Summary
Every pricing conversation eventually comes down to the same question: who carries the risk if the job takes longer than expected? Day work and fixed price are two different answers to that question, and tradespeople who pick the wrong one for a given job either lose money on overruns they didn't price for, or lose the job entirely by quoting an inflated fixed price to cover uncertainty they could have avoided pricing for in the first place.
The common mistake is treating this as a personality choice — "I always quote fixed price because customers like certainty" or "I always do day work because I got burned on a fixed quote once." Neither is a pricing strategy; they're habits that ignore the actual risk profile of the job in front of you. The right question for every job is: how confident am I, before I start, that I know exactly what's involved? A bathroom refit with the tiles chosen, the suite ordered, and no structural unknowns is a very different risk proposition from "re-plaster this ceiling" on a Victorian house with an unknown lath condition behind it.
This calculator sets out how to quantify that risk and translate it into a number — either the expected day-work bill, or the risk-adjusted fixed price that protects the same target profit margin set out in pricing guide. Getting the risk premium right (not guessing it) is what separates a sustainable fixed-price book of work from one that quietly loses money on every third job.
Key Facts
- Day work (time and materials) bills for actual hours/days worked plus materials at cost-plus markup — the tradesperson carries zero risk of underestimating the job
- Fixed price bills a single agreed sum regardless of how long the job actually takes — the tradesperson carries 100% of the risk of underestimating scope, time, or complications
- The deciding factor is scope certainty, not job size or trade — a small job with unknown conditions (opening up a wall, unknown subfloor) can be a worse fixed-price candidate than a large job with a fully specified scope
- Risk premium on fixed price — the amount added above the expected cost-plus figure to cover the probability and cost of overruns; typically 10-20% for moderate uncertainty, rising toward 25-35%+ for high-uncertainty jobs (opening up fabric of unknown condition, work on pre-1920s buildings, anything "subject to what we find")
- Legally, a "quote" is binding and an "estimate" is not — under consumer protection law, using the word "quote" for a fixed price creates a binding commitment at that figure (barring genuinely unforeseeable circumstances), while an "estimate" signals the figure may change; using the wrong term for the pricing model chosen is a common source of disputes
- A written day rate and estimated-days figure protects both parties on day work — stating "I expect this to take 3-4 days at £280/day, and will tell you immediately if that changes" gives the customer a budget expectation even though the final bill is time-based
- A "not-to-exceed" cap is a hybrid model — day-rate billing with an agreed maximum ceiling, giving the customer price certainty while still paying the tradesperson for actual time up to that ceiling; a smaller risk premium than full fixed price since the tradesperson still captures savings if the job finishes early
- Variance drives the premium, not just cost — two jobs with the same expected cost but different variance (one tightly specified, one "we think it's just a repair but won't know until we open it up") should carry different risk premiums even if their most-likely cost is identical
- Staged/milestone payments reduce cash-flow risk on longer fixed-price jobs — a separate consideration from the day-work-vs-fixed decision itself, but commonly paired with fixed pricing on multi-week jobs
- Discovered conditions mid-fixed-price-job need a documented variation process, not a renegotiated verbal figure — agree and record the scope change and its cost before doing the extra work, not after
- Consumer Rights Act 2015 requires that pricing information given to consumers is clear and not misleading — whichever model is used, the customer must understand upfront whether the figure is fixed or will vary with time
- CIS deduction treatment is unaffected by the pricing model — day work and fixed-price subcontractor payments are both subject to CIS where applicable; see cis deduction calculator
Quick Reference Table — Scope Certainty vs Recommended Model
Got your quantities? squote builds the full quote with labour, materials and markup.
Try squote free →| Scope Certainty | Example | Recommended Model | Typical Risk Premium (if fixed) |
|---|---|---|---|
| Very high — fully specified, no unknowns | New-build kitchen fit-out from an agreed design | Fixed price | 5-10% |
| High — minor unknowns, low cost impact | Bathroom refit, suite and tiles already chosen | Fixed price | 10-15% |
| Moderate — some unknowns, moderate cost impact | Re-wire of a house with partial access to voids | Fixed price (with premium) or not-to-exceed | 15-25% |
| Low — significant unknowns, high cost impact | Opening up a solid wall of unknown construction | Day work or not-to-exceed | 25-35%+ if fixed at all |
| Very low — scope cannot be assessed until work starts | Diagnostic/exploratory repair, "see what's underneath" | Day work only | Not applicable |
Detailed Guidance
Step 1 — Assess scope certainty honestly
Before pricing, separate what you actually know from what you're assuming. List the specific unknowns: Is the subfloor condition confirmed? Has the wall been opened up to check for services? Is the exact finish/spec agreed with the customer, or still "to be decided"? Each genuine unknown adds variance, and variance — not the size of the job — is what should push you toward day work or a larger risk premium.
Step 2 — Calculate the expected day-work cost
Expected cost = (Most likely days × day rate) + materials at cost-plus markup, using the breakeven day rate methodology from pricing labour. This is your baseline "most likely" figure regardless of which model you ultimately quote.
Example: A re-plastering job estimated at 3-5 days (most likely: 4 days) at a £280/day rate = £1,120 labour + £180 materials = £1,300 expected cost.
