Summary

Getting the DPC to the correct height above ground is a setting-out calculation done on nearly every new masonry job — new build, extension, garden wall with a damp-sensitive structure above it, or a replacement DPC on an existing wall. The regulation itself is simple (150mm minimum), but translating that into "how many courses do I lay before I put the DPC in" requires converting a millimetre clearance figure into whole brick or block courses, and then checking that the result also satisfies the second, less-quoted requirement: the DPC has to end up at the right level relative to the finished floor level and the floor's damp proof membrane (DPM), so the two can lap together properly.

Get this wrong in either direction and the consequences are different. Set the DPC too low (or let finished ground level creep up after landscaping) and the DPC is bridged — moisture tracks straight over the top of it into the wall, defeating the entire point of installing it. Set the DPC too high relative to the floor level and the DPC-to-DPM lap either fails to form properly or leaves a gap where damp can bridge internally at the wall/floor junction.

This calculator covers converting the 150mm minimum clearance into brick and block courses, handling sloping sites with stepped DPC courses, coordinating DPC height with the floor DPM, and the common site errors — usually final ground levels creeping up after the DPC is set — that cause damp problems years after completion. For the products and installation detail behind the DPC itself, see dpc dpm materials; for retrofit DPC on existing walls where the level is already fixed, see dpc replacement.

Key Facts

Quick Reference Table

Got your quantities? squote builds the full quote with labour, materials and markup.

Try squote free →
Courses (brick, 75mm each) Cumulative Height Meets 150mm Minimum? Typical Use
1 75mm No Below minimum — do not set DPC here
2 150mm Yes — exactly at minimum Acceptable but no margin for ground level creep
3 225mm Yes — with margin Commonly recommended practical minimum
4 300mm Yes — comfortable margin Sloped or exposed sites, or where paving is expected later
5 375mm Yes High-exposure sites, coastal, or heavy rainfall areas
6 450mm Yes Sites with significant expected ground level rise (new landscaping)
Block Courses (225mm each) Equivalent Brick Courses Cumulative Height
1 3 225mm
2 6 450mm
3 9 675mm

Detailed Guidance

Step 1: Establish the datum and the target clearance

Work from finished floor level (FFL) as the fixed datum where possible, since this is usually set early and confirmed on the drawings, whereas finished external ground level often isn't fixed until landscaping happens much later in the build programme. From FFL, establish the target external ground level (from the drawings or levels survey), and confirm the vertical distance between them. The DPC height is then set by working down from FFL by the agreed number of courses, while separately checking that this lands at least 150mm above the target ground level.

Step 2: Convert the required clearance into courses

Divide the required clearance (150mm minimum, or a larger margin figure) by the 75mm course height and round up to the next whole course — you cannot lay a fractional course, so 150mm ÷ 75mm = exactly 2 courses (no rounding needed), while a target of 200mm would round up to 3 courses (225mm), not down to 2 (150mm), since rounding down would breach the minimum.

Worked example: A specification calls for 200mm minimum clearance (a common practical margin above the 150mm statutory figure) on a site where finished ground level is confirmed.

Step 3: Handle a height that doesn't divide evenly

Real setting-out heights rarely land on a clean multiple of 75mm, because the DPC height also has to satisfy the separate constraint of aligning with the finished floor level and the floor DPM. Where the total distance from the footing/foundation top to the DPC course doesn't divide evenly by 75mm, there are three practical options:

  1. Adjust the mortar joint thickness slightly — within a ±3mm per joint tolerance, spread across several courses, to absorb a small discrepancy (a 15mm shortfall over 5 courses is only 3mm extra per joint, invisible in the finished brickwork).
  2. Use a brick-on-edge (soldier) course — at 102.5mm high, a soldier course can be introduced as a one-off levelling course to take up a larger discrepancy that a simple joint adjustment can't absorb.
  3. Adjust the foundation/footing top level — on a new build where the footing itself hasn't been cast yet, the simplest fix is to set the footing top level so that a whole number of standard courses reaches the DPC level exactly — this is the preferred approach whenever it's still possible, since it avoids any non-standard coursing in the finished wall.

