Drain Testing: Air Test, Water Test & CCTV Survey Procedures

Quick Answer: New above-ground drainage must be air tested to 38mm water gauge pressure, held for 3 minutes without pressure loss exceeding 6mm water gauge (BS EN 1329 / Approved Document H). Below-ground drainage should be tested with water to 1.5m head (300mm above the invert of the top of the drain run), held for 2 hours — any visible loss of water level indicates a failed joint or damaged pipe.

Summary

Drain testing is required at the end of new drainage installation to confirm the system is watertight before it is covered over or connected to the building. It is a Building Control inspection stage item for drainage covered by Approved Document H — the inspector may wish to witness the test, or accept a signed test certificate from the installer.

Testing methods differ for above-ground and below-ground drainage. Air testing is faster and uses simpler equipment; water testing is the traditional method and gives a clear visible result. CCTV surveying is used for existing drain systems to identify blockages, root intrusion, joint failures, collapsed pipes, and incorrect gradients — it is not a pressure test but a visual inspection.

Understanding when and how to test drainage is important not just for compliance, but for your own protection — a drain system that passes a test before backfill or burial means you have documentary evidence of a sound installation if problems arise later.

Key Facts

Quick Reference Table

Need to quote a plumbing job? squote generates accurate quotes from a voice recording.

Try squote free →
Test Type System Pressure/Head Duration Pass Criterion
Air test Above-ground drainage 38mm wg 3 minutes ≤6mm wg pressure drop
Water test Below-ground drainage 1.5m head above invert 2 hours No visible level drop
Smoke test Above-ground drainage Low pressure Visual observation No smoke at joints
CCTV survey Existing drainage N/A (visual only) N/A Report grade per MSCC4
Drain Size Max Distance Between Inspection Points
100mm 45m
150mm 45m
225mm+ 90m

Detailed Guidance

Above-Ground Air Test — Procedure

Equipment needed:

Procedure:

  1. Insert test plugs into all open ends of the drainage stack: both ends of each horizontal branch, the base of the stack (at the rodding point), and the top of the stack. Leave one connection accessible for the manometer.
  2. Connect the manometer to the stack via the open connection.
  3. Pump air into the system until the manometer reads 38mm water gauge. Close the pump valve.
  4. Observe the manometer for 3 minutes.
  5. Any loss must not exceed 6mm wg. If the pressure drops more than 6mm, the test fails.

Locating a failed joint:

Common failures:

Below-Ground Water Test — Procedure

Equipment needed:

Procedure:

  1. Close off the downstream end with an inflatable plug seated in the drain at the lowest inspection chamber.
  2. Fill the drain run with water from above, working upstream until the run is full to 1.5m head above the invert at the highest point.
  3. Allow 30 minutes for initial absorption into the pipe joints and walls (vitrified clay and concrete absorb some water initially; HDPE and PVC less so).
  4. Top up to the required level after the absorption period.
  5. Mark the water level precisely (tape to the inspection chamber wall, or use a staff gauge).
  6. Observe for 2 hours. The level should not drop visibly.
  7. Record start and finish levels and temperature.

Acceptance: For PVC-U, HDPE, and vitrified clay, a small level drop may be acceptable within the BS EN 1610 tolerance: ≤ 0.05 litres per m² of internal wetted surface per 100m of pipe length — this is very small and usually imperceptible. Any visible drop at the scale of a normal domestic installation should prompt investigation.

Locating a failed joint below ground:

CCTV Survey — When and How

A CCTV drain survey is not a pressure test — it is a visual inspection of the inside of an existing drain run using a wheeled camera head passed through from an access point.

When to use CCTV:

CCTV survey output:

A Grade 3–5 finding on a CCTV survey typically indicates the drain needs repair or lining. Drain lining (CIPP — cured-in-place pipe) can repair structural defects without excavation.

Smoke Testing for Leak Detection

Smoke testing is an alternative to air testing for above-ground drainage, or can be used in conjunction with CCTV for below-ground drainage venting checks. Non-toxic smoke is introduced at low pressure through a specialist machine.

Applications:

Smoke testing above-ground: Connect smoke machine at cleanout access point; plug all fixtures (block all traps or fill with water); apply smoke at low pressure; walk through building looking for smoke at light fittings, floor boards, around pipe penetrations.

Frequently Asked Questions

Does Building Control need to witness drain tests?

Yes, typically. Drainage is an inspection stage item under Part H. The BCO (Building Control Officer) or Approved Inspector should be notified before you backfill or cover drainage. In practice, many inspectors accept a signed test record rather than attending in person — confirm this in advance. If the inspector doesn't attend and problems arise later, a signed test certificate from the installer is your evidence of compliance.

Can I use air testing for below-ground drainage?

Yes, as an alternative to water testing. For below-ground drainage, the test pressure is the same (38mm wg for PVC-U and similar). Air testing is faster and easier to set up than filling a drain run with water, but it is harder to identify where a leak is occurring. For short, simple drain runs, it's a practical choice; for complex networks, water testing gives a more definitive result.

What is the gradient for a 100mm foul drain?

Approved Document H Table 1: the recommended gradient for a 100mm foul drain is 1:40 (2.5%), which is self-cleansing and provides adequate flow velocity to prevent solids settling. The minimum is 1:80 for runs up to 3m where the gradient cannot be achieved. Steeper than 1:25 (4%) can cause the liquid to outrun the solids and should not be used without approval.

Regulations & Standards