Step 3 — Calculate the risk-adjusted fixed price
Fixed price = Expected cost × (1 + risk premium), where the risk premium reflects the variance identified in Step 1, not a flat figure applied to every job regardless of its actual uncertainty.
Example (same job, moderate uncertainty — lath condition behind the old plaster unknown): £1,300 × 1.20 (20% premium) = £1,560 fixed price.
Step 4 — Worked example: comparing the two models
WORKED EXAMPLE: RE-PLASTERING JOB WITH UNKNOWN LATH CONDITION
================================================================
Most likely scenario (60% probability): 4 days, £1,300 total cost
Overrun scenario — rotten lath found (40% probability): 6 days, £1,850 total cost
EXPECTED VALUE (probability-weighted):
(0.60 × £1,300) + (0.40 × £1,850) = £780 + £740 = £1,520
DAY WORK OUTCOME:
Customer pays actual cost in either scenario — £1,300 or £1,850.
Tradesperson's margin is protected in both cases.
FIXED PRICE AT A 20% PREMIUM ON THE MOST-LIKELY FIGURE:
£1,300 × 1.20 = £1,560 quoted
If the most-likely scenario happens (60% of the time):
£1,560 charged vs £1,300 actual cost = £260 extra margin
If the overrun scenario happens (40% of the time):
£1,560 charged vs £1,850 actual cost = -£290 shortfall
Average outcome across many such jobs:
(0.60 × £260) + (0.40 × -£290) = £156 - £116 = +£40 average margin
✓ The 20% premium roughly breaks even against the expected-value
calculation here — on a job with this much lath-condition
uncertainty, a tradesperson doing many similar jobs would do
better either raising the premium toward 25-30%, or simply
quoting day work and letting the customer carry the variance.
This is the core lesson: a risk premium that looks generous on paper can still barely cover genuine uncertainty once you run the probability-weighted numbers — which is exactly why day work exists as an option, not a fallback.
Step 5 — Consider the not-to-exceed hybrid
Where a customer wants price certainty but the job has moderate uncertainty, a not-to-exceed cap splits the risk: bill day work as normal, but agree upfront that the total will not exceed a stated ceiling (set using the Step 3 risk-adjusted figure). The tradesperson keeps the upside of finishing early, the customer gets the downside protection of a cap — a smaller premium is justified than full fixed price because the tradesperson isn't absorbing unlimited overrun risk.
Step 6 — Document the choice and the variation process
State clearly in writing which model applies, using the correct legal term (quote for a binding fixed price, estimate for a non-binding day-work projection — see quoting tips). For fixed-price work, agree in advance how discovered conditions will be handled: a documented variation, signed off before the extra work starts, not a verbal "that'll be more" after the event.
Frequently Asked Questions
Can I switch from day work to fixed price (or vice versa) partway through a job?
Yes, but only by agreement — if work started as an estimate (day work) and a clearer scope has since emerged, you can offer to convert the remainder to a fixed price once both parties understand the revised scope. Converting unilaterally, or after the fact, risks a dispute over which figure actually applies.
Isn't a fixed price always better for winning the job?
Not necessarily — a fixed price with a large risk premium baked in to cover genuine uncertainty can price you out of the job entirely, where an honest day-work quote (with a stated most-likely range) can win the work and still protect your margin. Customers generally respond well to transparency about why a job can't be fully fixed-priced, provided it's explained before work starts.
What happens if actual days run well over on a fixed-price job?
The tradesperson absorbs the shortfall unless the overrun is caused by a genuine, documented change in scope (discovered condition, customer-requested addition) that was agreed as a variation before the extra work was done. This is exactly why Step 1's honest uncertainty assessment matters — it determines whether fixed price was the right call in the first place.
Does VAT treatment differ between the two models?
No — VAT is applied the same way regardless of pricing model, based on the tradesperson's VAT registration status; see vat registration for tradespeople. State clearly whether the day rate or fixed price quoted is inclusive or exclusive of VAT.
How do I estimate the risk premium if I've never tracked this before?
Start with the 10-20% range for typical domestic jobs with moderate uncertainty, then track actual-vs-quoted outcomes over several jobs of a similar type. If fixed-price jobs of a certain type consistently overrun, raise the premium for that job type (or move it to day work) rather than guessing again on the next one.
Regulations & Standards
No statutory formula governs this calculation — choosing between day work and fixed price, and setting any risk premium, is a commercial pricing decision, not a regulatory requirement
Consumer Rights Act 2015 — requires pricing information given to consumers to be clear and not misleading, including whether a figure is fixed or time-based
Consumer Contracts Regulations 2013 — may apply additional information requirements where a quote or estimate is given at a distance (phone, online) rather than in person
Citizens Advice — Pricing and quotes for tradespeople — consumer-facing guidance on the legal difference between a quote and an estimate
Federation of Master Builders — Pricing and estimating guidance — trade body guidance on choosing between pricing models
Which? — Quotes, estimates and invoices explained — consumer-facing explanation of quote vs estimate obligations
pricing guide — comparison of cost-plus, fixed price, day rate and value-based pricing models
pricing labour — breakeven day rate methodology used to calculate the expected cost in Step 2
day rate to hourly rate calculator — converting a day rate to an hourly rate for short jobs
quoting tips — the legal distinction between a binding quote and a non-binding estimate
cis deduction calculator — CIS deduction treatment, unaffected by which pricing model is used