Summary

The word "diversity" causes real confusion in EV charger load calculations, because it means something different here than it does everywhere else in domestic electrical design. For nearly every other domestic load — lighting, sockets, cookers, showers — BS 7671 Appendix 1 gives you a percentage to knock off the full connected load, on the statistical basis that not everything runs at once. For a single EV charger, that discount doesn't exist: the table entry for electric vehicle chargers is 100%, full stop, because a charger left plugged in overnight is treated as continuous, sustained demand, not intermittent use.

This calculator is the practical companion to electrical load, which covers the full domestic ADMD calculation across all load types. Here the focus narrows to the EV-specific questions that come up on almost every quote: how much does adding a charger actually add to the property's demand, when does that push an existing supply over its limit, and what changes when dynamic load management or multiple charge points are involved. None of this replaces a proper site assessment — see ev charger and part s ev charging for the installation and notification requirements — but it gives you the numbers to work through before you're on site.

A note on citation: the diversity guidance referenced throughout this article draws on BS 7671:2018+A4:2026 Appendix 1 and Section 722, and the IET Code of Practice for Electric Vehicle Charging Equipment Installation. The Code of Practice has been through several editions since it was first published; always check the current edition with the IET before relying on a specific clause number **** — the diversity principles below are stable across editions, but clause references may shift.

Key Facts

Quick Reference Table — Adding a Single EV Charger to Existing ADMD

Got your quantities? squote builds the full quote with labour, materials and markup.

Try squote free →
Existing Property ADMD Supply Rating + 7.4kW Charger (32A, no DLM) New Total Within Supply? Action
40A 60A (13.8kW) +32A 72A No DLM required or supply upgrade
45A 80A (18.4kW) +32A 77A Yes (marginal) Proceed, monitor; DLM still advisable
52A 80A (18.4kW) +32A 84A No Supply upgrade to 100A, or DLM, or limit to 16A charger
60A 100A (23kW) +32A 92A Yes Proceed
70A 100A (23kW) +32A 102A No (marginal) DLM recommended, or reduce to 16A (3.6kW) charger
85A 100A (23kW) +32A 117A No Supply upgrade or DLM mandatory

These figures assume no diversity discount on the charger itself, consistent with BS 7671 Appendix 1. "Within supply" is judged against continuous rated capacity, not a momentary peak.

Detailed Guidance

Step 1 — Establish the existing property ADMD

Before adding the charger, calculate the property's current ADMD using the full domestic diversity table in electrical load — lighting at 66%, cooker per the BS 7671 formula, shower(s) at 100% of the largest plus a reduced allowance for additional units, ring finals at 100% first ring + 40% additional rings, and so on. This gives you the baseline figure the charger will be added to.

Worked example — 3-bed semi, existing ADMD calculation:

Existing ADMD = 5.7 + 42 + 43.5 + 13 = 104.2A

This property already exceeds an 80A supply on ADMD alone, before any EV charger is considered — a common finding on older properties with an electric shower and no gas heating. Confirm the actual supply fuse rating before proceeding.

Step 2 — Add the EV charger at 100%, with no diversity

Add the charger's full rated current — 32A for a 7.4kW single-phase unit — directly to the existing ADMD figure. Do not apply any percentage reduction at this stage, regardless of how "unlikely" it seems that the shower, the charger and the immersion heater will all run simultaneously; BS 7671 Appendix 1 does not offer a diversity allowance for EV chargers, precisely because overnight charging is a sustained multi-hour load that can coincide with any other overnight or morning load.

Continuing the example: 104.2A (existing) + 32A (charger) = 136.2A

This is well beyond even a 100A supply. The property needs either a DLM-managed charger, a reduced-rate 16A (3.6kW) charger, or a DNO discussion about supply capacity — a straightforward 32A charger install is not viable here without one of those interventions.

Step 3 — Decide between DLM, a lower-rated charger, or a supply upgrade

Where the raw arithmetic (Step 2) exceeds the supply's continuous rating, three options exist:

Option A — Dynamic Load Management (DLM). A CT clamp on the incoming supply monitors real-time household demand and the charger's control electronics reduce or pause output to keep total demand within the supply limit. This doesn't change the BS 7671 diversity calculation on paper, but it is the recognised engineering solution that makes an install viable in practice on a constrained supply. Document the DLM device's make, model and settings in the installation certificate, since this is the safety justification for proceeding on a supply that the raw ADMD figure says is inadequate.

Option B — Reduce the charger to 16A (3.6kW). Halves the charger's contribution to ADMD (16A instead of 32A) at the cost of roughly doubling charge time. Continuing the example: 104.2A + 16A = 120.2A — still tight against a 100A supply, illustrating that a lower-rated charger alone doesn't always solve a heavily loaded property.

Option C — DNO supply upgrade. Request an upgrade from the DNO (commonly 80A to 100A, sometimes single-phase to three-phase for heavily loaded all-electric properties). Standard single-phase upgrades are often free or low-cost from the DNO; three-phase upgrades are a significant cost (£2,000–£8,000) and a multi-week to multi-month lead time — see ev charger pricing guide for full cost detail.

Step 4 — Multiple charge points on a shared supply

Where more than one charge point shares a single incoming supply — a house with two EVs on separate chargers, an HMO with a shared driveway, a small block of flats, or a workplace car park — you cannot simply multiply the single-charger 100% figure by the number of chargers and expect the DNO connection to support it. This is where genuine diversity across multiple charge points comes in, but it is not a fixed BS 7671 table percentage — it is assessed through:

Worked example — small workplace car park, 6 charge points, 100A three-phase supply available for EV charging (after other site loads accounted for):

Never present a multi-charger diversity assumption to a customer or building control as if it were a fixed BS 7671 percentage — it is a system design outcome that must be engineered and documented for the specific site, not read off a table.

Frequently Asked Questions

Why doesn't BS 7671 give a diversity discount for a single EV charger like it does for a shower?

Because the risk profile is different. A shower runs for a few minutes; even if several household members shower in sequence, the overlap is brief, so a diversity allowance reflecting "not everyone showers at once" is statistically reasonable. An EV charger left plugged in can run continuously for 6–10 hours overnight, coinciding with any other overnight load (immersion heater, storage heaters) for the full duration — there's no statistical basis for assuming it won't be at full demand for the period it's connected.

If I fit a DLM-capable charger, can I write a reduced ADMD figure on the certificate?

You should document what the DLM device actually does and the maximum current it will permit under worst-case conditions, rather than writing an arbitrary reduced figure. The safety case for a DLM installation on a constrained supply rests on the device's real-time management functioning correctly, not on a paper diversity calculation — make sure the certification reflects the device's specified operating limits, not an assumed "typical" reduced demand.

Does the property's existing supply always need upgrading if ADMD plus the charger exceeds it?

Not always — a DLM-managed charger or a reduced-rate 16A charger can both make an install viable without a DNO supply upgrade, and are frequently cheaper and faster than waiting for a three-phase upgrade. Which option is right depends on the customer's actual charging needs (how much daily range they need replenished overnight) versus the cost and lead time of a supply upgrade — this is a conversation to have before committing to a specification, not an automatic escalation to "you need a bigger supply."

Do heat pumps and EV chargers compound the same way?

Yes — heat pumps are also assessed at 100% of rated input when running, with no diversity discount, for the same reason as EV chargers: sustained, potentially overnight or all-day operation. A property adding both an ASHP and an EV charger should have both added at their full rated current to the existing ADMD, and the combined figure checked against supply capacity — this combination is one of the most common triggers for a genuine need for load management or a three-phase supply in all-electric retrofits.

Regulations & Standards