Summary

Sub-base depth is the single biggest driver of whether a driveway lasts 25 years or fails within three winters. It is also the layer that's easiest to skimp on, because once it's covered by blocks, tarmac or a concrete slab, nobody can see whether it was done properly — until the driveway starts to rut, sink, or crack under wheel loads.

The confusion tradespeople and homeowners run into is that "sub-base depth" isn't one number. It depends on what's going on top (block paving, tarmac, resin, concrete slab), what the vehicle loading will be (car only vs delivery vans vs occasional HGV), what the subgrade is like underneath (firm sand/gravel vs soft clay), and whether the surface needs to be permeable for SuDS compliance. Getting any of these wrong either wastes money (over-specifying depth on a firm subgrade) or causes early failure (under-specifying on clay).

This calculator gives the reference depths by scenario, the compaction rule that catches out most self-builders and general builders (compacting Type 1 in a single thick layer instead of 100mm lifts), and worked volume/tonnage examples so you can order the right amount of aggregate first time.

Key Facts

Quick Reference Table

Got your quantities? squote builds the full quote with labour, materials and markup.

Try squote free →
Driveway Type Sub-Base Material Minimum Compacted Depth Notes
Pedestrian path / patio MOT Type 1 100mm Light foot traffic only
Domestic car driveway MOT Type 1 150mm Standard for block paving, most surfaces
Occasional HGV / shared access MOT Type 1 200mm+ Consider geogrid on marginal subgrade
Tarmac driveway MOT Type 1 150mm Plus 50mm binder + 25-30mm surface course on top
Concrete slab driveway Compacted hardcore/Type 1 100–150mm Plus DPM and reinforced slab
Permeable block paving (SuDS) MOT Type 3 (no fines) 150–250mm Depth set by infiltration/attenuation design
Clay/soft subgrade (any type) As above + 50–100mm +50–100mm Add geotextile separation membrane
Resin bound on existing base N/A (uses existing base) N/A Only viable if existing base is sound

Detailed Guidance

Working Out How Much Sub-Base You Need

The calculation has three steps: establish the required compacted depth for the driveway type and subgrade, calculate the compacted volume, then convert to a tonnage order (aggregate is sold by weight, not volume).

Step 1 — depth. Pick the depth from the table above based on use (pedestrian, car, heavier) and subgrade condition (firm vs clay/soft).

Step 2 — volume. Volume (m³) = Area (m²) × Depth (m).

Step 3 — tonnage. Tonnage = Volume (m³) × bulk density (tonnes/m³). Use approximately 2.0–2.2 t/m³ for Type 1, 1.5–1.6 t/m³ for Type 3 — but always confirm with the merchant, since actual density varies by source material and moisture content.

Add 10% to the final tonnage for waste, over-dig and compaction variance.

Worked Example 1: Standard Domestic Driveway

A 40m² driveway for a family car, firm sandy subgrade, block paving finish.

Compact in two 75mm lifts (or one 100mm + one 50mm lift) with a vibrating roller, not a hand plate — Type 1 needs the mass of a roller to achieve full density at this depth.

Worked Example 2: Driveway on Clay Subgrade

A 60m² driveway, clay subgrade identified during excavation (sticky, plastic when wet), tarmac finish.

Worked Example 3: Permeable (SuDS) Block Paving

A 55m² driveway needing SuDS compliance because it's over the 5m² impermeable threshold at the front of the house, with moderate infiltration ground conditions.

Excavation Depth — Don't Forget the Full Build-Up

Sub-base depth is only one part of total excavation. Total dig depth = sub-base + laying course (if block paving, typically 30mm sharp sand) + surface thickness (block, slab, or binder/surface course) + 5mm settlement tolerance.

Example: 150mm sub-base + 30mm sand + 80mm blocks = 260mm total excavation for a standard block-paved car driveway. See block paving installation for the full layer-by-layer specification.

When to Get a Site-Specific Assessment Instead of Using Standard Depths

The standard depths in this article assume a reasonably firm subgrade (CBR broadly 2% or above). If any of the following apply, don't rely on the table — get a geotechnical assessment or at minimum a trial pit and CBR estimate before ordering material:

Frequently Asked Questions

Can I use less sub-base if I'm only doing a small patio, not a driveway?

Yes — pedestrian-only areas (patios, paths) need only 100mm of compacted Type 1, versus 150mm for a car driveway. The extra depth for driveways exists specifically to spread vehicle wheel loads; foot traffic doesn't generate that loading.

Do I need a different sub-base for resin bound driveways?

Resin bound surfacing itself is only 15–18mm thick and relies entirely on the strength of whatever is beneath it. If you're resurfacing an existing sound tarmac or concrete driveway, no new sub-base is needed. If you're building a new resin driveway from scratch, you need the full tarmac or concrete construction (including its own sub-base) first — resin is a surface finish, not a structural layer.

What happens if I compact a 200mm sub-base in one go instead of two layers?

The vibrating plate or roller can only achieve full compaction density in the top 100–150mm of any single lift. Compact 200mm in one pass and the lower half stays loose. Under repeated vehicle loading, the compacted crust eventually presses down into the loose material beneath, causing visible rutting and depressions — usually appearing within 6–18 months, concentrated under wheel tracks.

Is MOT Type 1 the same everywhere in the UK?

MOT Type 1 is a specification (crushed, well-graded aggregate to SHW Series 800), not a single product from one quarry — the exact stone (limestone, granite, recycled) and therefore the exact bulk density varies by region and supplier. Always confirm bulk density (tonnes per m³) with your specific merchant before finalising a tonnage order, especially on larger jobs where a density error compounds into a meaningful cost difference.

Do I need geotextile membrane under every driveway?

Not for a firm subgrade. Geotextile separation membrane becomes necessary when the subgrade is soft, wet, or fine-grained (clay, silt) — its job is to stop those fines migrating up into the sub-base voids over time, which would otherwise reduce the sub-base's load-bearing capacity. It's also standard practice under permeable (Type 3) sub-bases to keep the open-graded aggregate free of fines that would clog it.

Regulations & Standards