Building Regs Part P and Solar PV: Notifiable Work, Competent Persons Scheme Registration and Self-Certification

Quick Answer: Solar PV installation is notifiable work under Building Regulations Part P (England) because it involves the installation of a new circuit connected to the consumer unit. An MCS-certified installer who is registered with an approved Part P Competent Persons Scheme (NICEIC, NAPIT, Stroma, etc.) can self-certify the work without involving the local authority building control. The installer issues an Electrical Installation Certificate (EIC) and the Competent Persons Scheme notifies building control automatically. Without scheme registration, a building control application must be made before work starts.

Summary

Building Regulations Part P (Electrical Safety — Dwellings) requires that certain electrical work in domestic premises is either carried out by a registered competent person (who self-certifies) or is subject to a building control application. Solar PV installation involves the addition of a new circuit from the AC side of the inverter to the consumer unit, which is notifiable work under Part P.

For solar PV installers, the practical message is: if you are registered with an approved Competent Persons Scheme, you can self-certify the electrical work as part of the MCS commissioning process. If you are not registered, you need a building control application — which costs money, takes time, and involves a building control officer inspecting the work.

MCS certification and Part P registration are separate. Being MCS-certified does not automatically make you Part P registered; you must hold both to self-certify a solar PV installation.

Key Facts

Quick Reference Table: Part P Compliance Routes for Solar PV

Spending too long on quotes? squote turns a 2-minute voice recording into a professional quote.

Try squote free →
Installer Status Compliance Route Process
MCS-certified + CPS-registered (Part P) Self-certification Install; issue EIC; CPS notifies building control; EIC to customer
MCS-certified only (no Part P) Building control application Apply to LABC before works; LABC inspects; completion certificate issued by LABC
Subcontracting electrical work Use a Part P registered electrical subcontractor Subcontractor issues EIC; their CPS notifies building control
Existing installation work only (no new circuit) May not be notifiable Replacing panels on existing circuits is generally not notifiable; adding new circuit always is

Detailed Guidance

What Part P Requires for Solar PV

Solar PV installation work that is notifiable under Part P includes:

The DC wiring (panels to combiner box to inverter) is not separately notifiable under Part P but must comply with BS 7671 Chapters 4, 5, and 7 (particularly Section 712: photovoltaic power supply systems).

What Part P does not cover:

Self-Certification Process

Where the installer holds both MCS certification and CPS registration:

Step 1: Complete the installation Install the solar PV system in compliance with MCS 012 technical requirements, BS 7671 (Chapter 712 and relevant sections), and the Part P requirements for the electrical installation.

Step 2: Test and commission Test the electrical installation:

Step 3: Issue the EIC Complete the Electrical Installation Certificate for the new circuit. The EIC must include:

Step 4: CPS notification Log the job in the Competent Persons Scheme portal and submit the notification. The CPS notifies the local authority building control on the installer's behalf. This triggers the issuance of a building regulations compliance certificate (completion certificate) from the LABC, which is posted to the homeowner.

Step 5: Handover documentation Provide the customer with:

Building Control Application Route

Where the installer is not CPS-registered:

Before works commence: Submit a full plans application to the local authority building control (LABC) or an approved inspector. The application includes:

During works: The building control officer may attend site to inspect the work. Alternatively, a completion inspection is arranged after the work is finished.

After completion: The LABC issues a completion certificate confirming compliance with building regulations. This is the equivalent of the CPS-issued completion certificate.

Implications: The building control route adds cost (application fee + potential inspection) and time (application processing may take 1–3 weeks). It also involves a third party verifying the work, which can create delays if the officer requests changes. For commercial installers doing any volume of domestic solar PV work, CPS registration is strongly recommended.

Obtaining Part P Registration

For an existing MCS-certified solar PV installer without Part P registration:

The main approved CPS schemes for electrical work are NICEIC and NAPIT. Many solar installers already use NAPIT for MCS; NAPIT also offers Part P electrical registration as a separate (or bundled) service.

The assessment for Part P registration involves:

For an MCS-certified installer with solar PV qualifications who also holds an IEE/C&G electrical qualification, adding Part P registration is typically a straightforward assessment process.

Wales, Scotland, and Northern Ireland

Wales: Wales has its own building regulations (Building Regulations 2010 (Wales)) with a Part P equivalent. The Competent Persons Scheme route applies similarly.

Scotland: Scotland has Building Standards (Technical Handbooks, not Parts A–P). Electrical installations in Scotland must comply with Building Standards System and BS 7671, but the Part P CPS framework does not apply. Electrical work in Scotland is self-certified by the installer using an EIC; building control notification may be required for notifiable works under the Scottish system.

Northern Ireland: Northern Ireland has its own Building Regulations and Competent Persons Scheme arrangements. Confirm locally.

Frequently Asked Questions

If I'm replacing old solar panels (like-for-like), is that notifiable under Part P?

Replacing panels on an existing generation circuit with like-for-like panels, without modifying the circuit or consumer unit connection, is generally not notifiable under Part P. However, if you replace the inverter (which may require reconnecting to the consumer unit) or add a new circuit, that work is notifiable. Check the Competent Persons Scheme guidance if uncertain.

Does solar PV on a commercial property need Part P certification?

No. Part P applies only to domestic premises (dwellings). Solar PV on a commercial or industrial roof is governed by BS 7671 and MCS (for SEG eligibility) but not by Part P. Building Regulations may apply for structural changes (Part A), and planning permission may be required.

What if I'm a roofer installing the panels but not the electrical work — do I need Part P?

The panel mounting and DC wiring is not separately notifiable under Part P. The notifiable work is the AC connection to the consumer unit. If you are only doing the mechanical and DC side, and a registered electrician is doing the AC connection, only the electrician needs to be Part P registered. Ensure there is a clear demarcation agreed in writing.