Step 4: Coordinate DPC height with the floor DPM

The wall DPC and the floor's damp proof membrane (DPM) must be physically continuous at the wall/floor junction — a DPC that's correctly positioned relative to external ground level but poorly coordinated with the internal floor build-up creates a gap where damp can bridge internally, even though the external clearance rule is satisfied. The general principle: the wall DPC should be at, or below, the level of the top of the floor slab/oversite, with the floor DPM's upstand lapping a minimum 150mm up the wall face to meet or overlap the wall DPC. On a solid ground floor, this typically means the DPC course sits 1–2 brick courses below finished floor level; on a suspended timber floor, the relationship is similar but coordinated with the joist bearing level instead. Confirm the specific detail against the structural engineer's or architect's drawing rather than assuming a fixed course count — the exact relationship varies with floor type and construction sequence. See dpc dpm materials for the DPC/DPM continuity and lap requirements in full.

Step 5: Stepped DPC on sloping sites

Where a boundary or wall runs along a sloping site, a single continuous DPC course would either be far too high above ground at the low end or below the 150mm minimum at the high end. The standard solution is a stepped DPC — the DPC steps up in whole-course increments (commonly 2–4 courses, i.e. 150–300mm per step) at intervals along the run, keeping the internal floor level constant while maintaining at least 150mm clearance to ground at every point along the slope.

Worked example: A garden wall runs 12m along a slope that falls 450mm from one end to the other, with a design requirement to maintain internal floor level constant (e.g. where the wall forms part of a building's external envelope).

Steps in brickwork DPC are usually detailed with an angled or right-angled brick cut at the step itself, and the DPC material itself is dressed to follow the step rather than left as a flat sheet across a level change — check the specific DPC product's flexibility and manufacturer guidance for stepped detailing.

Step 6: Verify after landscaping — not just at DPC installation

The 150mm clearance is frequently correct at the point the DPC is laid but compromised later when landscaping, paving, or planting raises the ground level against the wall. Confirm with the client or landscaper what the final external levels will be before finalising the DPC course, and build in a working margin (225mm rather than the bare 150mm minimum) wherever the final landscaping design isn't yet fixed. This single step prevents the most common cause of DPC bridging identified in retrofit damp diagnosis work — see paving near dpc level for the specific rules around paving laid against an existing DPC.

Frequently Asked Questions

Is 150mm always enough, or should I always build in more?

150mm is the statutory minimum under Approved Document C, not a recommended target. In practice, most experienced bricklayers set out for 3 courses (225mm) as standard, and more (4–6 courses, 300–450mm) on exposed sites, high-rainfall areas, or anywhere landscaping is expected to raise ground level after construction. The extra cost of one or two additional courses of brickwork is trivial compared to the cost of a bridged DPC being diagnosed and remediated years later.

What happens if my DPC course doesn't align with a whole number of courses to the finished floor level?

Use the mortar joint tolerance (±3mm per joint) to absorb small discrepancies spread across several courses, or introduce a single brick-on-edge (soldier) course at 102.5mm to take up a larger one-off difference. On a new build where the footing hasn't been cast, the cleanest solution is to set the footing top level so a whole number of standard 75mm courses reaches the DPC level exactly, avoiding the need for either workaround.

Do I need to step the DPC on every sloping site, or only steep ones?

Step it whenever a single, level DPC course would fall below the 150mm minimum clearance at any point along the run — this is a function of the actual ground fall along the specific wall, not a fixed slope-angle threshold. Even a gentle slope over a long wall run can accumulate enough fall to require one or two steps; measure the actual ground levels at both ends (and at intermediate points on a long or uneven run) before assuming a level DPC will work throughout.

Does the 150mm rule apply to DPC in a garden wall the same way it applies to a house wall?

Yes — Approved Document C's 150mm minimum clearance applies to DPC in masonry generally, and the principle of avoiding a bridged DPC is exactly the same whether the wall is part of a habitable building or a free-standing garden wall. The consequence of getting it wrong differs (a damp garden wall is a durability issue rather than an internal damp problem for a resident), but the setting-out calculation is identical.

Can I check whether an existing wall's DPC height is compliant just by counting courses?

Yes, as a first check — count the brick courses from the current external ground level up to the visible DPC line (often a slightly different mortar colour or a visible membrane edge) and multiply by 75mm (or measure directly with a tape if the DPC is visible). If the result is under 150mm, or if ground level has clearly risen since construction (raised flower beds, added paving), the DPC is very likely bridged and this should be investigated as part of any damp diagnosis — see dpc replacement for full diagnosis and remediation options before assuming a chemical injection retrofit is required.

Regulations & Standards