Summary
The outer leaf of a cavity wall is not waterproof. In driving rain, water passes through the bricks and mortar and runs down the inside face of the outer leaf. That is by design: the cavity is a drainage gap. The problem comes wherever something crosses the cavity, such as a lintel, a window head, a meter box or an extension roof. Without a tray, water collects on top of the bridge and runs across it to the inner leaf, showing up as damp patches above windows, staining at ceiling level and wet plaster around meter boxes.
The cavity tray intercepts that water and steers it outward, and the weep holes let it out of the wall. Both must be present and both must work: a tray without weeps fills up and overflows at the ends; weeps without a tray behind them let nothing out.
Most cavity tray defects are not design failures. They are site failures: stop ends missing, trays not lapped, mortar droppings blocking the tray, weeps rendered over, or trays omitted altogether because the steel lintel "has its own". Building control inspectors, warranty surveyors and damp surveyors all look for them. Getting them right costs very little at the time and is very expensive to fix afterwards, because the outer leaf has to come out.
Key Facts
- Purpose — collect water running down the inner face of the outer leaf and discharge it outward through weep holes.
- Where required — over lintels and openings, over cavity bridges (meter boxes, ducts, sleeves, beams), at roof abutments, above cavity barriers where required, and at the base of the cavity in some details.
- Rise across the cavity — typically at least 150 mm from the outer leaf up to the inner leaf, so water falls outward.
- Extent — a tray over an opening normally extends at least 150 mm beyond each end of the lintel.
- Stop ends — required at each end of a tray that does not run the full length of the wall, so water cannot run off the end into the cavity.
- Weep hole spacing — Approved Document C: maximum 900 mm centres, at least two per tray over an opening; NHBC-referenced guidance and many manufacturers specify 450 mm centres.
- Weep position — in the perpend (vertical joint) of the outer leaf directly above the tray, at the lowest point.
- Laps — joints in trays lapped at least 100 mm and sealed, or use preformed jointing pieces.
- Base of cavity — the cavity should extend at least 225 mm below the lowest DPC so water collecting at the base stays below floor level.
- DPC height — the outer leaf DPC should be at least 150 mm above finished external ground level.
- Steel lintels — insulated steel lintels with an integral profile still usually need a separate cavity tray in severe exposure and where the manufacturer requires one.
- Materials — polymer or polyethylene DPC to BS EN 14909, preformed plastic trays, or lead in some roof abutment details.
- Exposure — the more exposed the elevation, the more important full trays, stop ends and close weep spacing become.
Quick Reference Table
Spending too long on quotes? squote turns a 2-minute voice recording into a professional quote.
Try squote free →| Location | Tray needed? | Weep holes | Key detail |
|---|---|---|---|
| Over window or door lintel | Yes | At least 2, max 900 mm centres (450 mm NHBC) | Stop ends, 150 mm past each lintel end |
| Over a long lintel (garage door) | Yes, continuous | Max 900 mm centres along length | Lap joints 100 mm, sealed |
| Over meter box | Yes | At least 2 | Box is a cavity bridge |
| Above telescopic air brick sleeve | Yes in exposed areas | At least 1–2 | Short tray with stop ends |
| Lean-to roof abutting cavity wall | Stepped cavity trays | Weep in each tray or lowest tray as detailed | Coordinate with lead flashings |
| Flat roof abutting cavity wall | Continuous tray | Max 900 mm centres | 150 mm above roof finish |
| Base of wall at DPC | Depends on detail | Often weeps at ground DPC on warranty jobs | 225 mm cavity below DPC |
| Cavity barrier / fire stop | Where required by design | As detailed | Avoid trapping water on barrier |
| Movement joint | Tray continuous or sealed | As detailed | Avoid tray stopping at joint |
Detailed Guidance
How a tray works
Picture water running down the inside face of the outer leaf. When it reaches a lintel, it needs to be caught and steered outward. The tray is laid on the outer leaf brickwork at the bed joint above the lintel, runs across the cavity sloping upward, and is built into the inner leaf a course or two higher. Water landing on it runs down the slope to the outer leaf, where weep holes let it drain out.
Rules that make it work:
- The slope must fall outward. A tray that is flat or falls inward sends water to the inner leaf.
- Stop ends must turn up at both ends. Otherwise water runs off the end of the tray and back into the cavity, often to the window reveal.
- The tray must be continuous over the opening. Joints are lapped and sealed, or preformed corner and junction pieces used.
- The weep must line up with the tray. A weep one course too high drains nothing.
Forming a site-made tray over a lintel
- Build the outer leaf to the course above the lintel.
- Lay the DPC tray on a mortar bed on the outer leaf, extending at least 150 mm beyond each end of the lintel.
- Take it up across the cavity to the inner leaf, keeping the rise at least 150 mm, and bed it into the inner leaf joint.
- Form or fit stop ends at both ends: preformed stop ends are faster and more reliable than folded DPC.
- Lap any joints at least 100 mm and seal.
- Fit weep vents in the perpends directly above the tray: at least two over each opening, at the spacing in the specification.
- Keep the tray clean: use a cavity batten or board to catch mortar droppings and remove it as you go.
