Soakaway Sizing and Design: BRE Digest 365, Percolation Testing and Part H

Quick Answer: A soakaway must be sized to discharge the design storm event into the ground within 24 hours. Use BRE Digest 365 percolation tests to measure soil infiltration rate (f, in m/s), then size the soakaway storage volume from V = A_d × i × D − A_b × f × 50 × D (BRE Digest 365 simplified). Minimum 5m from any building (Approved Document H3) and 2.5m from a boundary. For a typical 50m² roof on moderately draining soil (sandy clay, f = 5×10⁻⁶ m/s), expect a soakaway storage volume of around 1.0–1.5m³ — typically four 1m³ crates or a 1.5m × 1.5m × 1.5m granular pit.

Summary

A soakaway is an underground void that receives surface water — typically roof drainage from a domestic property — and allows it to infiltrate slowly into the surrounding subsoil. Where mains surface water sewers exist, Building Regulations Part H1/H3 specifies a discharge hierarchy: 1) infiltration to ground (soakaway); 2) discharge to watercourse; 3) discharge to surface water sewer; 4) combined sewer (last resort). Connection to a public surface water sewer requires Section 106 approval from the water authority and is now actively discouraged where ground infiltration is feasible. As a result, almost every new domestic surface water disposal — and most retrofits where capacity is added or roof areas extended — uses a soakaway as the primary route.

The single most common mistake on domestic projects is sizing the soakaway by guess or rule of thumb rather than to BRE Digest 365. A "small" 1m³ soakaway is acceptable for a porch or single garage roof but inadequate for a typical 75m² rear extension. Undersized soakaways back up, surcharge upstream gullies, and lead to localised flooding of patios, lawns and (worst case) the property's wall foundations. Conversely, oversized soakaways cost the customer money for no benefit.

Part H also requires soakaways to be sited away from buildings and boundaries to prevent water-saturated ground from undermining foundations or affecting neighbouring property. The 5m minimum distance from buildings is a simple rule that ignores soil type — on clay subsoils prone to seasonal shrinkage and swelling (Mercia Mudstone, Boulder Clay, London Clay), a soakaway closer than 7–10m can drive seasonal foundation movement. Always assess the geology before siting.

Key Facts

Quick Reference Table

Spending too long on quotes? squote turns a 2-minute voice recording into a professional quote.

Try squote free →
Catchment (roof area) Soil type Typical f (m/s) Soakaway storage required Typical crate quantity
30 m² Sandy gravel 1×10⁻⁴ 0.3 m³ 1 crate, granular surround
30 m² Sandy clay 5×10⁻⁶ 0.8 m³ 1 crate
50 m² Sandy gravel 1×10⁻⁴ 0.5 m³ 1 crate
50 m² Sandy clay 5×10⁻⁶ 1.2 m³ 2 crates
75 m² Sandy clay 5×10⁻⁶ 1.8 m³ 2–3 crates
100 m² Sandy clay 5×10⁻⁶ 2.4 m³ 3 crates
100 m² Silty clay 1×10⁻⁶ 4.5 m³ 5–6 crates
200 m² Sandy gravel 1×10⁻⁴ 2.0 m³ 2 crates
200 m² Silty clay 1×10⁻⁶ 9.0 m³ 9–12 crates

(All figures assume 1:10-year design storm, 15-minute duration, 35mm/h intensity for SE England — adjust for postcode rainfall via FEH or BRE rainfall maps.)

Detailed Guidance

Step 1 — Percolation testing per BRE Digest 365

The test must be done before designing the soakaway, not after. Three repeat tests in three separate trial pits, ideally during the wettest seasonal period (winter/early spring) to ensure the result represents the worst-case soil condition.

Trial pit construction:

  1. Excavate three pits at the proposed soakaway location, each 0.3m × 0.3m × 1.0m–3.0m deep — depth must match the proposed soakaway base level.
  2. Stand a graduated rule (or vertical scale) inside the pit.
  3. Fill the pit with clean water to a known level (typically 0.5–1.0m above the base).
  4. Measure the time for the water level to fall from 75% full to 25% full (the t_p75-25 time).
  5. Repeat — refill and re-test — at least three times per pit, take the longest of the three.
  6. Repeat in two more pits.

Calculate the infiltration rate for each pit:

f = (V_p75 - V_p25) / (a_p50 × t_p75-25)

where:

Use the lowest (worst) f value from the three pits for design.

Step 2 — Design storm rainfall depth

For a domestic soakaway, the typical design event is the 1 in 10-year, 15-minute storm. The total depth (mm) varies by location:

Location Typical 1:10 yr 15-min storm depth
South-east England 14 mm
Midlands 12 mm
North-west England 13 mm
Scotland (lowland) 11 mm

Convert mm to m by dividing by 1000. For SE England, the design storm is 0.014 m of rainfall in 0.25 hours (15 min) = 900 seconds.

