CDM Regulations 2015 for Groundworks: Principal Designer, Notifiable Projects and Construction Phase Plans

Quick Answer: The Construction (Design and Management) Regulations 2015 (CDM 2015) apply to all construction work including groundworks. For notifiable projects (more than 30 working days with >20 simultaneous workers, or >500 person-days), the client must notify HSE, appoint a Principal Designer, and a Principal Contractor. Every project needs a Construction Phase Plan before groundwork commences. The most common groundworks CDM failures are inadequate pre-construction hazard identification (utilities, contamination, unstable ground).

Summary

CDM 2015 replaced the 2007 Regulations and significantly changed how health and safety is managed on construction projects. For groundworks specifically, CDM introduces requirements at three stages: pre-construction (identifying hazards and producing pre-construction information), during construction (Construction Phase Plan, site health and safety management), and post-construction (health and safety file).

Groundworks carry some of the highest CDM risk areas in construction: underground utilities, unstable excavations, buried contamination, proximity to existing structures, and heavy plant operations. A poorly prepared Construction Phase Plan that doesn't adequately address these risks is one of the most common compliance failures found by HSE when investigating groundworks accidents.

CDM 2015 applies to all construction work — not just large projects. A domestic extension (single client, domestic premises) has a simplified regime: some CDM client duties are transferred to the contractor. But the safety management duties — preparing a Construction Phase Plan, identifying hazards, providing a safe working environment — remain regardless.

Key Facts

Quick Reference Table: CDM 2015 Duty Holders and Groundworks Responsibilities

Spending too long on quotes? squote turns a 2-minute voice recording into a professional quote.

Try squote free →
Duty Holder Key CDM Responsibility for Groundworks
Client Commission ground investigation; gather pre-construction info; appoint PD and PC
Principal Designer Identify and eliminate/reduce groundworks hazards at design stage; manage pre-construction info
Principal Contractor Produce Construction Phase Plan; manage safety on site; coordinate sub-contractors
Groundworks Contractor Follow CPP; competent workforce; trained for groundworks hazards; safe method statements
Designer (e.g. structural engineer) Design foundations to avoid/reduce hazards; consider buildability and CDM

Detailed Guidance

Pre-Construction Information for Groundworks

The Principal Designer is responsible for gathering pre-construction information. For groundworks this must include:

Utilities:

Ground conditions:

Contamination:

Adjacent structures:

Existing drainage and services in the ground:

All pre-construction information must be provided to the Principal Contractor before the Construction Phase Plan is produced.

The Construction Phase Plan for Groundworks

The Construction Phase Plan (CPP) is not a generic document — it must address the specific hazards and methods for the project. For groundworks, a compliant CPP includes:

1. Project description and key parties

2. Management arrangements

3. Groundworks-specific hazards and controls

Hazard Typical Control Measures
Underground utilities CAT/genny survey; hand-dig zone (500mm around services); permit to dig
Unstable excavations Risk assessment; trench support or battering; no entry without support ≥1.2m depth
Ground contamination PPE; waste classification; site decontamination procedures
Groundwater Dewatering plan; prevent groundwater from undermining foundations
Heavy plant interaction Exclusion zones; trained operators; banks man for reversing plant
Concrete delivery Vehicle management; PPE (alkali burns); COSHH assessment
Adjacent structures Monitoring; settlement surveys; notification to neighbours

4. Emergency procedures

5. Construction sequence

Proportionality: A domestic extension groundworks CPP can be a straightforward two to four page document addressing the specific hazards for that site. A city centre commercial development groundworks CPP for a basement excavation may run to 50+ pages. The content should be proportionate to the complexity and hazard level.

Notifiable Projects: When to Notify HSE

HSE must be notified on the F10 form when the construction phase is likely to exceed either threshold:

For groundworks: most domestic projects are not notifiable. A larger housing development, commercial project, or any project with significant programme duration is likely to be notifiable.

Online notification: Notify at hse.gov.uk/f10. The notification must be submitted by the Client before the construction phase begins. The F10 summary should be displayed on the site notice board.

Changes during construction: If the project scope changes and it becomes notifiable when it wasn't previously, the Client must notify HSE at that point.

Utility Strikes: The Most Common Groundworks CDM Failure

Utility strikes (hitting buried gas, electricity, water, or telecoms services) during groundworks are one of the most frequent serious incidents on construction sites. CDM 2015 requires the hazard to be identified and managed. The HSE's guidance "Avoiding danger from underground services" (HSG47) sets out the required approach:

  1. Plan — obtain all available utility records; interpret on a site plan
  2. Locate — use a CAT (cable avoidance tool) and signal generator (genny) to confirm routes on site; 'genny' injects a signal onto a pipe or cable which the CAT detects
  3. Avoid — design excavations to avoid utilities where possible; plan excavation routes
  4. Safe excavation — within 500mm of a utility service line, hand-dig only; no mechanical excavation
  5. Response — if a service is struck: gas leak → evacuate and call National Gas Emergency (0800 111 999); electricity strike → do not touch; move everyone clear; call 999 and the electricity network operator

A permit to dig (sometimes called a ground disturbance permit) is good practice and is required on many managed sites. It confirms that utility checks have been completed and that safe excavation procedures are in place.

Health and Safety File for Groundworks

At project completion, the Principal Designer prepares the Health and Safety File. For groundworks it must include:

The Health and Safety File is handed to the Client on project completion and must be retained for the life of the building. It provides essential information for any future works — renovation, extension, underpinning — that may affect the foundations or buried services.

Frequently Asked Questions

Does CDM apply to a self-build extension with one contractor?

Yes, CDM applies to all construction work. On a domestic project with a single contractor, the domestic client's duties are transferred to the contractor (Regulation 7). The contractor must prepare the Construction Phase Plan before starting and is responsible for managing H&S on site. The Project Designer duties also transfer in this scenario unless a separate designer is appointed.

Who appoints the Principal Designer on a groundworks project?

The Client appoints the Principal Designer. For most projects where an architect or structural engineer is designing the building, they will typically fulfil the Principal Designer role (with explicit appointment and acceptance of the duty). On groundworks-only contracts (e.g. a groundworks package on a larger development), the Principal Designer is typically appointed at the overall project level, not separately for the groundworks phase.

Is a method statement the same as a Construction Phase Plan?

No. A method statement describes how a specific operation will be carried out safely (e.g. how a trench will be excavated and supported). The Construction Phase Plan is the overarching health and safety management plan for the entire construction phase. Method statements are an important part of demonstrating how risks identified in the CPP will be controlled, but they are not the CPP itself.

What happens if groundworks start without a Construction Phase Plan?

Starting work without a CPP is a breach of CDM 2015 Regulation 12. HSE can issue a Prohibition Notice stopping work, or an Improvement Notice requiring a CPP to be produced. For notifiable projects where HSE has not been notified, the same enforcement applies. The Client, Principal Contractor, and individual contractors can all be prosecuted for CDM breaches.

Regulations & Standards