principles
protected stairway and open plan — protected stairway design
compartmentation — compartment walls and floors
fire door installation — fire doorsets and certification
fire stopping and penetration seals — fire-stopping products and classification
sprinkler systems — sprinklers in blocks over 11 m and care homes