Summary

The Workplace Charging Scheme is the commercial-premises sibling of the domestic EV Chargepoint Grant, and is the main funding route for a business, charity, school, or public sector body wanting to install EV charging for staff, fleet, or visitor vehicles at its own site. Unlike the domestic grant — which now mostly applies only to flats and rental properties — WCS remains broadly available to any eligible organisation with suitable off-street parking, which makes it one of the more commercially relevant EV grants for installers to understand and quote accurately.

The scheme rate changed materially in 2026: the per-socket cap rose from £350 to £500 from 1 April 2026, while the 75% cost-coverage rule and the 40-socket cap per applicant stayed the same. This means a business installing, say, 10 sockets at £2,000 each (£20,000 total) could previously claim up to £3,500 (10 × £350) and can now claim up to £5,000 (10 × £500), subject to the 75%-of-cost ceiling still applying per socket. Because this is exactly the kind of detail that changes between funding rounds, always verify the live rate on the gov.uk guidance page immediately before quoting — do not rely on a figure quoted from memory or from an older customer conversation.

For tradespeople, the practical value of WCS is that it's a genuine, non-repayable grant (not a loan), it's claimed by the OZEV-authorised installer on the customer's behalf as part of the job (not by the customer separately), and it directly reduces what the customer pays at the point of invoicing — making it a strong selling point for commercial EV charging quotes, provided the eligibility criteria are checked properly before the customer is promised a figure.

Key Facts

Quick Reference Table

Spending too long on quotes? squote turns a 2-minute voice recording into a professional quote.

Try squote free →
Parameter Detail
Grant per socket Up to £500 (from 1 April 2026; was £350 previously)
Coverage Up to 75% of total purchase + installation cost (inc. VAT)
Maximum sockets per applicant 40, across all sites combined
Maximum total grant £20,000 (40 × £500), cost-dependent
Scheme end date 31 March 2027 ****
Eligible applicant types Businesses, charities, public sector organisations
Geographic coverage England, Wales, Scotland, Northern Ireland
Parking requirement Dedicated off-street parking, staff/fleet designated
Landlord consent Required if applicant does not own the site
Installer requirement OZEV-authorised installer only
Chargepoint requirement OZEV-approved model, Smart Charge Points Regulations 2021 compliant
Minimum warranty 3 years, parts and installation
Applicable standards BS EN 61851, BS 7671
Voucher validity Typically 180 days from issue ****

Detailed Guidance

Checking Eligibility Before Quoting

The most common source of a failed WCS claim is quoting a job before confirming the customer genuinely meets the off-street parking and land ownership/consent requirements. Before including a WCS figure in a quote:

  1. Confirm the parking is dedicated to the applicant's premises and not shared public or on-street parking
  2. Confirm whether the applicant owns the site outright or is a tenant — if a tenant, landlord permission must be obtained and documented before or alongside the application, not assumed
  3. Confirm the applicant hasn't already claimed the full 40-socket allowance across other sites — the cap is per applicant, not per site, so a multi-site business needs to track this centrally
  4. Confirm the intended chargepoint model is on the current OZEV-approved list before specifying it in the quote — an otherwise suitable charger that isn't OZEV-approved cannot be claimed against

The Application and Claim Sequence

WCS is applicant-led at the voucher stage and installer-led at the claim stage:

1. Applicant (business/charity/public sector body) applies to OZEV
   for a WCS voucher, providing evidence of eligibility (parking,
   ownership/consent, organisation type)
        |
2. OZEV issues a voucher code, valid for a limited period
        |
3. Applicant selects an OZEV-authorised installer and provides
   the voucher code
        |
4. Installer verifies the voucher via the OZEV installer portal
   BEFORE starting work
        |
5. Installation carried out to BS EN 61851 / BS 7671, using an
   OZEV-approved, Smart Charge Points Regulations-compliant
   chargepoint
        |
6. Grant amount deducted from the customer's invoice at point
   of billing (customer pays net of grant)
        |
7. Installer claims the grant back from OZEV via the portal,
   submitting chargepoint photographs, serial numbers, and
   installation evidence
        |
8. OZEV processes the claim (a confirmation period typically
   applies) and pays the installer

Because the installer, not the customer, makes the final claim, it is the installer's responsibility to keep the paperwork trail (voucher verification, photographs, serial numbers, EIC) complete and in order — an incomplete claim can delay or forfeit payment even after the work is done.

Combining WCS With Other Funding

Larger commercial sites — fleet depots, multi-storey car parks, retail sites planning many future chargepoints — often need supply capacity and distribution infrastructure well beyond what a per-socket chargepoint grant covers. In these cases, the site's electrical infrastructure upgrade (new distribution board, additional cabling routes, sometimes a DNO supply reinforcement) may be eligible for the separate EV Infrastructure Grant rather than WCS, which covers the chargepoints themselves. Treat these as two separate funding conversations with the customer — see ev charging commercial premises for the wider commercial installation context, including load assessment and DNO application requirements for multi-chargepoint sites.

Common Mistakes When Quoting WCS Work

Frequently Asked Questions

Can a sole trader or home-based business claim WCS?

Some home-based enterprises can qualify under specific criteria, but this is a narrower case than a standard business premises application — check the current gov.uk guidance for the specific evidence required (registered business address matching the installation address, and confirmation the parking is used for business purposes) before assuming eligibility.

Does WCS cover chargepoints installed at employees' homes for a company car scheme?

That is generally a different funding route — home chargepoint installations for employees typically fall under different eligibility rules than the workplace-premises WCS scheme covered here, often requiring an evidence letter from the employer confirming the employee's role and permission to install. Do not conflate this with a standard WCS application for chargepoints at the business's own site — confirm which specific scheme applies to the customer's actual situation before quoting.

What happens if the WCS scheme closes before a project is finished?

Because the current scheme end date (31 March 2027) has already been extended once, and grant rates have changed mid-scheme before, any project timeline that depends on the grant being available should build in a buffer and confirm the voucher has been issued and is still valid before committing to a fixed completion date. A voucher issued and verified before the scheme closes should still be honourable per its terms, but do not assume a customer who hasn't yet applied will definitely be able to under the same terms later in the scheme's life.

Is the grant paid to the customer or the installer?

The grant is deducted from the customer's invoice at the point of billing, so the customer only pays the net amount — but the installer is the one who claims the grant back from OZEV afterwards. This means the installer effectively finances the grant amount between invoicing and OZEV's payment, which should be factored into cash flow planning on larger multi-socket jobs.