LABC guidance specifically warns about mortar droppings bridging trays and weeps being blocked or rendered over.
Steel lintels and integral trays
Many steel lintels are shaped so the outer flange acts like a tray, and manufacturers state where an additional DPC tray is or is not needed. As a rule of thumb:
- In sheltered and moderate exposure, follow the lintel manufacturer's instructions; some allow the lintel to act as the tray with weeps above.
- In severe and very severe exposure, and on warranty work, a separate cavity tray over the lintel is commonly required.
- Where the lintel is shorter than the tray needs to be, or the tray must run past jambs, fit a separate tray.
Check lintel types for lintel selection.
Roof abutments and stepped trays
Where a lean-to or pitched roof meets a cavity wall below the eaves of the main building, the outer leaf above the roof line sends water down inside the cavity onto the roof junction. Stepped cavity trays, a series of short trays following the slope of the roof, each with a stop end, catch it and discharge it over the flashing.
Key points:
- Use preformed stepped cavity trays matched to the roof pitch and brick course.
- Each tray discharges over the lead flashing or apron, never behind it.
- Fit a weep in the lowest tray, and in each tray where the manufacturer requires.
- A retrofit roof against an existing cavity wall needs trays cut in; this is skilled work and needs propping of the outer leaf in short lengths.
For flat roofs abutting a cavity wall, a continuous tray at least 150 mm above the finished roof surface, with weeps at the design spacing, is normal.
Common defects and how to spot them
| Symptom | Likely cause | Fix |
|---|---|---|
| Damp patch above window head | Tray missing, no stop ends or blocked | Open up outer leaf above opening, fit tray and stop ends |
| Damp at window reveal corner | Tray stops short of jamb | Extend tray past lintel end with stop end |
| Water staining below meter box | No tray over box | Fit tray over box |
| Damp at ceiling where extension roof meets wall | Stepped trays missing or discharging behind flashing | Cut in stepped trays |
| Weeps blocked or rendered over | Poor finishing | Clear weeps, fit vents |
| Wet cavity fill insulation above lintel | Mortar on tray bridging | Clear and reform |
Before blaming a tray, rule out other causes such as defective window seals, condensation or failed pointing. See condensation vs leak diagnosis.
Weep hole types
- Open perpend — leave the perpend empty of mortar; simple but lets insects in and looks untidy.
- Plastic weep vent — fits in the perpend, colour-matched to mortar, with a baffle against wind-driven rain and insects.
- Cavity weep with upstand — extends up the cavity to drain the tray even if mortar droppings collect.
Weeps must stay open. Do not render, point or paint over them, and keep landscaping and paving below them.
Frequently Asked Questions
How many weep holes do I need over a window?
At least two over each opening, at no more than 900 mm centres under Approved Document C, or 450 mm where your warranty provider or the tray manufacturer specifies it. A wide patio door or garage door lintel needs more along its length.
Do steel lintels need a separate cavity tray?
Sometimes. In sheltered or moderate exposure, the lintel manufacturer may allow the lintel to act as the tray. In severe exposure and on most warranty work, a separate tray with stop ends is normally required. Always check the manufacturer's data sheet and the warranty provider's standard.
Can I fit a cavity tray to an existing wall?
Yes, but it means removing the outer leaf above the opening or junction in short sections, fitting the tray and rebuilding. Prop or support the brickwork above, work in lengths of no more than about 1 m at a time, and match the bricks and mortar.
Are weep holes needed at ground level?
Not always. Weeps at the base of the cavity, at the DPC, are standard in many specifications and on warranty jobs, and are good practice with partial-fill insulation. Check the specification and the warranty standard.
What happens if the stop ends are missed?
Water collected by the tray runs off the end into the cavity, frequently tracking along the cavity closer into the window reveal. It is one of the most common causes of damp at the top corners of windows in newer homes.
Regulations & Standards
Building Regulations 2010, Part C — resistance to contaminants and moisture; Approved Document C Section 5 covers cavity walls, cavity trays and weep holes.
PD 6697:2019 — recommendations for the design of masonry structures to BS EN 1996-1-1 and BS EN 1996-2, including damp proof courses and cavity trays.
BS EN 1996-2 — Eurocode 6, design, selection of materials and execution of masonry.
BS EN 14909 — flexible sheets for waterproofing, plastic and rubber damp proof courses.
NHBC Standards, Chapter 6.1 — external masonry walls, including cavity tray and weep hole requirements for warranty work.
LABC Warranty Technical Manual — cavity trays and weep holes for warranty work.
GOV.UK — Approved Document C: site preparation and resistance to contaminants and moisture — official guidance
LABC — Installing site-formed cavity trays — practical guidance and common faults
LABC Warranty — Cavity trays and reveal closers — warranty requirements
NHBC Standards — Chapter 6.1 external masonry walls
Premier Guarantee — Cavity trays and reveal closers technical update — warranty detailing
damp proof course — DPC heights and materials at the base of the wall
lintel types — choosing lintels and how they interact with trays
cavity wall ties — tie spacing and keeping ties clean of mortar
condensation vs leak diagnosis — ruling out other causes of damp around openings
air bricks and underfloor ventilation — trays over telescopic vents