For more accuracy use FEH (Flood Estimation Handbook) rainfall depth-duration-frequency data, or the BRE rainfall map in Digest 365.

Step 3 — Soakaway storage volume

The BRE Digest 365 simplified design equation is:

S = (A_d × i × D) - (a_s50 × f × D)

Where:

The first term is total rainfall volume on the catchment over the storm; the second is the amount infiltrated during the storm. The difference is the required storage.

Try multiple durations (15-min, 30-min, 60-min, 4-hour, 24-hour) and the critical duration is the one giving the largest S. Soakaway storage is sized for that worst-case.

Worked example — typical 75m² rear extension, sandy clay

S = (75 × 1.56×10⁻⁵ × 900) - (4.5 × 5×10⁻⁶ × 900) = 1.053 - 0.020 = 1.03 m³ storage required

A 1.5m³ granular pit (3.375m³ volume × 30% void ratio = 1.01m³ storage) is on the limit — try 1.8m × 1.5m × 1.5m pit (giving 1.21m³ storage), or two 1m³ crates (90% void ratio = 1.8m³ storage) which comfortably exceeds the design requirement.

Check 24h drain-down: at the start of drain-down the side area is the full a_s = 4 × 1.5 × 1.5 = 9 m². Initial outflow rate = 9 × 5×10⁻⁶ = 4.5×10⁻⁵ m³/s. To drain 1.03 m³ at this rate = 22,888s = 6.4 hours — within 24h target. Pass.

Step 4 — Geometry and construction

Granular pit (Victorian) construction:

  1. Excavate to the design depth, typically 1.5–2.5m deep with sides battered or shored per CDM.
  2. Wrap the void with non-woven geotextile (Terram 1000 grade or similar) — overlap edges by 300mm.
  3. Fill with clean, washed, angular 40–75mm crushed concrete or hard stone (NOT pea gravel — too small a void ratio and silts up).
  4. Inflow pipe (100mm or 150mm) terminates inside the geotextile, with a perforated section at the top of the granular fill.
  5. Inspection chamber upstream of the soakaway is required for Part H compliance.
  6. Top the soakaway with geotextile, then 300mm of cover soil to grass level (or to base of footing detail).

Modular crate construction:

  1. Excavate to the design depth — usually 1.2m deeper than the pipe invert level to allow crate height plus 150mm bedding.
  2. Lay 150mm of 20mm angular crushed stone as bedding; level and compacted.
  3. Wrap crates fully in non-woven geotextile (Terram 1000 or equivalent) — sealing all overlaps.
  4. Stack crates per manufacturer instructions; connect to inflow pipe via proprietary inspection cap.
  5. Backfill sides with 200mm of 20mm angular crushed stone before granular surround backfill.
  6. Cover with geotextile, then minimum 500mm of cover for non-trafficked area (1m for vehicle loading — and use trafficked-grade crates).

Step 5 — Siting (Part H3 compliance)

On clay subsoils with seasonal shrink-swell behaviour, increase the 5m distance to 7–10m where possible — saturated clay near foundations can drive seasonal heave/subsidence.

When a soakaway is not viable

Alternative discharge routes:

Frequently Asked Questions

Do I need a percolation test for a small porch soakaway?

Strictly per BRE Digest 365 — yes, even for small soakaways. In practice for porch and small garage roofs (<20m² catchment), a single test is acceptable, and many local Building Control surveyors accept a rule-of-thumb assumption (e.g. 1m³ soakaway for porches on suspected clay subsoil). Always do the test on bigger jobs — the cost is small relative to the risk of an undersized soakaway needing rebuilding.

Can I discharge a foul drain to a soakaway?

No. Soakaways accept surface water only. Foul drainage must connect to a foul sewer, septic tank or package treatment plant per the Environment Agency General Binding Rules. A combined sewer surcharge from foul into a soakaway is a serious public health risk.

What's the minimum depth a soakaway needs to be?

The soakaway top should be at least 500mm below ground level (for clear cover and frost protection). The minimum total depth is usually 1.2–1.5m — small shallow soakaways (under 1m deep) struggle to access sufficiently permeable subsoil under the topsoil and rooting zone. A soakaway in topsoil only is largely ineffective in a saturated rain event.

How long do soakaways last before needing replacement?

A well-designed and constructed soakaway with appropriate geotextile and clean angular fill should last 25–40 years. Failure modes are:

Modular crate soakaways with inspection caps allow periodic CCTV inspection and jetting maintenance — extending life beyond the granular-pit norm.

Does my insurer/mortgage care about soakaway siting?

If the soakaway is closer than 5m to a building, or if the property has experienced subsidence and the soakaway is suspected as a contributing factor — yes. Saturated ground around foundations is a known subsidence trigger. Conversely, well-sited soakaways are routinely accepted by insurers and lenders without comment. Document the design and percolation test in case of a future query.

Regulations & Standards