Summary

Second fix carpentry is where a job either looks professionally finished or doesn't — there's nowhere to hide a bad mitre on a skirting joint or a door hung with an uneven gap the way there is with a stud wall buried behind plasterboard. It's also the stage most affected by what other trades left behind: pipework that wasn't notched cleanly, an electrician's back box sitting proud of the finished plaster line, or a floor that isn't quite where the specification said it would be. A second fix carpenter has to read and adapt to all of that while still hitting tight tolerances on visible joinery.

This article is a consolidated technical reference across the four main second fix carpentry elements — skirting, architrave, door hanging, and staircase finishing. For the broader cross-trade sequencing context (how second fix carpentry fits alongside plumbing, electrical, and heating second fix), see first fix second fix. For deep technical detail on each individual element, see the linked articles in Related Articles below — this piece is the map, not the full territory on any one topic.

Key Facts

Quick Reference Table — Second Fix Carpentry Elements

Spending too long on quotes? squote turns a 2-minute voice recording into a professional quote.

Try squote free →
Element Key dimension/tolerance Typical fixing method Standard
Skirting board 100–225mm height, scribed internal / mitred external corners Plugs+screws (masonry), adhesive+pins (board), nail gun (timber stud) BS 8000-5
Architrave 5–6mm reveal, mitred corners Adhesive + panel pins, punched and filled BS 8000-5
Internal door 2–3mm sides/head, 8–10mm bottom (carpet) 75–100mm butt hinges (2no. standard, 3no. fire door) BS 8214:2016 (fire doors)
Staircase — rise/going Max rise 220mm, min going 220mm Housed/glued/wedged stringer joints Approved Document K
Staircase — guarding 900mm alongside flight, 1100mm on landings Newel post fixed to structure, spindles at 100mm sphere spacing Approved Document K
Staircase — handrail One side minimum for domestic stairs over 1m wide (both sides often specified) Bracket-fixed to wall studs/noggins or newel-to-newel Approved Document K
Window board 3mm per 600mm expansion allowance (MDF) Silicone bead to sill, scribed to reveal BS 8000-5

Detailed Guidance

Skirting boards

Skirting protects the base of the wall, covers the plaster/floor junction, and is one of the most visually continuous lines in a room — any inconsistency in height or gap is immediately obvious.

Architrave

Architrave covers the joint between the door lining and the plastered wall, and sets the finished visual frame around every door opening in the property.

Door hanging

Hanging doors correctly is a combination of accurate clearances, correct hinge positioning, and getting the door to close and latch cleanly without binding.

Staircase second fix

While the staircase carcass (strings, treads, risers, newel posts) is generally first fix work, the visible finishing elements — balustrade, spindles, handrail, and newel caps — are second fix, completed after plastering and often after the main flooring is down.

Window boards

Often grouped with second fix carpentry even though timing can vary — window boards are sometimes fitted at first fix (before plastering, scribed into the reveal) and finished/trimmed at second fix, or fitted entirely at second fix depending on the sequence used.

Coordinating second fix carpentry with other trades

Second fix carpentry deliberately runs after electrical and plumbing second fix in the standard sequence, for good reason:

Frequently Asked Questions

Why is the internal corner on skirting scribed rather than mitred?

Internal wall corners in real buildings are very rarely exactly 90°. A mitred internal joint (two 45° cuts) will show a visible gap wherever the actual angle is off-square. A scribed (coped) joint — cutting the second piece along the profile of the first with a coping saw — stays tight regardless of the exact corner angle, which is why it's the standard method for internal skirting and architrave corners in the UK.

Can second fix carpentry start before the walls are fully dry from plastering?

No — fixing skirting, architrave, and doors into walls that are still drying risks fixings pulling loose as the plaster continues to shrink and cure, and any adhesive-fixed elements (architrave, some skirting) may not bond properly to a still-damp surface. Allow the plasterer's stated drying time (typically 1–3 weeks depending on conditions) before starting second fix carpentry.

What's the difference between a standard internal door and a fire door in terms of second fix work?

A fire door (FD30/FD60) has a tighter gap tolerance (3mm all round vs 2–3mm sides/head, 8–10mm base on a standard door), requires three hinges rather than two, needs intumescent strips (either frame-fitted or door-edge-integrated), and typically a certified self-closer. Fitting a fire door with standard-door clearances or hardware invalidates its fire rating even if it looks correctly hung.

How much movement should I allow when fitting MDF skirting and architrave?

Don't force joints bone-tight, especially on long runs — leave a slight allowance and avoid fully sealing both ends of a run with adhesive or silicone, which prevents natural expansion and contraction and can cause joints to open or bow over a heating season.

Does second fix carpentry need building control inspection?

Not typically for skirting, architrave, and door hanging on standard domestic work, but staircase alterations (new stairs, or changes to an existing staircase's geometry or guarding) usually do fall under Building Regulations and should be checked against Approved Document K requirements and, where structural, inspected by building control alongside the wider project.

Regulations & Standards