Heat Pump Electrical Connections: Circuit Sizing, DNO Notifications and Smart Controls

Quick Answer: Most domestic air source heat pumps (ASHP) up to 12kW run on single-phase 230V with a dedicated 20–32A circuit using 6mm² T&E cable. Systems above 3.68kW export capacity require prior G99 DNO notification. MCS installer certification is mandatory to claim the Boiler Upgrade Scheme (BUS) grant. The installation is notifiable under Building Regulations Part P.

Summary

Air source heat pumps are one of the fastest-growing heating technologies in the UK, driven by the Government's Boiler Upgrade Scheme grant (currently £7,500) and the Future Homes Standard mandate for low-carbon heating in new builds. The electrical installation for an ASHP is more demanding than for a gas boiler — it requires a dedicated circuit, correct cable sizing, an accessible outdoor isolator, and in most cases either G98 or G99 DNO notification.

For tradespeople, the critical issue is that heat pump installations sit at the intersection of electrical and plumbing disciplines. The electrical circuit sizing, control wiring (OpenTherm, on/off, or smart thermostat), and integration with immersion heater backup must all be correctly executed. Errors in circuit sizing cause nuisance tripping; errors in control wiring cause the system to run inefficiently, consuming far more electricity than it should.

This article covers all aspects of heat pump electrical installation — from cable sizing and consumer unit changes through to DNO notifications and smart control integration. It is relevant to both the electrical contractor installing the circuit and the heat pump installer specifying the electrical requirements.

Key Facts

Quick Reference Table

Quoting an electrical job? Describe the work and squote handles the pricing.

Try squote free →
ASHP Rated Input Typical Running Current Cable Size MCB Size Notification
Up to 3.5kW 15A 4mm² T&E 16A G98 (post-install)
3.5–5.5kW 24A 6mm² T&E 32A G99 (pre-approval)
5.5–8kW 35A 10mm² T&E 40A G99
8–12kW 50A 16mm² T&E 50A G99
>12kW >52A Three-phase supply Three-phase MCB G99

Note: These are indicative. Always calculate from the manufacturer's rated input current and account for cable route length, grouping factors, and ambient temperature derating.

Detailed Guidance

Circuit Sizing Calculations

Cable sizing for ASHP follows BS 7671:2018 Table 4D5 (flat twin and earth thermoplastic cable) with derating factors applied:

  1. Design current (Ib) — take from manufacturer data sheet; typically the rated input current at maximum output
  2. Ambient temperature correction — if cable runs through a warm area (loft in summer), apply correction factor; standard tables assume 30°C ambient
  3. Grouping factor — if cable is run grouped with other cables, apply the grouping derating factor
  4. Overcurrent device selection — select MCB rated above design current but within the cable's current-carrying capacity

Example for a 6kW ASHP:

Important: Use Type C or Type D MCBs for heat pump circuits. ASHP compressors have high start-up inrush current (typically 3–6× running current) that can trip Type B MCBs.

DNO Notification: G99 for Most Domestic ASHP

Unlike battery storage (which is about export capacity), DNO notification for heat pumps is driven by the impact on the local distribution network. As of ENA ER G99:

In practice: Many DNOs have developed fast-track processes for standard ASHP G99 applications. Approval is routine for most domestic installations in established residential areas. Problems arise in rural areas with long, lightly-loaded LV lines.

MCS installers are required to handle the G99 application process as part of the MCS installation process. Electrical contractors installing the circuit after MCS approval can proceed on the basis of the MCS documentation.

Outdoor Isolator Requirements

An ASHP requires an emergency isolator accessible without entering the building:

The isolator must be on the load side of the main consumer unit MCB, not on the supply side. It is a service isolation point, not an overcurrent protection device.

If the ASHP is wall-mounted in a utility room, the isolator within the room may satisfy this requirement provided it is accessible without opening junction boxes or moving the unit.

OpenTherm vs On/Off Control

Heat pump efficiency is significantly affected by how the system is controlled:

On/Off control:

OpenTherm modulation:

OpenTherm wiring:

BUS grant requirement: The MCS inspection process checks that the heat pump is correctly installed including controls. OpenTherm or equivalent modulating control is not mandated by MCS but is required for optimal performance targets referenced in MCS guidance.

Immersion Heater Backup Circuit

Most ASHP installations include a hot water cylinder with an integral immersion heater element. This is used for:

  1. Legionella pasteurisation — heating to 60°C+ periodically (ASHP typically operates at 50–55°C max)
  2. Backup heating — if ASHP fails or ambient temperature is very low
  3. Emergency boost — rapid reheating in high-demand situations

The immersion heater is a separate electrical load (typically 3kW/13A) and requires:

This circuit must be separately notified under Part P from the ASHP circuit.

SMETS2 Smart Meter and Time-of-Use Tariffs

Most ASHP owners benefit materially from switching to a time-of-use electricity tariff:

Tariff Type Off-Peak Rate Peak Rate Notes
Economy 7 8–12p/kWh (7 hours overnight) 26–30p/kWh Simple; some suppliers
Agile Octopus 1–15p/kWh (varies half-hourly) Up to 35p/kWh Real-time pricing; best for smart systems
Cosy Octopus 10p/kWh (6 hours/day) 24p/kWh Specifically designed for heat pumps

Accessing these tariffs requires a SMETS2 smart meter, which communicates half-hourly consumption data to the supplier. SMETS1 meters (installed before 2019) cannot support all time-of-use tariffs.

Smart heat pump controls (Tado, Nest, Vaillant SensoCOMFORT with Smart home integration) can schedule heating operation to coincide with cheap overnight electricity — this is one of the most effective ways to reduce running cost.

Frequently Asked Questions

Does an ASHP installation require a new consumer unit?

Not necessarily, but it is common. If the existing consumer unit does not have a spare way with sufficient rating, or if it is a split-load unit with insufficient RCD-protected ways, a new consumer unit may be required. The additional load of the ASHP should also be checked against the incoming service fuse rating — older properties may have only 60A or 80A service fuses, while a modern ASHP may push total consumption above this.

Can a plumber do the ASHP electrical work?

No. Electrical work including new circuits and consumer unit modifications must be carried out by a Part P competent person. MCS installers who are not Part P registered must sub-contract the electrical work to a registered electrician. The Part P certificate must be issued before the MCS installation certificate can be completed.

How long does G99 approval take?

The standard G99 assessment period is 45 working days (approximately 9 calendar weeks). Some DNOs offer fast-track approval for standard domestic ASHP applications in 5–10 working days. If the application triggers a distribution reinforcement requirement, the timeline is indeterminate and costs can run to thousands of pounds — this must be flagged to the customer before proceeding.

What happens if G99 is not obtained?

Installing an ASHP without required G99 approval is a breach of the Electricity Supply Regulations and could invalidate the installation and home insurance. The DNO has the right to disconnect any equipment connected without approval. MCS certification will also be withheld, meaning the BUS grant cannot be claimed.

Is three-phase supply always needed for large heat pumps?

Not always. Some manufacturers offer single-phase versions of heat pumps up to 14–16kW rated output (with a lower input current due to higher efficiency). Always check the manufacturer's data sheet for the specific model. Installing a three-phase supply is a significant additional cost (typically £2,000–5,000+) and time burden; confirm the requirement before specifying.

Regulations & Standards